Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
62%
₹9.09 Cr recommended · 64 works
Below median (76%)
Paid to vendors
₹5.59 Cr
38% of allocation
About the median
Works completed
46
72% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP64 works
₹9.09 Cr · 62% of the ₹14.70 Cr allocated
- Sanctioned by the district62 works
97% sanctioned · took 55 days on average (due within 45 days)
- Completed46 works
₹4.57 Cr final cost · 9.0 months from recommendation on average
2 works are still awaiting sanction, 1 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 64 works worth ₹9.09 Cr, a fund utilisation of 62%, higher than 25% of 18th Lok Sabha MPs.
- The district has sanctioned 62 of them, taking 55 days on average.
- ₹5.59 Cr has been paid to vendors, 38% of the allocation.
- 46 works are complete, typically 9.0 months after recommendation. 37 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 50 vendors. The largest received 10%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 73/100: finishing works counts most
- Works completed 30%72Completed ÷ recommended works.
- Spending efficiency 20%82Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%62Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%80Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%38Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: cmo shivpuri, 10% of payments across 50 vendors.
District sanction speed
98/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%98Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
64 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Regarding the construction of additional rooms at the Kushwah Samaj Girls Hostel, Gwalior, by the Adarsh Vivah Organising Committee.
Community buildings & public spacesConstruction of additional rooms and halls in the existing public and community building· Gwalior· #2323
₹10.0 L Awaiting sanction · 23 daysRec. 9 Oct 2026CC Road Construction
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Shivpuri· #191783
₹10.0 L Completed 30 Aug 2026Rec. 16 Apr 2025Paid ₹10.0 LCC road construction
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Shivpuri· #199891
₹10.0 L Completed 19 Aug 2026Rec. 15 May 2025Paid ₹10.0 LCC Road Construction
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Shivpuri· #193426
₹9.9 L Completed 18 Aug 2026Rec. 22 Apr 2025Paid ₹9.9 LCC road construction
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Shivpuri· #199887
₹10.0 L Completed 16 Aug 2026Rec. 15 May 2025Paid ₹10.0 LCC road construction
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Shivpuri· #199888
₹10.0 L Completed 14 Aug 2026Rec. 15 May 2025Paid ₹10.0 LTarring work
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Guna· #281916
₹6.8 L Vendor Identification · 23 Jun 2026Rec. 19 May 2026Construction of community hall
Community buildings & public spacesConstruction of community centers and community halls· Guna· #177243
₹10.0 L Completed 16 Apr 2026Rec. 24 Feb 2025Paid ₹10.0 LConstruction of community hall
Community buildings & public spacesConstruction of community centers and community halls· Guna· #177244
₹10.0 L Completed 16 Apr 2026Rec. 24 Feb 2025Paid ₹10.0 LNA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Guna· #177246
₹10.0 L Completed 16 Apr 2026Rec. 24 Feb 2025Paid ₹10.0 LNA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Guna· #177252
₹10.0 L Completed 13 Apr 2026Rec. 24 Feb 2025Paid ₹10.0 LCC road construction
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Shivpuri· #199885
₹10.0 L Completed 10 Apr 2026Rec. 15 May 2025Paid ₹10.0 LNA
Community buildings & public spacesConstruction of community centers and community halls· Ashoknagar· #151498
₹10.0 L Completed 2 Apr 2026Rec. 8 Nov 2024Paid ₹10.0 LNA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Ashoknagar· #151501
₹9.9 L Completed 31 Mar 2026Rec. 8 Nov 2024Paid ₹9.9 LConstruction of Pavers and Boundary wall in School premises
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Ashoknagar· #199890
₹10.0 L Completed 31 Mar 2026Rec. 15 May 2025Paid ₹10.0 L
18th Lok Sabha MPs from Madhya Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Durga Das Uikey · Betul | 99% | 57% | 288 | 75 |
| 2 | Gyaneshwar Patil · Khandwa | 87% | 58% | 233 | 73 |
| 3 | Dr. Lata Wankhede · Sagar | 97% | 75% | 113 | 73 |
| 4 | Jyotiraditya M. Scindia · Guna | 62% | 38% | 46 | 73 |
| 5 | Shri Anil Firojiya · Ujjain | 68% | 56% | 160 | 71 |
| 6 | Bharti Pardhi · Balaghat | 82% | 61% | 115 | 71 |
| 7 | Savitri Thakur · Dhar | 95% | 64% | 179 | 68 |
| 8 | Rahul Singh Lodhi · Damoh | 54% | 45% | 188 | 67 |
| 9 | Shankar Lalwani · Indore | 94% | 55% | 145 | 67 |
| 10 | Dr. Rajesh Mishra · Sidhi | 92% | 72% | 172 | 59 |
| 11 | Alok Sharma · Bhopal | 85% | 49% | 24 | 55 |
| 12 | Rodmal Nagar · Rajgarh | 100% | 65% | 54 | 54 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.