Works waiting for sanction
40 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.
Allocated limit
₹15.12 Cr
Median ₹14.70 Cr
Fund utilisation
100%
₹15.12 Cr recommended · 56 works
Above median (76%)
Paid to vendors
₹10.57 Cr
70% of allocation
Above median (37%)
Works completed
6
11% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP56 works
₹15.12 Cr · 100% of the ₹15.12 Cr allocated
- Sanctioned by the district15 works
27% sanctioned · took 4.3 months on average (due within 45 days)
- Completed6 works
₹5.43 Cr final cost · 17.3 months from recommendation on average
41 works are still awaiting sanction, 40 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 56 works worth ₹15.12 Cr, a fund utilisation of 100%, higher than 99% of 18th Lok Sabha MPs.
- The district has sanctioned 15 of them, taking 4.3 months on average.
- ₹10.57 Cr has been paid to vendors, 70% of the allocation.
- 6 works are complete, typically 17.3 months after recommendation. 5 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 15 vendors. The largest received 19%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 58/100: finishing works counts most
- Works completed 30%11Completed ÷ recommended works.
- Spending efficiency 20%51Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%83Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%70Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Ajay Kumar Singh, 19% of payments across 15 vendors.
District sanction speed
51/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%51Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
56 works · tap “Photos” to see geo-tagged photos from eSAKSHI
installation of street lights
Electricity & lightingLighting of public spaces· Sultanpur· #325496
₹1.94 Cr Awaiting sanction · 1 daysRec. 31 Oct 2026kindly execute the work as per attachement list
Electricity & lightingLighting of public spaces· Sultanpur· #284190
₹2.50 Cr Vendor Identification · 16 Oct 2026Rec. 27 May 2026Paid ₹1.49 CrKindly execute the work as per attachment list
Electricity & lightingLighting of public spaces· Sultanpur· #286495
₹59.5 L Vendor Identification · 16 Oct 2026Rec. 17 Jun 2026Paid ₹32.6 Lconstruction of new water tanks near the residence of nandkishore
Drinking waterConstruction of water tanks· Agra· #2233
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of hariom
Drinking waterConstruction of water tanks· Agra· #2234
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of dharmendra singh
Drinking waterConstruction of water tanks· Agra· #2235
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of rinku singh
Drinking waterConstruction of water tanks· Agra· #2236
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of brijmohan singh
Drinking waterConstruction of water tanks· Agra· #2237
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near gram thar gudiya laxmi
Drinking waterConstruction of water tanks· Agra· #2238
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of netram son of ramprakash
Drinking waterConstruction of water tanks· Agra· #2239
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near bypass road fatehabad kakrili wale raghunath singh
Drinking waterConstruction of water tanks· Agra· #2240
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of ramnarayanpur son of domar singh
Drinking waterConstruction of water tanks· Agra· #2241
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of narayansigh son of chaviram
Drinking waterConstruction of water tanks· Agra· #2242
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of bhupendra singh
Drinking waterConstruction of water tanks· Agra· #2243
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026construction of new water tanks near the residence of akash son of bhup singh
Drinking waterConstruction of water tanks· Agra· #2244
₹2.6 L Awaiting sanction · 60 daysRec. 2 Sep 2026
18th Lok Sabha MPs from Uttar Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Narendra Modi · Varanasi | 62% | 60% | 207 | 89 |
| 2 | Rajkumar Chahar · Fatehpur Sikri | 90% | 71% | 45 | 84 |
| 3 | Awadhesh Prasad · Faizabad | 98% | 65% | 143 | 84 |
| 4 | Utkarsh Verma Madhur · Kheri | 85% | 53% | 349 | 83 |
| 5 | Shri Arun Kumar Sagar · Shahjahanpur | 100% | 94% | 5 | 83 |
| 6 | Vinod Kumar Bind · Bhadohi | 81% | 58% | 525 | 82 |
| 7 | Ramesh Awasthi · Kanpur | 84% | 57% | 104 | 79 |
| 8 | Babu Singh Kushwaha · Jaunpur | 79% | 39% | 622 | 78 |
| 9 | Daroga Prasad Saroj · Lalganj | 65% | 56% | 212 | 76 |
| 10 | Mohibbullah · Rampur | 75% | 51% | 318 | 76 |
| 11 | Neeraj Maurya · Aonla | 100% | 91% | 17 | 75 |
| 12 | Mukesh Rajput · Farrukhabad | 99% | 91% | 246 | 74 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.