2nd of 11 from Kerala
Allocated limit
₹19.61 Cr
Median ₹14.70 Cr
Fund utilisation
74%
₹14.54 Cr recommended · 124 works
Above median (70%)
Paid to vendors
₹6.19 Cr
32% of allocation
Above median (25%)
Works completed
54
44% of recommended
Above median (26%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP124 works
₹14.54 Cr · 74% of the ₹19.61 Cr allocated
- Sanctioned by the district95 works
77% sanctioned · took 6.3 months on average (due within 45 days)
- Completed54 works
₹4.67 Cr final cost · 11.5 months from recommendation on average
29 works are still awaiting sanction, 25 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 124 works worth ₹14.54 Cr, a fund utilisation of 74%, higher than 55% of Rajya Sabha MPs.
- The district has sanctioned 95 of them, taking 6.3 months on average.
- ₹6.19 Cr has been paid to vendors, 32% of the allocation.
- 54 works are complete, typically 11.5 months after recommendation. 45 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 66 vendors. The largest received 6.7%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 65/100: finishing works counts most
- Works completed 30%44Completed ÷ recommended works.
- Spending efficiency 20%75Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%74Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%83Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%32Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SML ISUZU LTD, 6.7% of payments across 66 vendors.
District sanction speed
67/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%67Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
124 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Bridge Across Prappuzha Thodu Between Ward Nos. 04 and 16
Roads & bridgesConstruction of culverts and bridges· Kottayam· #323703
₹50.0 L Awaiting sanction · 11 daysRec. 21 Oct 2026Purchase of School Vehicle for Dr. Rajendra Prasad Memorial LP School, Chottupara, Idukki School Code :30543
Education & librariesPurchase of vans and buses for educational institutions· Idukki· #323715
₹14.0 L Awaiting sanction · 11 daysRec. 21 Oct 2026Construction of Puthan Puratil Mukku Poolakandi Road (Concreting)
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kozhikode· #323721
₹7.0 L Awaiting sanction · 11 daysRec. 21 Oct 2026Construction of Poolakndi Karinkuttimukku Nadukavil Road (Concreting)
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kozhikode· #323722
₹12.0 L Awaiting sanction · 11 daysRec. 21 Oct 2026“Low mast light at the Kayyuri Pumb junction”, Near Sankara Narayana Moorthy temple. In Ward 9, Pallickathodu (GP)Pampady Block, Kottayam (Dist)
Electricity & lightingLighting of public spaces· Kottayam· #149258
₹2.1 L Completed 7 Oct 2026Rec. 24 Oct 2024Paid ₹2.1 L“Low mast light in Challoli junction”, Near Challoli Drinking Water Project Ward 8 , Pallickathodu (GP).Pampady Block, Kottayam(Dist)
Electricity & lightingLighting of public spaces· Kottayam· #149259
₹2.1 L Completed 7 Oct 2026Rec. 24 Oct 2024Paid ₹2.1 L“Low mast light in Parathanam Junction”, Near SNDP Mandiram Ward 12, Pallickathodu (GP)“Low mast light in Parathanam Junction”, Near SNDP Mandiram Ward 12, Pallickathodu (GP)Pampady Block, Kottayam(Dist)
Electricity & lightingLighting of public spaces· Kottayam· #149260
₹2.1 L Completed 7 Oct 2026Rec. 24 Oct 2024Paid ₹2.1 L“Low mast light in Chappath junction”, Near Chappath Water Authority pumping Station in ward 10 Pallickathodu (GP).Pampady Block, Kottayam(Dist)
Electricity & lightingLighting of public spaces· Kottayam· #149261
₹2.1 L Completed 7 Oct 2026Rec. 24 Oct 2024Paid ₹2.1 L“Low mast light in Kurumkudi junction,” Near Kurumkudi Anganwadi&ARFSC Bank. Ward 10 , Pallickathodu (GP),Pampady Block, Kottayam(Dist)
Electricity & lightingLighting of public spaces· Kottayam· #149263
₹2.1 L Completed 7 Oct 2026Rec. 24 Oct 2024Paid ₹2.1 LConstruction of Modern Anganwadi Building with Park Compound wall Purchase of Equipments A W No92 PurathittaWard 9 Pallicathodu GP Pampady Block
Education & librariesConstruction of buildings for crèches and anganwadies· Kottayam· #145191
₹45.0 L Sanctioned · 28 Sept 2026Rec. 3 Oct 2024Low mast light in Kavungumpalam Junction”, Near Anickad church,Ward 4, Pallickathodu (GP),Pampady Block, Kottayam(Dist)
Electricity & lightingLighting of public spaces· Kottayam· #149262
₹2.1 L Completed 28 Sept 2026Rec. 24 Oct 2024Paid ₹2.1 LConstruction of Oravil Parambath Chettiyankandi Road in Ward 05, Ulliyeri GP Balusheri Block Panchayth Kozhikode Concreting
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kozhikode· #178991
₹4.5 L Completed 24 Sept 2026Rec. 4 Mar 2025Paid ₹4.5 LConstruction of Nelliparambu Iruppayimmal Road” (Concreting) in Ward 13, Unnikulam GP, Balussery Block, Kozhikode
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kozhikode· #139208
₹7.4 L Completed 23 Sept 2026Rec. 5 Sep 2024Paid ₹7.4 L“Construction Drainage in Mundakkapoyil Rajagiri Road in Ward 04, Unnikulam (GP), (Balussery BLOCK), Kozhikode
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kozhikode· #144174
₹7.9 L Completed 23 Sept 2026Rec. 28 Sep 2024Paid ₹7.9 LConstruction of High School Ground Road Thrikottur Road (Concreting) in Ward No 17 Thikkodi (GP) Melady (BP) Kozhikode
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kozhikode· #165446
₹2.5 L Completed 22 Sept 2026Rec. 14 Jan 2025Paid ₹2.5 L
Rajya Sabha MPs from Kerala
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Abdul Wahab | 86% | 32% | 132 | 68 |
| 2 | Smt. P. T. Usha | 74% | 32% | 54 | 65 |
| 3 | Smt. Jebi Mather Hisham | 69% | 25% | 52 | 65 |
| 4 | Dr. John Brittas | 94% | 29% | 40 | 63 |
| 5 | Shri A. A. Rahim | 52% | 29% | 33 | 61 |
| 6 | Dr. V. Sivadasan | 98% | 12% | 34 | 60 |
| 7 | Shri Jose K. Mani | 77% | 19% | 45 | 59 |
| 8 | Shri Sandosh Kumar P | 68% | 26% | 40 | 59 |
| 9 | Shri P. P. Suneer | 70% | 17% | 22 | 55 |
| 10 | Shri Haris Beeran | 87% | 17% | 20 | 54 |
| 11 | Shri C. Sadanandan Master | 94% | 0% | 0 | 20 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.