Skip to content
MPLADSTracker
This is a record from the 17th Lok Sabha (2019–24). eSAKSHI covers its final year only, from April 2023. Comparisons are with other 17th Lok Sabha MPs.

MPLADS report card · 17th Lok Sabha

Swami Sachchidanandhari Sakshi ji Maharaj

Lok SabhaUnnao · Uttar Pradesh

MP score81/100335th of 539 in the 17th Lok Sabha
51st of 81 from Uttar Pradesh
Re-elected to the 18th Lok Sabha Then: 67% utilisation, 14 works completed, score 41.
  • Payments concentrated with one vendor

    88% of vendor payments went to DHIRENDRA SINGH.

Allocated limit

₹10.23 Cr

Median ₹8.60 Cr

Fund utilisation

91%

₹9.30 Cr recommended · 83 works
Below median (98%)

Paid to vendors

₹9.29 Cr

91% of allocation
About the median

Works completed

66

80% of recommended
About the median

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP83 works

    ₹9.30 Cr · 91% of the ₹10.23 Cr allocated

  2. Sanctioned by the district82 works

    99% sanctioned · took 3.0 months on average (due within 45 days)

  3. Completed66 works

    ₹8.68 Cr final cost · 23.1 months from recommendation on average

1 works are still awaiting sanction, 1 of them for more than 45 days.

In plain words

What the numbers say

  • Recommended 83 works worth ₹9.30 Cr, a fund utilisation of 91%, higher than 18% of 17th Lok Sabha MPs.
  • The district has sanctioned 82 of them, taking 3.0 months on average.
  • ₹9.29 Cr has been paid to vendors, 91% of the allocation.
  • 66 works are complete, typically 23.1 months after recommendation. 61 works have geo-tagged photos on eSAKSHI.
  • The largest share of funds went to Roads & bridges.
  • Payments went to 5 vendors. The largest received 88%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 81/100: finishing works counts most

  1. Works completed 30%80Completed ÷ recommended works.
  2. Spending efficiency 20%93Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%91Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%92Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%91Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    15
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: DHIRENDRA SINGH, 88% of payments across 5 vendors.

District sanction speed

92/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%92Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

83 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Gramsabha Haibatpur block bangarmau Mansharam ke darwaje se hote huye Kanhaiya Lal ke darwaje tak interlocking karya.

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #47136

    ₹18.9 L Completed 16 Jan 2026Rec. 7 Nov 2023Paid ₹18.9 L
  • Chandrika kheda me amar saheed Gulab Singh Lodhi mela prangad me atirikt nirman karya.

    Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Unnao· #47138

    ₹2.1 L Completed 16 Jan 2026Rec. 7 Nov 2023Paid ₹2.1 L
  • SOHRAMAU ARJUNAMAU MARG SE GRAM SAROTI ME PRAMOD AWASTHI KE GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53796

    ₹11.4 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹11.4 L
  • GRAM ITKUTI ME BHUIYA DEVI MELA PRANGAN ME BOUNDRY WALL KA NIRMAN KARYA

    Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Unnao· #53797

    ₹3.5 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹3.5 L
  • SOHRAMAU JAITPUR MARG SE GAORA KATHERUA SAMPARK MARG PAR INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53798

    ₹19.7 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹19.7 L
  • GRAM DILWAL MAZRA BABA KHEDA ME MAIN ROAD SE BABURAM KE GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53800

    ₹10.9 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹10.9 L
  • GRAM PANCHAYAT BHITREPAR ME RAMPRASAD KE GHAR SE SHRIRAM KE GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53801

    ₹8.7 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹8.7 L
  • GRAM AMRETHA DAMAR ROAD SE GRAM JALIMKHEDA ME KAMLESH KE GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53802

    ₹18.3 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹18.3 L
  • GRAM PARSANDAN ME TINKU LODHI KE MAKAN SE SHIVPAL LODHI KE MAKAN TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53803

    ₹13.0 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹13.0 L
  • GRAM PIRHARI ME SHIVSHANKAR LODHI KE MAKAN SE RAMKISHAN LODHI KE MAKAN TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53804

    ₹6.1 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹6.1 L
  • GRAM PANCHAYAT PALI KE MAZRA MEETKHEDA BLOCJK NAWABGANJ ME ASHISH KUMAR KE GHAR SE SUKHBIR KUMAR KE GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #53805

    ₹12.8 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹12.8 L
  • GRAM KAITHANKHEDA JANSAR VIKAS KHAND NAWABGANJ HARKESH LOSHI KE GHAR SE BHAGWANDEEN LODHI KE GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #54085

    ₹13.8 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹13.8 L
  • GRAM SARIYA VIKAS KHAND SIKANDARPUR SARAUSI GRAM DEVARA KHURD ME RAMJEEVAN KE GHAR SE MAIN ROAD TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #54086

    ₹11.1 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹11.1 L
  • GRAM PANCHAYAT DEWARA KALA ME GRAM SAMBHALKHEDA VINOD LODHI KE GHAR SE BHOLA CHAVAN KE GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #54087

    ₹24.8 L Completed 16 Jan 2026Rec. 28 Nov 2023Paid ₹24.8 L
  • GRAM RAMSINGHKHEDA MAJRA THANA ME DILIP DHOBI KE GHAR SE BHOLA KA GHAR TAK INTERLOCKING KARYA

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #68861

    ₹4.0 L Completed 16 Jan 2026Rec. 23 Dec 2023Paid ₹4.0 L

17th Lok Sabha MPs from Uttar Pradesh

Ranked by MP score

#MPUtilisationSpentCompletedScore
1Shri Narendra Modi · Varanasi100%100%296100
2Mahesh Sharma · Gautam Buddha Nagar100%97%8899
3Anurag Sharma · Jhansi100%100%13798
4Seyed Tufail Hasan · Moradabad100%98%18897
5Shri Ajay (Teni) Misra · Kheri97%97%5197
6Shri Kunwar Danish Ali · Amroha100%97%32597
7Kirti Vardhan Singh · Gonda96%96%13096
8Girish Chandra · Nagina95%95%23896
9Shri Lallu Singh · Faizabad98%94%6296
10Shri Shafiqur Rahman Barq · Sambhal99%97%20695
11Rajesh Verma · Sitapur100%100%2295
12Prof SP Singh Baghel · Agra100%100%3695

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.