5th of 42 from West Bengal
Allocated limit
₹7.22 Cr
Median ₹8.60 Cr
Fund utilisation
100%
₹7.19 Cr recommended · 146 works
About the median
Paid to vendors
₹6.99 Cr
97% of allocation
Above median (88%)
Works completed
140
96% of recommended
Above median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP146 works
₹7.19 Cr · 100% of the ₹7.22 Cr allocated
- Sanctioned by the district146 works
100% sanctioned · took 2.2 months on average (due within 45 days)
- Completed140 works
₹6.93 Cr final cost · 14.2 months from recommendation on average
In plain words
What the numbers say
- Recommended 146 works worth ₹7.19 Cr, a fund utilisation of 100%, higher than 70% of 17th Lok Sabha MPs.
- The district has sanctioned 146 of them, taking 2.2 months on average.
- ₹6.99 Cr has been paid to vendors, 97% of the allocation.
- 140 works are complete, typically 14.2 months after recommendation. 121 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 99 vendors. The largest received 11%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 96/100: finishing works counts most
- Works completed 30%96Completed ÷ recommended works.
- Spending efficiency 20%99Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%86Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%97Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SARDAR ENTERPRISE, 11% of payments across 99 vendors.
District sanction speed
96/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%96Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
146 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of ACR of Panikhali F.P. High School G.P- Fulmalancha
Education & librariesConstruction of rooms and halls in school and colleges· South 24 Parganas· #71048
₹6.2 L Completed 14 Oct 2026Rec. 29 Dec 2023Paid ₹6.2 LSupply Erection Installetion & Commissioning of 6.00Mtr soler highmast light led lighting arrangement alongwith Civil work (Construction & foundation) at the near of Bughmari Islamia High Madrasah Main Gate
Electricity & lightingStreet lights· South 24 Parganas· #48959
₹78,200 Completed 23 Sept 2026Rec. 11 Nov 2023Paid ₹78,200Supply Erection Installetion & Commissioning of 6.00Mtr soler highmast light led lighting arrangement alongwith Civil work (Construction & foundation) at the field of Bughmari F.P School
Electricity & lightingStreet lights· South 24 Parganas· #48960
₹80,900 Completed 23 Sept 2026Rec. 11 Nov 2023Paid ₹80,900Renovation of Library room and Headmaster's room by installing wooden cabinate , self etc. and purchase of book for library of Bughmari Islamia high Madrasah (H.S). G.P. - Sahajadapur
Education & librariesConstruction of public libraries and reading rooms· South 24 Parganas· #22766
₹3.4 L Completed 16 Sept 2026Rec. 18 Sep 2023Paid ₹3.4 LConstruction of Mukta Mancha on the ground of Bughmari Islamia high Madrasah (H.S). G.P. - Sahajadapur
Community buildings & public spacesConstruction of buildings for community cultural activities· South 24 Parganas· #22768
₹5.5 L Completed 16 Sept 2026Rec. 18 Sep 2023Paid ₹5.5 LSupply, Erection Installetion & Commissioning of 6.00 Mts Highmast light LED lighting arrangement along with civil Work(Construction & foundation ) near Paschim Tatulberia F.P School, G.P- Beledurganagar, Mouza-Paschim Tatulberia, J.L-106, Dag No-357
Electricity & lightingStreet lights· South 24 Parganas· #73365
₹79,694 Completed 10 Sept 2026Rec. 2 Jan 2024Paid ₹79,694Supply, Erection Installetion & Commissioning of 6.00 Mts Highmast light LED lighting arrangement along with civil Work(Construction & foundation ) near Purba Raghunathpur Sardarer Chak F.P School , G.P-Beledurganagar, Mouza-Purba Raghunathpur, J.L-107, Dag No-54
Electricity & lightingStreet lights· South 24 Parganas· #73374
₹79,424 Completed 10 Sept 2026Rec. 2 Jan 2024Paid ₹79,424Construction of concrete road at monirampur from provas mondal's house towards radhaballav's house at Dhamua North GP under Magrahat-II Block . E.A- E.O. Magrahat-II P.S
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· South 24 Parganas· #5699
₹3.5 L Completed 9 Sept 2026Rec. 22 Jul 2023Paid ₹3.5 LInstalation solar highmast light at baniberia near sarder para khamar at Hotar Marjada GP under Magrahat-II Block , E.A- E.O. Magrahat-II P.S
Electricity & lightingStreet lights· South 24 Parganas· #5714
₹1.7 L Completed 9 Sept 2026Rec. 23 Jul 2023Paid ₹1.7 LInstalletion of High mast light at the near of Bangiyo Gramin Bikas Bank at Banglermore G.P- Dakshin Barasat
Electricity & lightingStreet lights· South 24 Parganas· #82439
₹2.5 L Completed 9 Sept 2026Rec. 15 Jan 2024Paid ₹2.5 LInstallation of 34 number of electric street light at Gabinda Nagar Bazar, the connection and elictrict bill will bear by the Said Grampanchayet, G.P- Tambuldah-II , Block- Canning-II
Electricity & lightingStreet lights· South 24 Parganas· #24928
₹9.7 L Completed 5 Sept 2026Rec. 23 Sep 2023Paid ₹9.7 LInstallation of 34 number of electric street light at Mallikati Bazar, the connection and elictrict bill will bear by the Said Grampanchayet, G.P-Deuli-I , Block- Canning-II
Electricity & lightingStreet lights· South 24 Parganas· #24929
₹9.7 L Completed 5 Sept 2026Rec. 23 Sep 2023Paid ₹9.7 LInstallation of Mini highmast light at Hedia Bhabananda, the connection and elictrict bill will bear by the Said Grampanchayet, G.P- Sarengabad , Block- Canning-II
Electricity & lightingStreet lights· South 24 Parganas· #24931
₹1.8 L Completed 5 Sept 2026Rec. 23 Sep 2023Paid ₹1.8 LRenovation and electrification of Principal's room, Profesor's room, Auditorium and Main Gate of Jibantala Rokeya Mashavidyalaya , G.P-Sarengabad,
Education & librariesConstruction of rooms and halls in school and colleges· South 24 Parganas· #24935
₹24.5 L Completed 5 Sept 2026Rec. 23 Sep 2023Paid ₹24.5 LConstruction of steel Railing for North side Mini Stadium at Jibantala Rokeya Mahavidyalaya Under Sarengabad G.P of Canning-II Deelopment block
Sports & fitnessConstruction of stadiums· South 24 Parganas· #71039
₹8.0 L Completed 5 Sept 2026Rec. 29 Dec 2023Paid ₹8.0 L
17th Lok Sabha MPs from West Bengal
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Kalyan Banerjee · Sreerampur | 100% | 98% | 111 | 99 |
| 2 | Ms Mimi Chakraborty · Jadavpur | 100% | 96% | 250 | 97 |
| 3 | Shri Abhishek Banerjee · Diamond Harbour | 100% | 97% | 149 | 97 |
| 4 | Ms Mahua Moitra · Krishnanagar | 100% | 100% | 27 | 97 |
| 5 | Pratima Mondal · Joynagar | 100% | 97% | 140 | 96 |
| 6 | Smt Sajda Ahmed · Uluberia | 96% | 96% | 180 | 96 |
| 7 | Smt Locket Chatterjee · Hooghly | 100% | 100% | 307 | 96 |
| 8 | Smt Satabdi Roy (Banerjee) · Birbhum | 100% | 99% | 127 | 95 |
| 9 | Shri Kunar Hembram · Jhargram | 100% | 100% | 31 | 95 |
| 10 | Dr Sukanta Majumdar · Balurghat | 94% | 82% | 336 | 95 |
| 11 | Asit Kumar Mal · Bolpur | 100% | 100% | 55 | 94 |
| 12 | Shri Deepak (Dev) Adhikari · Ghatal | 93% | 87% | 195 | 94 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.