Skip to content
MPLADSTracker

Guide & methodology

How MPLADS works, and how we measure it

Everything you need to read this site with confidence: what the scheme is, the rules MPs and districts follow, how each number is calculated, and where the data comes from.

The scheme

The Members of Parliament Local Area Development Scheme (MPLADS) is a Central Sector scheme, started in 1993 and run by the Ministry of Statistics and Programme Implementation (MoSPI). It lets each MP recommend developmental works of a capital nature in their area, focused on durable community assets such as drinking water, education, health, sanitation and roads.

Each MP is entitled to ₹5 crore a year. The money is not paid to the MP: the Government of India releases it to the MP’s Nodal District Authority (usually the District Collector), in two instalments of ₹2.5 crore. The MP only recommends works. The district sanctions them, an implementing agency executes them, and vendors are paid for the work.

Key rules (MPLADS Guidelines, 2023)

  • Where: Lok Sabha MPs recommend works in their constituency. Elected Rajya Sabha MPs recommend works in the state that elected them. Nominated MPs may choose any district in the country.
  • Outside the area: MPs may also recommend a limited amount each year for works outside their constituency or state, and more for areas hit by severe calamities.
  • SC/ST areas: at least 15% of the entitlement is meant for areas inhabited by Scheduled Castes and 7.5% for Scheduled Tribe areas.
  • Eligible works: durable community assets that are available for public use. Examples include roads, school buildings, drinking water, health facilities and community halls.
  • Not allowed: works for maintenance or repair of any kind; offices or residences of government bodies; works on private, commercial or religious property; grants, loans or relief funds; memorials; and purchase of land.
  • Timelines: the district is expected to sanction an eligible work within 45 days of recommendation and to complete sanctioned works, generally within a year.
  • eSAKSHI: since 1 April 2023 the whole fund flow (recommendation, sanction, work orders and vendor payments) runs through the eSAKSHI portal, so each rupee can be traced to a work and a vendor.

This is a plain-language summary. The guidelines are the authority. Read them on mplads.gov.in.

Life of a work

  1. Entitlement released. MoSPI credits the MP’s limit on eSAKSHI. This is the allocated limit on this site.
  2. Recommended. The MP proposes a work with an estimated cost. This counts towards works recommended.
  3. Sanctioned. The Implementing District Authority (IDA) checks eligibility and feasibility, sanctions the work and assigns an implementing agency.
  4. Executed & paid. Vendors are paid through the portal as the work progresses. These are the expenditure records.
  5. Completed. The work is marked complete with its final cost, photographs and, where collected, a citizen rating.

Metrics

MetricHow it’s calculatedMostly reflects
Allocated limitThe MP’s allocated limit as reported by eSAKSHIMoSPI releases
Fund utilisationValue of works recommended ÷ allocated limit. This is MoSPI’s own measure of how much of an MP’s fund has been used.The MP
SanctionedRecommended works that the district has sanctioned ÷ works recommendedDistrict authority
Time to sanctionAverage days from recommendation to sanction (the guideline is 45 days)District authority
Overdue sanctionsWorks still unsanctioned more than 45 days after recommendation, on the snapshot dateDistrict authority
SpentVendor payments ÷ allocated limitDistrict & agencies
Completion rateWorks completed ÷ works recommendedDistrict & agencies
Time to completeAverage days from recommendation to completion, where both dates exist
Citizen ratingAverage of ratings (1–5) on completed works; missing ratings are ignoredCitizens
Top-vendor shareLargest vendor’s payments ÷ all vendor payments for the MP
Vendor HHISum of squared payment shares × 10,000 (0 = spread out, 10,000 = one vendor)

Every work carries its eSAKSHI id, so recommendations, sanctions, completions and payments are joined exactly, not by guessing from names. Medians compare each MP with others in the same house and term.

MP score

A number from 0 to 100, so MPs can be ranked. Finishing works counts most, then spending money well, so an MP whose funds are paid out without works being completed doesn’t rank high. Each part is 0–100; a part without enough data (e.g. fewer than 5 completed works) is left out and the rest are re-weighted.

  • Works completed (30%): Completed ÷ recommended works.
  • Spending efficiency (20%): Value of completed works ÷ money paid out. Money paid without works finished scores low.
  • Fund utilisation (15%): Value of works recommended ÷ allocated limit (MoSPI’s measure).
  • Proof of work (15%): Share of completed works with photos or documents uploaded on eSAKSHI.
  • Funds spent (10%): Paid to vendors ÷ allocated limit.
  • Vendor diversity (10%): How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything. Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

District sanction speed

Sanctioning works is the district authority’s job, not the MP’s. So it is a separate grade shown next to each MP’s score, which does not change the MP’s rank:

  • Sanction speed (100%): Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Citizen ratings are shown but not scored, because they are often missing. Every table can also be sorted by the individual measures.

Attention flags

Flags are simple, published rules. They are prompts for questions, never findings of wrongdoing.

  • No works recommended: At least ₹2.5 Cr allocated and not a single work recommended. Mostly reflects: MP.
  • Most funds not yet used: At least ₹2.5 Cr allocated, and works recommended for less than 25% of it (MoSPI’s utilisation measure). Mostly reflects: MP.
  • Works waiting for sanction: At least 10 recommended works, and at least 40% of all this MP’s recommended works, still not sanctioned more than 45 days after recommendation (the guideline deadline). Mostly reflects: District authority.
  • Recommended, but little spent: At least half the allocation recommended, but under 10% paid out to vendors. Mostly reflects: District authority & agencies.
  • No completed works reported: 20 or more works recommended and none reported complete. Mostly reflects: District authority & agencies.
  • Payments concentrated with one vendor: One vendor received 50% or more of at least ₹1 Cr paid, across 5 or more payments. Mostly reflects: District authority.

Data & freshness

All data comes straight from the public services behind MoSPI’s eSAKSHI dashboard (dashboard , portal). There are no spreadsheets or manual copies in between. A sync step downloads four tables for each of three groups: the 18th Lok Sabha, the Rajya Sabha and the 17th Lok Sabha. The tables are allocated limits, works recommended (with sanction details and stage), works completed, and vendor payments.

  • Amounts are read in rupees and dates day-first (the portal writes 05-Jun-2024).
  • State names are standardised, and reserved-seat suffixes such as “(SC)” are split from constituency names.
  • Works, completions and payments are joined by eSAKSHI’s work id. MPs are matched by house, term, state and name, ignoring honorifics.
  • Photos are not copied. They are fetched live from eSAKSHI when you open them.
  • Nothing is estimated, imputed or filled in. Missing values are shown as “—”.

Current snapshot: 1 Nov 2026, 12:00 pm IST, from eSAKSHI API (mplads.mospi.gov.in). 100% of completed works and 100% of payments matched a recommended work by id.

TableRecordsDownload time
18th Lok Sabha · Allocated limits5443.6s
18th Lok Sabha · Works recommended1,15,575228.4s
18th Lok Sabha · Works completed38,13553.3s
18th Lok Sabha · Vendor payments93,304122.8s
Rajya Sabha · Allocated limits2361.7s
Rajya Sabha · Works recommended27,05370.5s
Rajya Sabha · Works completed10,60817.3s
Rajya Sabha · Vendor payments27,11040.1s
17th Lok Sabha · Allocated limits5442.3s
17th Lok Sabha · Works recommended94,538313.4s
17th Lok Sabha · Works completed72,86092.6s
17th Lok Sabha · Vendor payments1,40,304184.8s

Caveats: eSAKSHI covers fund flows from 1 April 2023, so works funded earlier under the old physical system are not included. For the 17th Lok Sabha this means only its final year. The allocated limit is the amount the portal reports. Errors in the official data carry through as published.

State map: @svg-maps/india by Victor Cazanave, licensed CC BY 4.0. It is used for shading only and is not an authoritative depiction of boundaries. Ladakh is drawn within Jammu and Kashmir on this map.

What you can do

  • Look up the works for your MP on this site, then check them on the official eSAKSHI dashboard.
  • Visit a completed work. Does it exist, is it in use, does it match the photo? Many works have geo-tagged photos.
  • Ask your MP’s office which works they plan to recommend and why. Funds not yet recommended are an open question.
  • Ask the district. The Nodal District Authority (District Collector’s MPLADS cell) is responsible for sanction, execution and payments.
  • File an RTI with the district’s Public Information Officer for sanction orders, estimates, work orders and completion certificates for a specific work.

FAQ

Why is “spent” so much lower than utilisation?

Utilisation counts a work as soon as the MP recommends it. Money is paid only after the district sanctions it and work progresses, so payments trail recommendations by months. Compare an MP with the median for their house, not with 100%.

Why can utilisation be above 100%?

The source data sometimes shows works recommended worth more than the allocated limit it reports, for example estimates that include future instalments. We show the numbers as published.

Does a low score mean an MP is doing a bad job?

Not on its own. Utilisation and completion depend heavily on district administration, and a recently elected MP will naturally score lower. Use the score to find questions worth asking.

Is this an official government website?

No. It is an independent presentation of public data. For official figures, use the eSAKSHI portal.

I found an error. What should I do?

If the official portal shows the same thing, the error is in the source data. Otherwise it may be ours. Please open an issue in the project repository with the page link.

This site shows public data as published, to help citizens understand how MPLADS funds are used. It does not create or alter the underlying data and has no intent to target any individual or institution. Back to the overview