1st of 25 from Andhra Pradesh
Allocated limit
₹6.99 Cr
Median ₹8.60 Cr
Fund utilisation
100%
₹6.99 Cr recommended · 129 works
About the median
Paid to vendors
₹6.89 Cr
99% of allocation
Above median (88%)
Works completed
127
98% of recommended
Above median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP129 works
₹6.99 Cr · 100% of the ₹6.99 Cr allocated
- Sanctioned by the district125 works
97% sanctioned · took 2 days on average (due within 45 days)
- Completed127 works
₹6.89 Cr final cost · 6.1 months from recommendation on average
4 works are still awaiting sanction, 4 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 129 works worth ₹6.99 Cr, a fund utilisation of 100%, higher than 84% of 17th Lok Sabha MPs.
- The district has sanctioned 125 of them, taking 2 days on average.
- ₹6.89 Cr has been paid to vendors, 99% of the allocation.
- 127 works are complete, typically 6.1 months after recommendation. 127 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 42 vendors. The largest received 9.6%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 99/100: finishing works counts most
- Works completed 30%98Completed ÷ recommended works.
- Spending efficiency 20%100Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%99Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%99Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Rothu Srinivasa Rao, 9.6% of payments across 42 vendors.
District sanction speed
98/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%98Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
131 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of retaining Wall for protecting the eroded banks of D/s of Mukkollu Paaru Baaru Vaddu B/w KM 0.000 to 0.016
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· Kakinada· #55646
₹4.3 L Completed 27 Dec 2025Rec. 2 Dec 2023Paid ₹4.3 LConstruction of retaining wall for protecting the eroded banks of D/s of Mukkollu Paaru Baaru Vaddu b/w K.M.0.016 to 0.032
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· Kakinada· #55647
₹4.2 L Completed 27 Dec 2025Rec. 2 Dec 2023Paid ₹4.2 LProviding basic infrastructure and Shuttle Court in Tarakarama Nagar
Sports & fitnessDevelopment of playfields and sports grounds· Kakinada· #121657
₹4.9 L Completed 7 Oct 2025Rec. 6 Mar 2024Paid ₹4.9 LConstruction of 1st Floor Seminar Hall to A S D Government Women’s Degree College
Education & librariesConstruction of rooms and halls in school and colleges· Kakinada· #54964
₹40.9 L Completed 30 Aug 2025Rec. 30 Nov 2023Paid ₹40.9 LConstruction of Culverts in EBC Colony in 19th and 20th Ward at Gollaprolu NP
Roads & bridgesConstruction of culverts and bridges· Kakinada· #84281
₹4.0 L Completed 18 Jun 2025Rec. 18 Jan 2024Paid ₹4.0 LConstruction of Compound Wall at Burial Ground Scheduled Caste area at 24th Ward
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Kakinada· #121692
₹5.0 L Completed 24 May 2025Rec. 6 Mar 2024Paid ₹5.0 LConstruction of Compound wall to Multipurpose Hall
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Kakinada· #107765
₹4.2 L Completed 17 May 2025Rec. 17 Feb 2024Paid ₹4.2 LConstruction of Multipurpose Hall near Ambedkar statue at Anand Nagar at Komaragiri (V)
Community buildings & public spacesConstruction of buildings for community cultural activities· Kakinada· #84275
₹4.5 L Completed 15 May 2025Rec. 18 Jan 2024Paid ₹4.5 LConstruction of Waiting shed to Burial Ground at Sagar Nagar in Komaragiri (V) of U.Kothapalli (M)
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Kakinada· #89085
₹5.0 L Completed 15 May 2025Rec. 25 Jan 2024Paid ₹5.0 LConstruction of CC Drain from D.No.6-4-248 to 6-4-251, 4-3-102/A1 to 4-3-101, and D.No.4-3-102/P1 to Tatapudi Syamuyelu
Sanitation & drainageProviding drains and gutters for public drainage· Kakinada· #121707
₹4.9 L Completed 2 May 2025Rec. 6 Mar 2024Paid ₹4.9 LProviding CC Road from D.No.20-1-73 to 20-1-79/1
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kakinada· #111041
₹4.9 L Completed 22 Apr 2025Rec. 21 Feb 2024Paid ₹4.9 LConstruction of Kitchen and Dining Hall in Dr. B.R.Ambedkar SC & ST Boys Hostel, Kakinada in 37th Ward of Kakinada Municipal Corporation
Community buildings & public spacesSetting up of kitchen and pantries· Kakinada· #70651
₹49.1 L Completed 3 Apr 2025Rec. 28 Dec 2023Paid ₹49.1 LConstruction of Net Weaving Centre with Open Slab at Nayakar Colony at Uppada (V) of U.Kothapalli (M)
Community buildings & public spacesConstruction of buildings for community cultural activities· Kakinada· #89075
₹5.0 L Completed 26 Mar 2025Rec. 25 Jan 2024Paid ₹5.0 LConstruction of CC Road from Bharathi Srinu (H) to Tikkada Jagannadham (H) and other
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kakinada· #111042
₹4.7 L Completed 26 Mar 2025Rec. 21 Feb 2024Paid ₹4.7 LProviding CC Road in D.No.14-1-37 to 14-1-42 in 14th Ward
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kakinada· #121661
₹4.9 L Completed 24 Mar 2025Rec. 6 Mar 2024Paid ₹4.9 L
17th Lok Sabha MPs from Andhra Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Vanga Geetha Viswanath · Kakinada | 100% | 99% | 127 | 99 |
| 2 | Pocha Brahmananda Reddy · Nandyal | 100% | 100% | 137 | 98 |
| 3 | Srinivas Kesineni · Vijayawada | 89% | 89% | 91 | 97 |
| 4 | Nandigam Suresh · Bapatla | 95% | 93% | 118 | 97 |
| 5 | Dr Sanjeev Kumar Singari · Kurnool | 90% | 89% | 359 | 96 |
| 6 | Smt Chinta Anuradha · Amalapuram | 98% | 86% | 176 | 96 |
| 7 | Jayadev Galla · Guntur | 100% | 97% | 132 | 95 |
| 8 | Talari Rangaiah · Anantapur | 87% | 84% | 191 | 94 |
| 9 | Shri N Reddeppa · Chittoor | 96% | 81% | 141 | 91 |
| 10 | Kinjarapu Ram Mohan Naidu · Srikakulam | 95% | 81% | 106 | 89 |
| 11 | Kuruva Gorantla Madhav · Hindupur | 85% | 83% | 63 | 89 |
| 12 | Midhun Reddy · Rajampet | 86% | 73% | 196 | 89 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.