15th of 17 from Telangana
Allocated limit
₹14.85 Cr
Median ₹14.70 Cr
Fund utilisation
62%
₹9.19 Cr recommended · 182 works
Below median (76%)
Paid to vendors
₹1.74 Cr
12% of allocation
Below median (37%)
Works completed
9
4.9% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP182 works
₹9.19 Cr · 62% of the ₹14.85 Cr allocated
- Sanctioned by the district67 works
37% sanctioned · took 3.8 months on average (due within 45 days)
- Completed9 works
₹70.5 L final cost · 4.8 months from recommendation on average
115 works are still awaiting sanction, 31 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 182 works worth ₹9.19 Cr, a fund utilisation of 62%, higher than 25% of 18th Lok Sabha MPs.
- The district has sanctioned 67 of them, taking 3.8 months on average.
- ₹1.74 Cr has been paid to vendors, 12% of the allocation.
- 9 works are complete, typically 4.8 months after recommendation. 5 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 15 vendors. The largest received 33%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 37/100: finishing works counts most
- Works completed 30%5Completed ÷ recommended works.
- Spending efficiency 20%41Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%62Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%56Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%12Paid to vendors ÷ allocated limit.
- Vendor diversity 10%84How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SVR CONSTRUCTIONS, 33% of payments across 15 vendors.
District sanction speed
80/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%80Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
182 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
construction of mini bus stand
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Peddapalli· #323118
₹5.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026drilling of boare well and pumpset
Drinking waterInstalling tube-wells and borewells· Peddapalli· #323119
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026drilling of borewell and pumpset
Drinking waterInstalling tube-wells and borewells· Peddapalli· #323120
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Dirilling of bore well and hand pump
Drinking waterInstalling hand pumps· Peddapalli· #323121
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026drilling of bore well and hand pump
Drinking waterInstalling hand pumps· Peddapalli· #323122
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026laying of CC Road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Peddapalli· #323125
₹5.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Side drain
Sanitation & drainageProviding drains and gutters for public drainage· Peddapalli· #323127
₹5.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Construction of SC Community Hall
Community buildings & public spacesConstruction of community centers and community halls· Peddapalli· #323130
₹5.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Construction of compound wall of Mudhiraj community
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Peddapalli· #323131
₹5.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Laying of CC Road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Peddapalli· #323134
₹5.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Laying of cc Road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Peddapalli· #323137
₹5.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Drilling of Borewell and pumpset
Drinking waterInstalling tube-wells and borewells· Peddapalli· #323138
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026RO Water plant
Drinking waterInstalling community drinking water plants· Peddapalli· #323139
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026Drilling of bore well and pumpset
Drinking waterInstalling tube-wells and borewells· Peddapalli· #323140
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026drilling of borewell and pumpset
Drinking waterInstalling tube-wells and borewells· Peddapalli· #323142
₹2.0 L Awaiting sanction · 10 daysRec. 22 Oct 2026
18th Lok Sabha MPs from Telangana
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Balram Naik Porika · Mahabubabad | 74% | 50% | 239 | 75 |
| 2 | Chamala Kiran Kumar Reddy · Bhongir | 64% | 45% | 417 | 71 |
| 3 | Dr.Mallu Ravi · Nagarkurnool | 75% | 42% | 143 | 68 |
| 4 | Arvind Dharmapuri · Nizamabad | 97% | 57% | 480 | 65 |
| 5 | Sanjay Kumar Bandi · Karimnagar | 97% | 41% | 217 | 61 |
| 6 | Kadiyam Kavya · Warangel | 74% | 24% | 76 | 60 |
| 7 | Konda Vishweshwar Reddy · Chelvella | 64% | 29% | 182 | 56 |
| 8 | Aruna. D. K · Mahabubnagar | 87% | 34% | 129 | 56 |
| 9 | Godam Nagesh · Adilabad | 73% | 25% | 81 | 55 |
| 10 | Madhavaneni Raghunandan Rao · Medak | 82% | 25% | 41 | 50 |
| 11 | Eatala Rajender · Malkajgiri | 77% | 13% | 34 | 47 |
| 12 | Suresh Kumar Shetkar · Zahirabad | 71% | 27% | 65 | 39 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.