73rd of 81 from Uttar Pradesh
Allocated limit
₹7.36 Cr
Median ₹8.60 Cr
Fund utilisation
98%
₹7.23 Cr recommended · 11 works
About the median
Paid to vendors
₹6.93 Cr
94% of allocation
Above median (88%)
Works completed
4
36% of recommended
Below median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP11 works
₹7.23 Cr · 98% of the ₹7.36 Cr allocated
- Sanctioned by the district11 works
100% sanctioned · took 6.8 months on average (due within 45 days)
- Completed4 works
₹3.55 Cr final cost · 18.4 months from recommendation on average
In plain words
What the numbers say
- Recommended 11 works worth ₹7.23 Cr, a fund utilisation of 98%, higher than 51% of 17th Lok Sabha MPs.
- The district has sanctioned 11 of them, taking 6.8 months on average.
- ₹6.93 Cr has been paid to vendors, 94% of the allocation.
- 4 works are complete, typically 18.4 months after recommendation. 3 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 7 vendors. The largest received 36%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 62/100: finishing works counts most
- Works completed 30%36Completed ÷ recommended works.
- Spending efficiency 20%51Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%98Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%60Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%94Paid to vendors ÷ allocated limit.
- Vendor diversity 10%80How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Balaji Enterprises, 36% of payments across 7 vendors.
District sanction speed
75/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%75Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
11 works · tap “Photos” to see geo-tagged photos from eSAKSHI
aadrsh vidyalay mahmmadpur, sandila, hardoi as per construction of hall in this school, ammount 250000.00
Education & librariesConstruction of rooms and halls in school and colleges· Hardoi· #43120
₹2.5 L Vendor Identification · 21 Sept 2026Rec. 1 Nov 2023Paid ₹1.9 LSUPPLY AND INSTALLATION OF LED SEMI HIGH MAST LIGHT(04 LIGHT WALI 200 WATT) AT 101 DIFFRENT PLACES AT MISHRIKH LOK SABHA AS PER ATTACHEMENT OF LIST ( ENCLOSED) PER LED LIGHT COST 150500.00 TOTAL COST 15200500.00
Electricity & lightingStreet lights· Kanpur Nagar· #67156
₹1.51 Cr Completed 19 Jan 2026Rec. 21 Dec 2023Paid ₹1.51 CrSUPPLY AND INSTALLATION OF LED SEMI HIGH MAST LIGHT(EK LIGHT WALI 200 WATT) AT 141 DIFFRENT PLACES AT MISHRIKH LOK SABHA AS PER ATTACHEMENT OF LIST (ENCLOSED) PER LED LIGHT COST= 76800.00 TOTAL AMOUNT 10828800
Electricity & lightingLighting of public spaces· Sitapur· #34354
₹1.08 Cr Completed 14 Feb 2025Rec. 8 Oct 2023Paid ₹1.08 CrSUPPLY AND INSTALLATION OF LED SEMI HIGH MAST LIGHT(04 LIGHT WALI 200 WATT) AT 53 DIFFRENT PLACES AT MISHRIKH LOK SABHA AS PER ATTACHEMENT OF LIST (ENCLOSED) PER LED LIGHT COST 177500.00 TOTAL COST 9407500.00
Electricity & lightingLighting of public spaces· Sitapur· #34356
₹94.1 L Completed 14 Feb 2025Rec. 8 Oct 2023Paid ₹94.1 LSUPPLY AND INSTALLATION OF LED SEMI HIGH MAST LIGHT(06 LIGHT WALI 200 WATT) AT 01 PLACE AT MISHRIKH LOK SABHA AS PER ATTACHEMENT OF LIST (ENCLOSED) PER LED LIGHT COST 236600.00
Electricity & lightingLighting of public spaces· Sitapur· #34361
₹2.4 L Completed 14 Feb 2025Rec. 8 Oct 2023Paid ₹2.4 Lconstruction of CC interlocking road from damar rode towoards to shyamu pal (tentative 100m ) amount 500000,
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Hardoi· #130313
₹5.0 L Work partially Completed · 10 Sept 2024Rec. 16 Mar 2024Paid ₹4.9 Lconstruction of CC interlocking rode from chheda yadav house towoards to ramkeshan (tentative 250m ) amount 1000000,
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Hardoi· #130314
₹10.0 L Work partially Completed · 10 Sept 2024Rec. 16 Mar 2024Paid ₹9.9 Lconstruction of CC interlocking road from harischandr house towoards to madev mandir (tentative 130m ) amount 600000
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Hardoi· #130315
₹6.0 L Work partially Completed · 10 Sept 2024Rec. 16 Mar 2024Paid ₹5.9 LSUPPLY AND INSTALLATION OF LED SEMI HIGH MAST LIGHT(04 LIGHT WALI 200 WATT) AT 55 DIFFRENT PLACES AT MISHRIKH LOK SABHA AS PER ATTACHEMENT OF LIST (ENCLOSED) PER LED LIGHT COST 178100.00 TOTAL COST 9795500.00
Electricity & lightingLighting of public spaces· Hardoi· #72664
₹90.8 L Vendor Identification · 9 Mar 2024Rec. 1 Jan 2024Paid ₹65.7 LSUPPLY AND INSTALLATION OF LED SEMI HIGH MAST LIGHT(04 LIGHT WALI 200 WATT) AT 54 DIFFRENT PLACES AT MISHRIKH LOK SABHA AS PER ATTACHEMENT OF LIST (ENCLOSED) PER LED LIGHT COST 171000.00 TOTAL COST 14193000.00
Electricity & lightingLighting of public spaces· Hardoi· #34366
₹1.38 Cr Vendor Identification · 7 Jan 2024Rec. 8 Oct 2023Paid ₹1.37 CrSUPPLY AND INSTALLATION OF LED SEMI HIGH MAST LIGHT(04 LIGHT WALI 200 WATT) AT 67 DIFFRENT PLACES AT MISHRIKH LOK SABHA AS PER ATTACHEMENT OF LIST (ENCLOSED) PER LED LIGHT COST 171000.00 TOTAL COST 11457000.00
Electricity & lightingLighting of public spaces· Hardoi· #34369
₹1.15 Cr Vendor Identification · 7 Jan 2024Rec. 8 Oct 2023Paid ₹1.13 Cr
17th Lok Sabha MPs from Uttar Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Narendra Modi · Varanasi | 100% | 100% | 296 | 100 |
| 2 | Mahesh Sharma · Gautam Buddha Nagar | 100% | 97% | 88 | 99 |
| 3 | Anurag Sharma · Jhansi | 100% | 100% | 137 | 98 |
| 4 | Seyed Tufail Hasan · Moradabad | 100% | 98% | 188 | 97 |
| 5 | Shri Ajay (Teni) Misra · Kheri | 97% | 97% | 51 | 97 |
| 6 | Shri Kunwar Danish Ali · Amroha | 100% | 97% | 325 | 97 |
| 7 | Kirti Vardhan Singh · Gonda | 96% | 96% | 130 | 96 |
| 8 | Girish Chandra · Nagina | 95% | 95% | 238 | 96 |
| 9 | Shri Lallu Singh · Faizabad | 98% | 94% | 62 | 96 |
| 10 | Shri Shafiqur Rahman Barq · Sambhal | 99% | 97% | 206 | 95 |
| 11 | Rajesh Verma · Sitapur | 100% | 100% | 22 | 95 |
| 12 | Prof SP Singh Baghel · Agra | 100% | 100% | 36 | 95 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.