9th of 11 from Kerala
Allocated limit
₹12.43 Cr
Median ₹14.70 Cr
Fund utilisation
70%
₹8.70 Cr recommended · 93 works
About the median
Paid to vendors
₹2.13 Cr
17% of allocation
Below median (25%)
Works completed
22
24% of recommended
Below median (26%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP93 works
₹8.70 Cr · 70% of the ₹12.43 Cr allocated
- Sanctioned by the district59 works
63% sanctioned · took 7.2 months on average (due within 45 days)
- Completed22 works
₹1.27 Cr final cost · 13.0 months from recommendation on average
34 works are still awaiting sanction, 32 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 93 works worth ₹8.70 Cr, a fund utilisation of 70%, higher than 50% of Rajya Sabha MPs.
- The district has sanctioned 59 of them, taking 7.2 months on average.
- ₹2.13 Cr has been paid to vendors, 17% of the allocation.
- 22 works are complete, typically 13.0 months after recommendation. 21 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Education & libraries.
- Payments went to 18 vendors. The largest received 22%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 55/100: finishing works counts most
- Works completed 30%24Completed ÷ recommended works.
- Spending efficiency 20%60Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%70Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%95Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%17Paid to vendors ÷ allocated limit.
- Vendor diversity 10%98How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: VE Commercial Vehicles Ltd, 22% of payments across 18 vendors.
District sanction speed
56/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%56Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
93 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Concreting of Marath Road at Ward-14 ,Othukkungal GP
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #321273
₹2.5 L Sanctioned · 31 Oct 2026Rec. 9 Oct 2026Sanjay Gandhi Road Renovation at Ward-13 Parichakam(North) of Marancheri GP
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #291048
₹15.0 L Sanctioned · 29 Oct 2026Rec. 2 Jul 2026Installation of Solar Mini Mast Light at Ward-17,Palad Junction,Vazhikkadavu GP-Nilambur Block
Electricity & lightingLighting of public spaces· Malappuram· #223195
₹3.0 L Sanctioned · 9 Oct 2026Rec. 23 Aug 2025Tarring of Mangottil Road of ward-14 of Othukkungal GP
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #321274
₹3.5 L Awaiting sanction · 23 daysRec. 9 Oct 2026Concreting and Protection Side wall construction of Kalanchola Colony Road of Ward-3 of Mankada Grama Panchayat
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #321277
₹10.0 L Awaiting sanction · 23 daysRec. 9 Oct 2026Installation of SOlar Mini Mast Light
Electricity & lightingLighting of public spaces· Malappuram· #272476
₹3.0 L Sanctioned · 7 Oct 2026Rec. 15 Mar 2026Installation of Solar Mini Mast Light
Electricity & lightingLighting of public spaces· Malappuram· #272477
₹3.0 L Sanctioned · 7 Oct 2026Rec. 15 Mar 2026Solar Mini Mast Light Installation at Chala Junction of Ward-15,Thripperunthura GP
Electricity & lightingLighting of public spaces· Alappuzha· #161662
₹3.0 L Completed 5 Oct 2026Rec. 5 Jan 2025Paid ₹3.0 LInstallation of SOlar Mini Mast Light at Bunglavu-Karuvankallu Road Junction of ward 27 of Kondotty Municipality
Electricity & lightingLighting of public spaces· Malappuram· #272303
₹3.0 L Sanctioned · 23 Sept 2026Rec. 5 Mar 2026She space and Gym at ward-10 of Thuravur GramaPanchayat,Ernakulam Dist.(Maintenance Only)
Sports & fitnessConstruction of buildings for multi-gym· Ernakulam· #168802
₹2.2 L Completed 14 Sept 2026Rec. 25 Jan 2025Paid ₹2.2 LPurchase of School Van for GLPS,Lakkidi
Education & librariesPurchase of vans and buses for educational institutions· Wayanad· #232309
₹15.4 L Completed 14 Sept 2026Rec. 15 Sep 2025Paid ₹15.4 LINSTALATION OF SOLAR MINI MAST LIGHT AT MUNAMBATH MEENKAL JUNCTION OF WARD-8 OF OTHUKKUNGAL GRAMA PANCHAYAT
Electricity & lightingLighting of public spaces· Malappuram· #243974
₹3.0 L Sanctioned · 5 Sept 2026Rec. 5 Nov 2025INSTALATION OF SOLAR MINI MAST LIGHT AT KIDANGAYATH MANKUZHI JUNCTION,PANTHALLUR-ORAVAMPURAM ROAD SIDE OF WARD-9 OF ANAKKAYAM GRAMAPANCHAYAT
Electricity & lightingLighting of public spaces· Malappuram· #243975
₹3.0 L Sanctioned · 5 Sept 2026Rec. 5 Nov 2025INSTALLATION OF SOLAR MINI MAST LIGHT AT NELLIKKAPPARAMBA JUNCTION NEAR HEALTH SUBCENTRE OF WARD -8 OF KAVANNUR GRAMAPANCHAYAT
Electricity & lightingLighting of public spaces· Malappuram· #243977
₹3.0 L Sanctioned · 5 Sept 2026Rec. 5 Nov 2025Mini School Bus Purchase for Veliyankode GMUPS(Anakath School),Ward-3 of Veliyankode GP
Education & librariesPurchase of vans and buses for educational institutions· Malappuram· #291490
₹16.4 L Sanctioned · 5 Sept 2026Rec. 2 Jul 2026
Rajya Sabha MPs from Kerala
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Abdul Wahab | 86% | 32% | 132 | 68 |
| 2 | Smt. P. T. Usha | 74% | 32% | 54 | 65 |
| 3 | Smt. Jebi Mather Hisham | 69% | 25% | 52 | 65 |
| 4 | Dr. John Brittas | 94% | 29% | 40 | 63 |
| 5 | Shri A. A. Rahim | 52% | 29% | 33 | 61 |
| 6 | Dr. V. Sivadasan | 98% | 12% | 34 | 60 |
| 7 | Shri Jose K. Mani | 77% | 19% | 45 | 59 |
| 8 | Shri Sandosh Kumar P | 68% | 26% | 40 | 59 |
| 9 | Shri P. P. Suneer | 70% | 17% | 22 | 55 |
| 10 | Shri Haris Beeran | 87% | 17% | 20 | 54 |
| 11 | Shri C. Sadanandan Master | 94% | 0% | 0 | 20 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.