Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
80%
₹11.81 Cr recommended · 45 works
Above median (76%)
Paid to vendors
₹2.50 Cr
17% of allocation
Below median (37%)
Works completed
3
6.7% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP45 works
₹11.81 Cr · 80% of the ₹14.70 Cr allocated
- Sanctioned by the district33 works
73% sanctioned · took 2.5 months on average (due within 45 days)
- Completed3 works
₹49.9 L final cost · 10.2 months from recommendation on average
12 works are still awaiting sanction, 4 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 45 works worth ₹11.81 Cr, a fund utilisation of 80%, higher than 57% of 18th Lok Sabha MPs.
- The district has sanctioned 33 of them, taking 2.5 months on average.
- ₹2.50 Cr has been paid to vendors, 17% of the allocation.
- 3 works are complete, typically 10.2 months after recommendation. 3 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 8 vendors. The largest received 35%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 37/100: finishing works counts most
- Works completed 30%7Completed ÷ recommended works.
- Spending efficiency 20%20Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%80Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%60Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%17Paid to vendors ÷ allocated limit.
- Vendor diversity 10%81How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: KANDAVALLI BUTCHAMMA, 35% of payments across 8 vendors.
District sanction speed
91/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%91Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
45 works · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of a Compound Wall at the OC Burial Ground in Biccavole Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #321852
₹23.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of a Cremation Building at the Sagarupeta BC Burial Ground in Rangapuram Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #321853
₹8.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of a Waiting Hall at the OC Burial Ground in Ramavaram Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #321863
₹20.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of Additional Rooms and a Compound Wall for the BC Community Building at Bobbilanka Village
Community buildings & public spacesConstruction of additional rooms and halls in the existing public and community building· East Godavari· #321864
₹25.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of Bathing Facilities and a Water Storage Tank at the Burial Ground in Narendrapuram Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #321865
₹5.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of Compound wall at the OC Burial Ground in Kamsalipalem Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #321866
₹5.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of a Cremation Building and Crematin Platfor at the OC Burial Ground in Kamsalipalem Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #321867
₹5.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of SC Community Hall in Prakasaraopalem (V) in Nallajerla (M)
Community buildings & public spacesConstruction of community centers and community halls· East Godavari· #321868
₹15.0 L Awaiting sanction · 19 daysRec. 13 Oct 2026Construction of Compound Wall at SC Burial Ground in Prakkilanka village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #291944
₹10.0 L Sanctioned · 15 Sept 2026Rec. 27 Aug 2026Construction of Burial Ground Platform at Doddigunta Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #309038
₹10.0 L Sanctioned · 15 Sept 2026Rec. 27 Aug 2026Construction of Multipurpose Activity Centre in the BC area of Teepearru
Community buildings & public spacesConstruction of community centers and community halls· East Godavari· #309039
₹25.0 L Sanctioned · 15 Sept 2026Rec. 27 Aug 2026Construction of Multipurpose Activity Centre in the OC area of Ravimetla
Community buildings & public spacesConstruction of community centers and community halls· East Godavari· #309040
₹20.0 L Sanctioned · 15 Sept 2026Rec. 27 Aug 2026Construction of Multipurpose Activity Centre in the SC area of Kamsalipalem
Community buildings & public spacesConstruction of community centers and community halls· East Godavari· #309042
₹20.0 L Sanctioned · 15 Sept 2026Rec. 27 Aug 2026Construction of Cremation Platform with Burning Berth in BC Burial Ground in Kotikesavaram Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· East Godavari· #291943
₹10.0 L Awaiting sanction · 66 daysRec. 27 Aug 2026Construction of additional infrastructure at Sramika Bhavan in the Municipal Corporation 49th Ward of Rajamahendravaram
Community buildings & public spacesConstruction of additional rooms and halls in the existing public and community building· East Godavari· #309041
₹60.0 L Awaiting sanction · 66 daysRec. 27 Aug 2026
18th Lok Sabha MPs from Andhra Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Prabhakar Reddy Vemireddy · Nellore | 96% | 56% | 138 | 83 |
| 2 | Bastipati Nagaraju Panchalingala · Kurnool | 58% | 28% | 144 | 75 |
| 3 | Daggumalla Prasada Rao · Chittoor | 99% | 63% | 137 | 74 |
| 4 | GM Harish Balayogi · Amalapuram | 79% | 39% | 54 | 73 |
| 5 | Putta Mahesh Kumar · Eluru | 92% | 31% | 67 | 71 |
| 6 | Midhun Reddy · Rajampet | 96% | 36% | 211 | 70 |
| 7 | Maddila Gurumoorthy · Tirupati | 93% | 37% | 122 | 69 |
| 8 | B K Parthasarathi · Hindupur | 62% | 31% | 56 | 66 |
| 9 | Kinjarapu Ram Mohan Naidu · Srikakulam | 91% | 40% | 79 | 63 |
| 10 | Gumma Thanuja Rani · Araku | 71% | 55% | 30 | 58 |
| 11 | Y S Avinash Reddy · Kadapa | 83% | 33% | 58 | 57 |
| 12 | Dr Byreddy Shabari · Nandyal | 57% | 31% | 70 | 57 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.