Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
88%
₹12.97 Cr recommended · 49 works
Above median (76%)
Paid to vendors
₹6.85 Cr
47% of allocation
Above median (37%)
Works completed
3
6.1% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP49 works
₹12.97 Cr · 88% of the ₹14.70 Cr allocated
- Sanctioned by the district31 works
63% sanctioned · took 2.9 months on average (due within 45 days)
- Completed3 works
₹2.12 Cr final cost · 6.8 months from recommendation on average
18 works are still awaiting sanction.
In plain words
What the numbers say
- Recommended 49 works worth ₹12.97 Cr, a fund utilisation of 88%, higher than 70% of 18th Lok Sabha MPs.
- The district has sanctioned 31 of them, taking 2.9 months on average.
- ₹6.85 Cr has been paid to vendors, 47% of the allocation.
- 3 works are complete, typically 6.8 months after recommendation. 3 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 19 vendors. The largest received 32%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 43/100: finishing works counts most
- Works completed 30%6Completed ÷ recommended works.
- Spending efficiency 20%31Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%88Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%60Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%47Paid to vendors ÷ allocated limit.
- Vendor diversity 10%85How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: MS VIDYARTHI CONSTRUCTION, 32% of payments across 19 vendors.
District sanction speed
93/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%93Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
49 works · tap “Photos” to see geo-tagged photos from eSAKSHI
Allahabad loksabha koraon block install solar light.
Electricity & lightingLighting of public spaces· Prayagraj· #324852
₹9.0 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha chhetra hand pumps install.
Drinking waterInstalling hand pumps· Prayagraj· #324859
₹3.1 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha meja block solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #324869
₹21.4 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block koraon solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #324937
₹11.6 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha Manda block solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #324941
₹5.9 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block manda solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #325059
₹6.7 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block jasra solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #325063
₹8.0 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block karchhana solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #325068
₹23.1 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block chaka solar light
Electricity & lightingLighting of public spaces· Prayagraj· #325070
₹21.4 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block kondhiyara solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #325071
₹14.1 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block shankargar solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #325075
₹9.2 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block urwa solar light install.
Electricity & lightingLighting of public spaces· Prayagraj· #325077
₹8.0 L Awaiting sanction · 2 daysRec. 30 Oct 2026Allahabad loksabha block urwa solar light 2 install.
Electricity & lightingLighting of public spaces· Prayagraj· #325084
₹10.8 L Awaiting sanction · 2 daysRec. 30 Oct 2026Hand pump established in Allahabad loksabha chhetra.
Drinking waterInstalling hand pumps· Prayagraj· #324429
₹23.1 L Awaiting sanction · 8 daysRec. 24 Oct 2026Hand pump established in Allahabad loksabha chhetra
Drinking waterInstalling hand pumps· Prayagraj· #324436
₹47.3 L Awaiting sanction · 8 daysRec. 24 Oct 2026
18th Lok Sabha MPs from Uttar Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Narendra Modi · Varanasi | 62% | 60% | 207 | 89 |
| 2 | Rajkumar Chahar · Fatehpur Sikri | 90% | 71% | 45 | 84 |
| 3 | Awadhesh Prasad · Faizabad | 98% | 65% | 143 | 84 |
| 4 | Utkarsh Verma Madhur · Kheri | 85% | 53% | 349 | 83 |
| 5 | Shri Arun Kumar Sagar · Shahjahanpur | 100% | 94% | 5 | 83 |
| 6 | Vinod Kumar Bind · Bhadohi | 81% | 58% | 525 | 82 |
| 7 | Ramesh Awasthi · Kanpur | 84% | 57% | 104 | 79 |
| 8 | Babu Singh Kushwaha · Jaunpur | 79% | 39% | 622 | 78 |
| 9 | Daroga Prasad Saroj · Lalganj | 65% | 56% | 212 | 76 |
| 10 | Mohibbullah · Rampur | 75% | 51% | 318 | 76 |
| 11 | Neeraj Maurya · Aonla | 100% | 91% | 17 | 75 |
| 12 | Mukesh Rajput · Farrukhabad | 99% | 91% | 246 | 74 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.