Allocated limit
₹15.57 Cr
Median ₹14.70 Cr
Fund utilisation
87%
₹13.49 Cr recommended · 417 works
Above median (76%)
Paid to vendors
₹9.07 Cr
58% of allocation
Above median (37%)
Works completed
233
56% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP417 works
₹13.49 Cr · 87% of the ₹15.57 Cr allocated
- Sanctioned by the district357 works
86% sanctioned · took 2.5 months on average (due within 45 days)
- Completed233 works
₹7.32 Cr final cost · 11.5 months from recommendation on average
60 works are still awaiting sanction, 14 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 417 works worth ₹13.49 Cr, a fund utilisation of 87%, higher than 67% of 18th Lok Sabha MPs.
- The district has sanctioned 357 of them, taking 2.5 months on average.
- ₹9.07 Cr has been paid to vendors, 58% of the allocation.
- 233 works are complete, typically 11.5 months after recommendation. 218 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 91 vendors. The largest received 38%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 73/100: finishing works counts most
- Works completed 30%56Completed ÷ recommended works.
- Spending efficiency 20%81Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%87Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%94Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%58Paid to vendors ÷ allocated limit.
- Vendor diversity 10%77How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: KPL EQUIPMENTS PRIVATE LIMITED, 38% of payments across 91 vendors.
District sanction speed
93/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%93Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
417 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
sondarya karan near sant senaji samaj kalyan ichapur
Community buildings & public spacesDevelopment of public parks· Burhanpur· #147088
₹2.5 L Completed 31 Oct 2026Rec. 14 Oct 2024Paid ₹2.5 Lward 15 mai bhagwat chouhan l ghr k pas rcc shed
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Burhanpur· #259970
₹5.0 L Completed 31 Oct 2026Rec. 20 Jan 2026Paid ₹5.0 Lshiv mandir k pas saundaryakaran
Community buildings & public spacesDevelopment of public parks· Burhanpur· #259582
₹5.0 L Completed 24 Oct 2026Rec. 19 Jan 2026Paid ₹5.0 Lnear kunbhi samaj go shala singot bhavan nirman
Community buildings & public spacesConstruction of buildings for community cultural activities· Khandwa· #146592
₹15.0 L Completed 23 Oct 2026Rec. 10 Oct 2024Paid ₹15.0 Ladhiwakta sang mai mahilao k liye tin shed
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Khandwa· #305613
₹2.5 L Vendor Identification · 21 Oct 2026Rec. 19 Aug 2026Paid ₹2.4 Lsarvajanki upyog k liye shed
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Khandwa· #316305
₹10.0 L Sanctioned · 16 Oct 2026Rec. 21 Sep 2026muslim jamat mai sarvajanik upyog k liye tin shed
Community buildings & public spacesConstruction of community centers and community halls· Khandwa· #316313
₹3.0 L Sanctioned · 16 Oct 2026Rec. 21 Sep 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320875
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320876
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320877
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320878
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320879
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320880
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320881
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026water tanker
Drinking waterPurchase of mobile water tankers· Burhanpur· #320882
₹1.9 L Awaiting sanction · 24 daysRec. 8 Oct 2026
18th Lok Sabha MPs from Madhya Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Durga Das Uikey · Betul | 99% | 57% | 288 | 75 |
| 2 | Gyaneshwar Patil · Khandwa | 87% | 58% | 233 | 73 |
| 3 | Dr. Lata Wankhede · Sagar | 97% | 75% | 113 | 73 |
| 4 | Jyotiraditya M. Scindia · Guna | 62% | 38% | 46 | 73 |
| 5 | Shri Anil Firojiya · Ujjain | 68% | 56% | 160 | 71 |
| 6 | Bharti Pardhi · Balaghat | 82% | 61% | 115 | 71 |
| 7 | Savitri Thakur · Dhar | 95% | 64% | 179 | 68 |
| 8 | Rahul Singh Lodhi · Damoh | 54% | 45% | 188 | 67 |
| 9 | Shankar Lalwani · Indore | 94% | 55% | 145 | 67 |
| 10 | Dr. Rajesh Mishra · Sidhi | 92% | 72% | 172 | 59 |
| 11 | Alok Sharma · Bhopal | 85% | 49% | 24 | 55 |
| 12 | Rodmal Nagar · Rajgarh | 100% | 65% | 54 | 54 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.