Skip to content
MPLADSTracker
This is a record from the 17th Lok Sabha (2019–24). eSAKSHI covers its final year only, from April 2023. Comparisons are with other 17th Lok Sabha MPs.

MPLADS report card · 17th Lok Sabha

Shri NK Premachandran

Lok SabhaKollam · Kerala

MP score86/100238th of 539 in the 17th Lok Sabha
14th of 20 from Kerala
Re-elected to the 18th Lok Sabha Then: 77% utilisation, 78 works completed, score 62.

Allocated limit

₹4.99 Cr

Median ₹8.60 Cr

Fund utilisation

86%

₹4.27 Cr recommended · 60 works
Below median (98%)

Paid to vendors

₹3.89 Cr

78% of allocation
Below median (88%)

Works completed

54

90% of recommended
Above median (83%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP60 works

    ₹4.27 Cr · 86% of the ₹4.99 Cr allocated

  2. Sanctioned by the district60 works

    100% sanctioned · took 11.7 months on average (due within 45 days)

  3. Completed54 works

    ₹3.66 Cr final cost · 14.3 months from recommendation on average

In plain words

What the numbers say

  • Recommended 60 works worth ₹4.27 Cr, a fund utilisation of 86%, higher than 9.9% of 17th Lok Sabha MPs.
  • The district has sanctioned 60 of them, taking 11.7 months on average.
  • ₹3.89 Cr has been paid to vendors, 78% of the allocation.
  • 54 works are complete, typically 14.3 months after recommendation. 36 works have geo-tagged photos on eSAKSHI.
  • The largest share of funds went to Roads & bridges.
  • Payments went to 40 vendors. The largest received 7.7%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 86/100: finishing works counts most

  1. Works completed 30%90Completed ÷ recommended works.
  2. Spending efficiency 20%94Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%86Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%67Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%78Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    100
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: HAREES, 7.7% of payments across 40 vendors.

District sanction speed

51/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%51Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

60 works · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Construction of Drainage at Gurunar Ela Road near Paripally Paravur Road in Chathanur Constituency

    Sanitation & drainageProviding drains and gutters for public drainage· Kollam· #131171

    ₹9.3 L Completed 19 Sept 2026Rec. 16 Mar 2024Paid ₹9.3 L
  • Construction of Building for Anganwadi No. 52 near Ayyankoyickal Temple at Ward No/. 16, Thevalakkara GP Chavara Constituency

    Education & librariesConstruction of buildings for crèches and anganwadies· Kollam· #131165

    ₹12.8 L Completed 5 Sept 2026Rec. 16 Mar 2024Paid ₹12.8 L
  • Construction of side wall and concreting of Kailasam SC Colony road- Paravattam Ward, Punalur Municipality in Punalur Constituency (SC)

    Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Kollam· #131161

    ₹6.7 L Completed 11 May 2026Rec. 16 Mar 2024Paid ₹6.7 L
  • Construction of side protection wall at Arinalloor market Muttam Road Arinallor ward No. 7 at Thevalakkara GP in Chavara Constituency

    Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Kollam· #131459

    ₹61,353 Completed 11 Mar 2026Rec. 16 Mar 2024Paid ₹61,353
  • Construction of reading room for Vilakkupara LP School at Eroor Gramapanchayat in Punalur Constituency

    Education & librariesConstruction of public libraries and reading rooms· Kollam· #131005

    ₹5.0 L Completed 26 Dec 2025Rec. 16 Mar 2024Paid ₹5.0 L
  • Concreting of road from Pallimukku Kalyanimukku Canal Road at Manalil Ward, Ayiranalloor Village, Yeroor GP, Punalur Constituency

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kollam· #131015

    ₹7.5 L Completed 26 Dec 2025Rec. 16 Mar 2024Paid ₹7.5 L
  • Bus waiting shed at Padappakara Palli junction of Perayam Gramapanchayat

    Community buildings & public spacesConstruction of bus-sheds or bus-stops· Kollam· #174076

    ₹5.4 L Completed 18 Nov 2025Rec. 4 Mar 2022Paid ₹5.4 L
  • Side wall construction of the road from Kalluvila Junction to Kayalvaram at Ward No. 12 in Perayam Gramapanchayat in Kundara Constituency

    Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Kollam· #131003

    ₹1.9 L Completed 17 Nov 2025Rec. 16 Mar 2024Paid ₹1.9 L
  • Construction of Mini Open Air Auditorium at Vettuvila Jayanti Colony in Anchalummoodu Division of Kollam

    Community buildings & public spacesConstruction of buildings for community cultural activities· Kollam· #174075

    ₹21.7 L Completed 31 Oct 2025Rec. 19 May 2022Paid ₹21.7 L
  • Construction of Building for Library and Reading room for Perumpuzha Kala- Samskarika Samithi, Perumpuzha, in Kundara

    Community buildings & public spacesConstruction of buildings for community cultural activities· Kollam· #174101

    ₹13.6 L Completed 4 Oct 2025Rec. 15 Feb 2024Paid ₹13.6 L
  • Concreting of road from Vazhamon Temple - Valakkode ward at Punalur Municipality in Punalur Constituency

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kollam· #131536

    ₹4.8 L Completed 16 Sept 2025Rec. 16 Mar 2024Paid ₹4.8 L
  • Road Concreting of Marithimoodu bus stand No. 12 Kadamankodu at Kulathupuzha GP in Punalur constituency

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kollam· #174098

    ₹13.7 L Completed 4 Aug 2025Rec. 15 Feb 2024Paid ₹13.7 L
  • Construction of building for Anganwadi Kalangummukal ward at Punalur Municipality Punalur Constituency

    Community buildings & public spacesConstruction of buildings for community cultural activities· Kollam· #130874

    ₹14.1 L Completed 3 Aug 2025Rec. 16 Mar 2024Paid ₹14.1 L
  • Construction of short bridge and culvert at Saktikulangara Pandazha Purathezham Kiniginiyazhikam bhagom in Chavara Constituency

    Roads & bridgesConstruction of culverts and bridges· Kollam· #131462

    ₹9.2 L Completed 5 Jul 2025Rec. 16 Mar 2024Paid ₹9.2 L
  • Construction of building for Kadamankodu Tribal LP School in Kulathupuzha GP in Punalur Constituency

    Education & librariesConstruction of rooms and halls in school and colleges· Kollam· #174096

    ₹44,722 Completed 23 Jun 2025Rec. 15 Feb 2024Paid ₹44,722

17th Lok Sabha MPs from Kerala

Ranked by MP score

#MPUtilisationSpentCompletedScore
1M P Abdussamad Samadani · Malappuram84%84%17995
2T N Prathapan · Thrissur100%95%9094
3E T Mohammed Basheer · Ponnani84%83%11794
4Rahul Gandhi · Wayanad90%90%7193
5Shri M K Raghavan · Kozhikode77%74%21392
6Shri Rajmohan Unnithan · Kasaragod98%97%28392
7Dr Shashi Tharoor · Thiruvananthapuram91%84%15092
8Adv Adoor Prakash · Attingal100%97%29092
9Anto Antony · Pathanamthitta99%88%15490
10Adv Dean Kuriakose · Idukki90%82%14790
11Smt Ramya Haridas · Alathur100%100%41890
12Vellalath Kochukrishnan Nair Sreekandan · Palakkad100%83%14590

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.