Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
68%
₹9.98 Cr recommended · 90 works
Below median (76%)
Paid to vendors
₹1.66 Cr
11% of allocation
Below median (37%)
Works completed
17
19% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP90 works
₹9.98 Cr · 68% of the ₹14.70 Cr allocated
- Sanctioned by the district65 works
72% sanctioned · took 4.1 months on average (due within 45 days)
- Completed17 works
₹1.14 Cr final cost · 16.6 months from recommendation on average
25 works are still awaiting sanction, 25 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 90 works worth ₹9.98 Cr, a fund utilisation of 68%, higher than 37% of 18th Lok Sabha MPs.
- The district has sanctioned 65 of them, taking 4.1 months on average.
- ₹1.66 Cr has been paid to vendors, 11% of the allocation.
- 17 works are complete, typically 16.6 months after recommendation. 17 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 6 vendors. The largest received 32%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 54/100: finishing works counts most
- Works completed 30%19Completed ÷ recommended works.
- Spending efficiency 20%68Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%68Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%11Paid to vendors ÷ allocated limit.
- Vendor diversity 10%85How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: MINTU SARKAR, 32% of payments across 6 vendors.
District sanction speed
74/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%74Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
90 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Installation of purified water scheme with reserviour within Radhanagar BSP Pry. school in Radhanagar , under holka barobisha no 1G.P.
Drinking waterInstalling community drinking water plants· Alipurduar· #270959
₹5.0 L Sanctioned · 6 Oct 2026Rec. 25 Feb 2026Construction of New Class Room in 2nd floor of barobisha High School in Barobisha under Kumargram Panchayet Samiti
Education & librariesConstruction of rooms and halls in school and colleges· Alipurduar· #176201
₹18.9 L Completed 30 Sept 2026Rec. 18 Feb 2025Paid ₹18.9 LNH31 To Madarihat Maha Samsan Ghat Madarihat GP
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Alipurduar· #287679
₹38.8 L Sanctioned · 15 Sept 2026Rec. 20 Jun 2026Raju pual House to SSK School Subhas nagar 4 No MAdarihat GP
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Alipurduar· #287682
₹38.8 L Sanctioned · 15 Sept 2026Rec. 20 Jun 2026Installation of Single Unit Mini high Mast Solar Street Light System Six Nos 60W Semi Intregrted Solar street light at Singimari High School Booth under Rampur II Gram Panchayat within Tufanganj II Development Block
Electricity & lightingStreet lights· Cooch Behar· #210024
₹7.4 L Completed 9 Sept 2026Rec. 18 Jun 2025Paid ₹7.4 LInstallation of Single Unit Mini high Mast Solar Street Light System Six Nos 60W Semi Intregrted Solar street light at Jaldhoa Chowpathi under Rampur II Gram Panchayat within Tufanganj II Development Block
Electricity & lightingStreet lights· Cooch Behar· #210026
₹7.4 L Completed 9 Sept 2026Rec. 18 Jun 2025Paid ₹7.4 LInstallation of Single Unit Mini high Mast Solar Street Light System Six Nos 60W Semi Intregrted Solar street light at Anchal Para Bazar under Rampur II Gram Panchayat within Tufanganj II Development Block
Electricity & lightingStreet lights· Cooch Behar· #210027
₹7.4 L Completed 9 Sept 2026Rec. 18 Jun 2025Paid ₹7.4 LInstallation of Single Unit Mini high Mast Solar Street Light System Six Nos 60W Semi Intregrted Solar street light at near house of Ratan Chakraborty under Rampur II Gram Panchayat within Tufanganj II Development Block
Electricity & lightingStreet lights· Cooch Behar· #210028
₹7.4 L Completed 9 Sept 2026Rec. 18 Jun 2025Paid ₹7.4 LInstallation of Single Unit Mini high Mast Solar Street Light System Six Nos 60W Semi Intregrted Solar street light at Madhurbhasha Natun Bazar under Rampur II Gram Panchayat within Tufanganj II Development Block
Electricity & lightingStreet lights· Cooch Behar· #210029
₹7.4 L Completed 9 Sept 2026Rec. 18 Jun 2025Paid ₹7.4 LInstallation of Single Unit Mini high Mast Solar Street Light System Six Nos 60W Semi Intregrted Solar street light at Garbhanga School Chowpathi under Rampur II Gram Panchayat within Tufanganj II Development Block
Electricity & lightingStreet lights· Cooch Behar· #210030
₹7.4 L Completed 9 Sept 2026Rec. 18 Jun 2025Paid ₹7.4 LEstimate for construction of Boulder sausage works for protection of paver Block Roads from prafullo das to Nagen Rava house within salbari-II gram panchayat under tufanganj-II panchayat samity
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Cooch Behar· #299179
₹16.6 L Sanctioned · 3 Sept 2026Rec. 27 Jul 2026Constuction of paver Road From PMGHY Road to Nagen Rava House Within salbari-II gram panchayat under tufanganj-II panchayat samity.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Cooch Behar· #299181
₹17.1 L Sanctioned · 3 Sept 2026Rec. 27 Jul 2026Constuction of paver Road From PMGHY Road to Govinda Rava House Within salbari-II gram panchayat under tufanganj-II panchayat samity.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Cooch Behar· #299183
₹12.7 L Sanctioned · 3 Sept 2026Rec. 27 Jul 2026Constuction of paver Road From Amit Roy house to kanai Rava House Within salbari-II gram panchayat under tufanganj-II panchayat samity.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Cooch Behar· #299186
₹12.7 L Sanctioned · 3 Sept 2026Rec. 27 Jul 2026Sining of Rig Bore Tube Well with submersible pump at Chinchula Godam Line Kalchini GP in Kalchini Block under Alipurduar Distict
Drinking waterInstalling tube-wells and borewells· Alipurduar· #185179
₹5.2 L Completed 2 Sept 2026Rec. 21 Mar 2025Paid ₹5.2 L
18th Lok Sabha MPs from West Bengal
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Asit Kumar Mal · Bolpur | 89% | 60% | 146 | 83 |
| 2 | Pratima Mondal · Joynagar | 66% | 50% | 180 | 82 |
| 3 | Kalyan Banerjee · Sreerampur | 63% | 52% | 97 | 82 |
| 4 | Shri Deepak (Dev) Adhikari · Ghatal | 95% | 56% | 166 | 81 |
| 5 | Shri Abhishek Banerjee · Diamond Harbour | 64% | 49% | 254 | 79 |
| 6 | Kalipada Saren · Jhargram | 78% | 49% | 40 | 76 |
| 7 | Prasun Banerjee · Howrah | 74% | 50% | 140 | 74 |
| 8 | Kakoli Ghosh Dastidar · Barasat | 87% | 43% | 82 | 71 |
| 9 | Smt Sajda Ahmed · Uluberia | 72% | 34% | 96 | 71 |
| 10 | Saumitra khan · Bishnupur | 98% | 44% | 48 | 71 |
| 11 | Bag Mitali · Arambag | 96% | 41% | 95 | 71 |
| 12 | Smt Satabdi Roy (Banerjee) · Birbhum | 48% | 32% | 62 | 71 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.