Skip to content
MPLADSTracker

MPLADS report card · 18th Lok Sabha

Ram Shiromani

Lok SabhaSPShrawasti · Uttar Pradesh

MP score12/100528th of 542 in the 18th Lok Sabha
80th of 80 from Uttar Pradesh
Also an MP in the 17th Lok Sabha Then: 100% utilisation, 762 works completed, score 84.
  • Works waiting for sanction

    708 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.

  • No completed works reported

    1357 works recommended, none reported complete yet.

  • Payments concentrated with one vendor

    84% of vendor payments went to NAVEEN ENTERPRISES.

Allocated limit

₹15.17 Cr

Median ₹14.70 Cr

Fund utilisation

59%

₹9.01 Cr recommended · 1,357 works
Below median (76%)

Paid to vendors

₹2.42 Cr

16% of allocation
Below median (37%)

Works completed

0

0% of recommended
Below median (28%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP1,357 works

    ₹9.01 Cr · 59% of the ₹15.17 Cr allocated

  2. Sanctioned by the district649 works

    48% sanctioned · took 5.8 months on average (due within 45 days)

  3. Completed0 works

    ₹0 final cost

708 works are still awaiting sanction, 708 of them for more than 45 days.

In plain words

What the numbers say

  • Recommended 1,357 works worth ₹9.01 Cr, a fund utilisation of 59%, higher than 22% of 18th Lok Sabha MPs.
  • The district has sanctioned 649 of them, taking 5.8 months on average.
  • ₹2.42 Cr has been paid to vendors, 16% of the allocation.
  • 0 works are complete.
  • The largest share of funds went to Electricity & lighting.
  • Payments went to 4 vendors. The largest received 84%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 12/100: finishing works counts most

  1. Works completed 30%0Completed ÷ recommended works.
  2. Spending efficiency 20%0Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%59Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%0Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%16Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    19
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: NAVEEN ENTERPRISES, 84% of payments across 4 vendors.

District sanction speed

54/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%54Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

1,357 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Installation of a high-mast light (9 meters in height, including 6 lights) near the temple close to Prabhakar Verma house

    Electricity & lightingLighting of public spaces· Shrawasti· #309085

    ₹2.2 L Awaiting sanction · 62 daysRec. 31 Aug 2026
  • 40-Installation of a solar street light near Rajesh Valmiki house at Valmiki Water Tank Ramna

    Electricity & lightingStreet lights· Shrawasti· #264256

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 42-Installation of a solar street light near the water tank in Kyapurwa

    Electricity & lightingStreet lights· Shrawasti· #264258

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 43-Installation of a solar street light near Shankar Ji temple

    Electricity & lightingStreet lights· Shrawasti· #264259

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 44-Installation of a solar street light near Shankar Ji big Shiva temple

    Electricity & lightingStreet lights· Shrawasti· #264260

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 45-Installation of a solar street light near Shankar Ji temple in Jarkushaha

    Electricity & lightingStreet lights· Shrawasti· #264261

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 46-Installation of a solar street light near the Shiva temple in Kursahw

    Electricity & lightingStreet lights· Shrawasti· #264262

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 47-Installation of a solar street light near Shankar Ji temple

    Electricity & lightingStreet lights· Shrawasti· #264263

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 49-Installation of a solar street light near the intersection in Masaha Kala Installation

    Electricity & lightingStreet lights· Shrawasti· #264265

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 50-Installation of a solar street light near the house of Mangaleshwar Prasad Yadav in Kurshaha.

    Electricity & lightingStreet lights· Shrawasti· #264266

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 1-Installation of a solar street light near Firoz Ahmed house in Kurshaha

    Electricity & lightingStreet lights· Shrawasti· #264303

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 3-Installation of a solar street light near the intersection of Ramnagar village

    Electricity & lightingStreet lights· Shrawasti· #264305

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 4-Installation of a solar street light near Gaya Prasad Dom house in Khargaura

    Electricity & lightingStreet lights· Shrawasti· #264306

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 5-Installation of a solar street light near the intersection in Gujarpurwa

    Electricity & lightingStreet lights· Shrawasti· #264307

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026
  • 6-Installation of a solar street light near Vipaldas Kuttipurwa

    Electricity & lightingStreet lights· Shrawasti· #264308

    ₹26,150 Sanctioned · 21 Aug 2026Rec. 4 Feb 2026

18th Lok Sabha MPs from Uttar Pradesh

Ranked by MP score

Compare
#MPUtilisationSpentCompletedScore
1Shri Narendra Modi · Varanasi62%60%20789
2Rajkumar Chahar · Fatehpur Sikri90%71%4584
3Awadhesh Prasad · Faizabad98%65%14384
4Utkarsh Verma Madhur · Kheri85%53%34983
5Shri Arun Kumar Sagar · Shahjahanpur100%94%583
6Vinod Kumar Bind · Bhadohi81%58%52582
7Ramesh Awasthi · Kanpur84%57%10479
8Babu Singh Kushwaha · Jaunpur79%39%62278
9Daroga Prasad Saroj · Lalganj65%56%21276
10Mohibbullah · Rampur75%51%31876
11Neeraj Maurya · Aonla100%91%1775
12Mukesh Rajput · Farrukhabad99%91%24674

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.