State profile
Telangana
24 MPs: 17 in the Lok Sabha and 7 in the Rajya Sabha. Median MP score 51 out of 100.
Allocated
₹400.5 Cr
24 MPs
Fund utilisation
70%
₹279.5 Cr recommended · 6,784 works
Sanctioned
74%
1,110 works waiting over 45 days
Paid to vendors
₹105.8 Cr
26% of allocation
Works completed
2,440
36% of recommended works
Follow the money
Bar length relative to the largest stage
- Allocated limit₹400.5 Cr
- Recommended by MPs₹279.5 Cr
70% fund utilisation · 6,784 works
- Paid to vendors₹105.8 Cr
26% of allocation · 3,428 payments
- Value of completed works₹71.77 Cr
2,440 works finished
Top sectors
Value of works recommended in Telangana
MPs from Telangana
Ranked by MP score. How it’s scored
| # | MP | House | Utilisation | Spent | Completion | Score |
|---|---|---|---|---|---|---|
| 1 | Balram Naik PorikaMahabubabad | Lok Sabha | 74% | 50% | 62% | 75 |
| 2 | Chamala Kiran Kumar ReddyBhongir | Lok Sabha | 64% | 45% | 83% | 71 |
| 3 | Dr.Mallu RaviNagarkurnool | Lok Sabha | 75% | 42% | 60% | 68 |
| 4 | Arvind DharmapuriNizamabad | Lok Sabha | 97% | 57% | 52% | 65 |
| 5 | Shri Ravi Chandra VaddirajuRajya Sabha | Rajya Sabha | 92% | 51% | 36% | 63 |
| 6 | Shri Anil Kumar Yadav MandadiRajya Sabha | Rajya Sabha | 76% | 38% | 58% | 62 |
| 7 | Sanjay Kumar BandiKarimnagar | Lok Sabha | 97% | 41% | 34% | 61 |
| 8 | Kadiyam KavyaWarangel | Lok Sabha | 74% | 24% | 32% | 60 |
| 9 | Konda Vishweshwar ReddyChelvella | Lok Sabha | 64% | 29% | 34% | 56 |
| 10 | Aruna. D. KMahabubnagar | Lok Sabha | 87% | 34% | 34% | 56 |
| 11 | Godam NageshAdilabad | Lok Sabha | 73% | 25% | 23% | 55 |
| 12 | Shri Damodar Rao DivakondaRajya Sabha | Rajya Sabha | 82% | 34% | 33% | 52 |
| 13 | Madhavaneni Raghunandan RaoMedak | Lok Sabha | 82% | 25% | 21% | 50 |
| 14 | Eatala RajenderMalkajgiri | Lok Sabha | 77% | 13% | 11% | 47 |
| 15 | Suresh Kumar ShetkarZahirabad | Lok Sabha | 71% | 27% | 15% | 39 |
| 16 | Ramasahayam Raghuram ReddyKhammam | Lok Sabha | 54% | 21% | 8.5% | 39 |
| 17 | Kunduru RaghuveerNalgonda | Lok Sabha | 18% | 6.0% | 16% | 39 |
| 18 | Shri B. Parthasaradhi ReddyRajya Sabha | Rajya Sabha | 56% | 3.9% | 2.9% | 38 |
| 19 | Vamsi Krishna GaddamPeddapalle | Lok Sabha | 62% | 12% | 4.9% | 37 |
| 20 | Asaduddin OwaisiHyderabad | Lok Sabha | 80% | 7.6% | 3.4% | 28 |
| 21 | Dr. Abhishek Manu SinghviRajya Sabha | Rajya Sabha | 79% | 7.2% | 0% | 16 |
| 22 | Smt. Renuka ChowdhuryRajya Sabha | Rajya Sabha | 31% | 6.3% | 0% | 15 |
| 23 | Kishan Reddy GangapuramSecunderabad | Lok Sabha | 40% | 5.6% | 0% | 11 |
| 24 | Shri Vem Narendar ReddyRajya Sabha | Rajya Sabha | 0% | 0% | — | 0 |
Implementing agencies
District authorities with the most works recommended
| Agency | Works | Awaiting sanction | Completed | Avg time |
|---|---|---|---|---|
| Nizamabad | 693 | 180 (144 late) | 331 (48%) | 3.5 months |
| Jagitial | 467 | 19 (1 late) | 211 (45%) | 7.8 months |
| Khammam | 459 | 209 (5 late) | 40 (8.7%) | 5.1 months |
| Vikarabad | 371 | 20 (16 late) | 122 (33%) | 8.1 months |
| Sangareddy | 343 | 195 (137 late) | 34 (9.9%) | 7.5 months |
| Karimnagar | 336 | 166 (162 late) | 84 (25%) | 9.2 months |
| Ranga Reddy | 311 | 9 (3 late) | 185 (59%) | 5.6 months |
| Siddipet | 278 | 127 (109 late) | 125 (45%) | 6.4 months |
| Medchal Malkajgiri | 272 | 85 (77 late) | 32 (12%) | 11.2 months |
| Adilabad | 264 | 138 (138 late) | 21 (8.0%) | 4.9 months |
Worth asking about
Each flag states the rule that triggered it. It prompts a question; it is not a finding of wrongdoing.
- Shri Anil Kumar Yadav MandadiRajya Sabha
Payments concentrated with one vendor
61% of vendor payments went to SANTRIX CONSTRUCTIONS.
- Aruna. D. KLok Sabha
Payments concentrated with one vendor
54% of vendor payments went to VIOLET ENTERPRISES.
- Madhavaneni Raghunandan RaoLok Sabha
Works waiting for sanction
97 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.
- Kunduru RaghuveerLok Sabha
Most funds not yet used
Works recommended for only 18% of the allocated limit.
- Shri B. Parthasaradhi ReddyRajya Sabha
Recommended, but little spent
56% of funds recommended, but only 3.9% paid out to vendors.
- Asaduddin OwaisiLok Sabha
Works waiting for sanction
15 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.
Recommended, but little spent
80% of funds recommended, but only 7.6% paid out to vendors.
Payments concentrated with one vendor
92% of vendor payments went to A F Construction op by Ismail.
- Dr. Abhishek Manu SinghviRajya Sabha
Recommended, but little spent
79% of funds recommended, but only 7.2% paid out to vendors.
- Smt. Renuka ChowdhuryRajya Sabha
No completed works reported
102 works recommended, none reported complete yet.
- Kishan Reddy GangapuramLok Sabha
Works waiting for sanction
22 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.
No completed works reported
38 works recommended, none reported complete yet.
- Shri Vem Narendar ReddyRajya Sabha
No works recommended
Funds are available, but no works have been recommended yet.