4th of 16 from Telangana
Allocated limit
₹10.72 Cr
Median ₹8.60 Cr
Fund utilisation
100%
₹10.68 Cr recommended · 208 works
About the median
Paid to vendors
₹8.75 Cr
82% of allocation
Below median (88%)
Works completed
174
84% of recommended
About the median
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP208 works
₹10.68 Cr · 100% of the ₹10.72 Cr allocated
- Sanctioned by the district201 works
97% sanctioned · took 7.1 months on average (due within 45 days)
- Completed174 works
₹8.50 Cr final cost · 10.8 months from recommendation on average
7 works are still awaiting sanction, 7 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 208 works worth ₹10.68 Cr, a fund utilisation of 100%, higher than 71% of 17th Lok Sabha MPs.
- The district has sanctioned 201 of them, taking 7.1 months on average.
- ₹8.75 Cr has been paid to vendors, 82% of the allocation.
- 174 works are complete, typically 10.8 months after recommendation. 86 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 50 vendors. The largest received 20%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 85/100: finishing works counts most
- Works completed 30%84Completed ÷ recommended works.
- Spending efficiency 20%97Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%49Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%82Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: UPPARI SHEKHAR, 20% of payments across 50 vendors.
District sanction speed
72/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%72Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
208 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Laying of CC Road at Mudimyal Village
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Ranga Reddy· #119572
₹4.2 L Completed 7 Sept 2026Rec. 3 Mar 2024Paid ₹4.2 LProviding of LED based Hi-mast lights with material
Electricity & lightingLighting of public spaces· Vikarabad· #126961
₹5.3 L Completed 11 May 2026Rec. 13 Mar 2024Paid ₹5.3 LLaying of CC Road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Vikarabad· #126350
₹10.0 L Completed 5 May 2026Rec. 12 Mar 2024Paid ₹10.0 LProviding of LED based Hi- Mast lights with material
Electricity & lightingLighting of public spaces· Vikarabad· #126962
₹5.3 L Completed 22 Apr 2026Rec. 13 Mar 2024Paid ₹5.3 LProviding of LED Based Hi-mast lights with material
Electricity & lightingLighting of public spaces· Vikarabad· #126963
₹5.3 L Completed 22 Apr 2026Rec. 13 Mar 2024Paid ₹5.3 LProviding of LED based Hymass lights with material
Electricity & lightingLighting of public spaces· Vikarabad· #126964
₹5.3 L Completed 22 Apr 2026Rec. 13 Mar 2024Paid ₹5.3 LProviding of LED based Hi-mast lights with material
Electricity & lightingLighting of public spaces· Vikarabad· #126966
₹7.1 L Completed 22 Apr 2026Rec. 13 Mar 2024Paid ₹7.1 LLaying of CC road from GP building to Kavalibabu (H) at Ebbanoor (V), Dharur (M) Vikarabad (D)
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Vikarabad· #270165
₹10.0 L Physical Inspection · 18 Apr 2026Rec. 19 Feb 2024Paid ₹10.0 LLaying of CC Road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Vikarabad· #126491
₹5.0 L Completed 15 Apr 2026Rec. 12 Mar 2024Paid ₹5.0 LConstruction of Cultural Center
Community buildings & public spacesConstruction of community centers and community halls· Ranga Reddy· #125756
₹9.8 L Completed 10 Mar 2026Rec. 11 Mar 2024Paid ₹9.8 LLaying of CC Road at Chevella Village
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Ranga Reddy· #119573
₹8.0 L Completed 26 Sept 2025Rec. 3 Mar 2024Paid ₹8.0 LLaying of CC Road at Chevella Village
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Ranga Reddy· #119574
₹10.0 L Completed 26 Sept 2025Rec. 3 Mar 2024Paid ₹10.0 LConstruction of Side Drain
Sanitation & drainageProviding drains and gutters for public drainage· Vikarabad· #123532
₹5.0 L Completed 30 Aug 2025Rec. 8 Mar 2024Paid ₹5.0 LConstruction of Side Drain
Sanitation & drainageProviding drains and gutters for public drainage· Vikarabad· #123533
₹5.0 L Completed 30 Aug 2025Rec. 8 Mar 2024Paid ₹5.0 LLaying of formation road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Vikarabad· #126665
₹5.5 L Completed 28 Aug 2025Rec. 12 Mar 2024Paid ₹5.5 L
17th Lok Sabha MPs from Telangana
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Ramulu Pothuganti · Nagarkurnool | 99% | 81% | 158 | 90 |
| 2 | Smt Kavitha Malothu · Mahabubabad | 100% | 80% | 161 | 87 |
| 3 | Shri Komati Reddy Venkat Reddy · Bhongir | 89% | 87% | 356 | 85 |
| 4 | Gaddam Ranjith Reddy · Chelvella | 100% | 82% | 174 | 85 |
| 5 | Anumula Revanth Reddy · Malkajgiri | 100% | 68% | 28 | 84 |
| 6 | Uttam Kumar Nalamada Reddy · Nalgonda | 100% | 96% | 270 | 83 |
| 7 | Venkatesh Netha Borlakunta · Peddapalle | 99% | 75% | 264 | 79 |
| 8 | Dayakar Pasunoori · Warangel | 96% | 88% | 226 | 78 |
| 9 | Bheemrao Baswanthrao Patil · Zahirabad | 100% | 68% | 399 | 76 |
| 10 | Nama Nageswara Rao · Khammam | 87% | 71% | 193 | 73 |
| 11 | Sanjay Kumar Bandi · Karimnagar | 99% | 58% | 294 | 73 |
| 12 | Asaduddin Owaisi · Hyderabad | 96% | 70% | 32 | 67 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.