MPLADS report card · 18th Lok Sabha

Lavu Sri Krishna Devarayalu

Lok SabhaTDPNarasaraopet · Andhra Pradesh

MP score22/100507th of 542 in the 18th Lok Sabha
23rd of 25 from Andhra Pradesh
Also an MP in the 17th Lok Sabha Then: 98% utilisation, 70 works completed, score 77.
  • Works waiting for sanction

    89 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.

Allocated limit

₹17.40 Cr

Median ₹14.70 Cr

Fund utilisation

42%

₹7.36 Cr recommended · 131 works
Below median (76%)

Paid to vendors

₹24.0 L

1.4% of allocation
Below median (37%)

Works completed

1

0.8% of recommended
Below median (28%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP131 works

    ₹7.36 Cr · 42% of the ₹17.40 Cr allocated

  2. Sanctioned by the district42 works

    32% sanctioned · took 32 days on average (due within 45 days)

  3. Completed1 works

    ₹16.0 L final cost · 4.2 months from recommendation on average

89 works are still awaiting sanction, 89 of them for more than 45 days.

In plain words

What the numbers say

  • Recommended 131 works worth ₹7.36 Cr, a fund utilisation of 42%, higher than 8.1% of 18th Lok Sabha MPs.
  • The district has sanctioned 42 of them, taking 32 days on average.
  • ₹24.0 L has been paid to vendors, 1.4% of the allocation.
  • 1 works are complete, typically 4.2 months after recommendation.
  • The largest share of funds went to Sanitation & drainage.
  • Payments went to 4 vendors. The largest received 67%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 22/100: finishing works counts most

  1. Works completed 30%1Completed ÷ recommended works.
  2. Spending efficiency 20%67Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%42Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%0Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%1Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    Not enough data
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: ASHOK CONSTRUCTIONS, 67% of payments across 4 vendors.

District sanction speed

66/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%66Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

131 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Consturuction of CC Roads cum Drains from Ramalayam Temple to Ponnuri Venkateswarlu House 300 Mtrs

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305008

    ₹6.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of CC Drain from Yampongu Pedaswamy House to R&B Road

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305010

    ₹6.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Laying of Internal CC Roads with Drains

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305012

    ₹8.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of CC Roads & Drains from Sanka Thirupati Rao House to Ramulavari Temple

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305014

    ₹4.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of RCC Pipe Culverts in Donka Road

    Roads & bridgesConstruction of culverts and bridges· Palnadu· #305018

    ₹2.4 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of Side Drains from Sangana Kotireddy House upto Water Plant in Vadlamudivaripalem village H/o Rompicherla

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305028

    ₹4.8 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of CC Road with side Drains from Ch. Venkata Rao House to Anjaneya Swamy Statue in Karlakunta village

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305033

    ₹8.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of CC Roads in Internal Roads in Ravipadu village (Balaiah Nagar)

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305037

    ₹6.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of CC Roads from Poleramma Temple to Burial Ground

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305040

    ₹6.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of CC Road with side Drains from Narasaraopet- Chilakaluripet R&B Road to Bathina Nageswarao Site in Kesanupalle village

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305041

    ₹8.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of CC Roads with Side Drains and culverts from Ch.Parameswara Rao house to Ramisetty Kotaiah & Krishna Rao site

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305044

    ₹4.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Providing Internal CC Roads with Drains in Lakshmipuram village

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305046

    ₹6.4 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Construction of RCC Pipe Culverts on the road from Nekarikallu Village to Poleramma Temple

    Roads & bridgesConstruction of culverts and bridges· Palnadu· #305049

    ₹2.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Providing Internal CC Roads in Bhumayapalem

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305228

    ₹4.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026
  • Providing Internal CC Roads and Side Drains

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Palnadu· #305234

    ₹8.0 L Awaiting sanction · 75 daysRec. 18 Aug 2026

18th Lok Sabha MPs from Andhra Pradesh

Ranked by MP score

Compare
#MPUtilisationSpentCompletedScore
1Prabhakar Reddy Vemireddy · Nellore96%56%13883
2Bastipati Nagaraju Panchalingala · Kurnool58%28%14475
3Daggumalla Prasada Rao · Chittoor99%63%13774
4GM Harish Balayogi · Amalapuram79%39%5473
5Putta Mahesh Kumar · Eluru92%31%6771
6Midhun Reddy · Rajampet96%36%21170
7Maddila Gurumoorthy · Tirupati93%37%12269
8B K Parthasarathi · Hindupur62%31%5666
9Kinjarapu Ram Mohan Naidu · Srikakulam91%40%7963
10Gumma Thanuja Rani · Araku71%55%3058
11Y S Avinash Reddy · Kadapa83%33%5857
12Dr Byreddy Shabari · Nandyal57%31%7057

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.