Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
68%
₹10.06 Cr recommended · 71 works
Below median (76%)
Paid to vendors
₹4.90 Cr
33% of allocation
Below median (37%)
Works completed
35
49% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP71 works
₹10.06 Cr · 68% of the ₹14.70 Cr allocated
- Sanctioned by the district62 works
87% sanctioned · took 35 days on average (due within 45 days)
- Completed35 works
₹3.90 Cr final cost · 9.7 months from recommendation on average
9 works are still awaiting sanction, 2 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 71 works worth ₹10.06 Cr, a fund utilisation of 68%, higher than 38% of 18th Lok Sabha MPs.
- The district has sanctioned 62 of them, taking 35 days on average.
- ₹4.90 Cr has been paid to vendors, 33% of the allocation.
- 35 works are complete, typically 9.7 months after recommendation. 35 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 16 vendors. The largest received 15%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 69/100: finishing works counts most
- Works completed 30%49Completed ÷ recommended works.
- Spending efficiency 20%80Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%68Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%33Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: INDRA JEET VERMA, 15% of payments across 16 vendors.
District sanction speed
99/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%99Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
71 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Community center and Community Hall
Community buildings & public spacesConstruction of community centers and community halls· Pilibhit· #255715
₹23.9 L Completed 29 Oct 2026Rec. 27 Dec 2025Paid ₹23.9 LConstruction of Community center and Community Hall
Community buildings & public spacesConstruction of community centers and community halls· Pilibhit· #255719
₹24.3 L Completed 29 Oct 2026Rec. 27 Dec 2025Paid ₹24.3 LConstruction of Public Toilets and Bathrooms
Sanitation & drainageConstruction of public toilets and bathrooms· Pilibhit· #255724
₹24.3 L Completed 29 Oct 2026Rec. 27 Dec 2025Paid ₹24.3 LConstruction of a tin shed near Radha Govind Temple, located in Village Sili Jagir Bengali Colony
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Bareilly· #322029
₹17.9 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Barat Ghar/Community Hall in Village Kaichu Tanda
Community buildings & public spacesConstruction of community centers and community halls· Pilibhit· #322030
₹25.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Barat Ghar/Community Center in village Karnapur between Abhaypur shahgarh and Bangla urf Mitrasenpur
Community buildings & public spacesConstruction of community centers and community halls· Pilibhit· #322031
₹25.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of 2 No. Cremation Platform at Muktidham Pilibhit
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Pilibhit· #322032
₹17.9 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Anteshti Sthal and common RCC Shed in Village Jua Jawaharpur
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Bareilly· #322646
₹10.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of antyesthi Sthal in Village Thiriya Nawazishpur
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Bareilly· #322665
₹3.5 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Antyeshti Sthal in Village Dhamipur
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Bareilly· #322666
₹3.5 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Barat Ghar/ Community Center in Village Maidana
Community buildings & public spacesConstruction of community centers and community halls· Pilibhit· #310647
₹25.0 L Sanctioned · 29 Sept 2026Rec. 14 Sep 2026Construction of Boundary Wall and Shed at existing anteshti Sthal in Village Auria Janakpuri
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Pilibhit· #310648
₹24.9 L Sanctioned · 29 Sept 2026Rec. 14 Sep 2026Construction of Anteshti Sthal in Village Vasthana
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Pilibhit· #310649
₹15.7 L Sanctioned · 29 Sept 2026Rec. 14 Sep 2026Construction of Anteshti Sthal in Village Mar
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Pilibhit· #310646
₹15.7 L Awaiting sanction · 48 daysRec. 14 Sep 2026Construction of Anteshti Sthal in Village Shastri Nagar
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Pilibhit· #310650
₹15.7 L Awaiting sanction · 48 daysRec. 14 Sep 2026
18th Lok Sabha MPs from Uttar Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Narendra Modi · Varanasi | 62% | 60% | 207 | 89 |
| 2 | Rajkumar Chahar · Fatehpur Sikri | 90% | 71% | 45 | 84 |
| 3 | Awadhesh Prasad · Faizabad | 98% | 65% | 143 | 84 |
| 4 | Utkarsh Verma Madhur · Kheri | 85% | 53% | 349 | 83 |
| 5 | Shri Arun Kumar Sagar · Shahjahanpur | 100% | 94% | 5 | 83 |
| 6 | Vinod Kumar Bind · Bhadohi | 81% | 58% | 525 | 82 |
| 7 | Ramesh Awasthi · Kanpur | 84% | 57% | 104 | 79 |
| 8 | Babu Singh Kushwaha · Jaunpur | 79% | 39% | 622 | 78 |
| 9 | Daroga Prasad Saroj · Lalganj | 65% | 56% | 212 | 76 |
| 10 | Mohibbullah · Rampur | 75% | 51% | 318 | 76 |
| 11 | Neeraj Maurya · Aonla | 100% | 91% | 17 | 75 |
| 12 | Mukesh Rajput · Farrukhabad | 99% | 91% | 246 | 74 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.