1st of 11 from Kerala
Allocated limit
₹31.27 Cr
Median ₹14.70 Cr
Fund utilisation
86%
₹27.01 Cr recommended · 374 works
Above median (70%)
Paid to vendors
₹9.87 Cr
32% of allocation
Above median (25%)
Works completed
132
35% of recommended
Above median (26%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP374 works
₹27.01 Cr · 86% of the ₹31.27 Cr allocated
- Sanctioned by the district249 works
67% sanctioned · took 6.2 months on average (due within 45 days)
- Completed132 works
₹8.79 Cr final cost · 9.7 months from recommendation on average
125 works are still awaiting sanction, 120 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 374 works worth ₹27.01 Cr, a fund utilisation of 86%, higher than 71% of Rajya Sabha MPs.
- The district has sanctioned 249 of them, taking 6.2 months on average.
- ₹9.87 Cr has been paid to vendors, 32% of the allocation.
- 132 works are complete, typically 9.7 months after recommendation. 117 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 127 vendors. The largest received 5.8%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 68/100: finishing works counts most
- Works completed 30%35Completed ÷ recommended works.
- Spending efficiency 20%89Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%86Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%89Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%32Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SML ISUZU LTD, 5.8% of payments across 127 vendors.
District sanction speed
62/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%62Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
374 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of road, retaining wall and drainage at Janathapadi Padikkunnu PVS school- Pattarakka link road or pathway, Ward no. 24, Nilambur Municipality
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #260707
₹28.0 L Sanctioned · 31 Oct 2026Rec. 21 Jan 2026Construction of Side protection and road at Christian church -Lulu mall colony road/pathway, Ward No.19, Pothukkal Panchayat
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #323865
₹15.0 L Sanctioned · 31 Oct 2026Rec. 22 Oct 2026Construction of Vadakkeparamb road or pathway, ward no.16, Manjeri Municipality
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #325409
₹80,000 Awaiting sanction · 1 daysRec. 31 Oct 2026Construction of Vetekkode Harijan Nagar road or pathway, ward No.16, Manjeri Municipality
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #325464
₹1.3 L Awaiting sanction · 1 daysRec. 31 Oct 2026Construction of Thekkechala road or pathway, ward No.16, Manjeri Municipality
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #325465
₹2.9 L Awaiting sanction · 1 daysRec. 31 Oct 2026Purchasing of Smart TV for AMLPS Pullancheri, Manjeri Municipality
Education & librariesPurchase of smart boards, visual display units and projectors· Malappuram· #288726
₹1.0 L Sanctioned · 30 Oct 2026Rec. 24 Jun 2026Construction of Perumunda SC Nagar road or pathway, Ward No. 13, Chaliyar Panchayat
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #325200
₹5.0 L Awaiting sanction · 2 daysRec. 30 Oct 2026Construction of Mattakadu XIME College road or pathway, ward no.12, Kalamassery Municipality
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Ernakulam· #182236
₹15.0 L Sanctioned · 29 Oct 2026Rec. 16 Mar 2025Setting up of High mast light at E Ahmed Sahib Memmorial ground, Ward No. 12, Karulai Panchayat
Electricity & lightingLighting of public spaces· Malappuram· #288727
₹5.3 L Sanctioned · 29 Oct 2026Rec. 24 Jun 2026Construction of Myladi school kunnu road or pathway, Ward No.10, Chaliyar Panchayat
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #323864
₹10.0 L Sanctioned · 29 Oct 2026Rec. 22 Oct 2026Construction of Pelathodi road or pathway, Ward No.23, Kodur Panchayat
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malappuram· #321692
₹3.0 L Sanctioned · 28 Oct 2026Rec. 12 Oct 2026Installation of UWSS Pipeline at Malaparamb area, Ward No.15, Anakayam Panchayat
Drinking waterProviding supply pipelines for drinking water· Malappuram· #324739
₹5.0 L Awaiting sanction · 4 daysRec. 28 Oct 2026Setting up of Minimast light at Eriyad Collegepadi, Ward No. 07, Thiruvali Panchayat
Electricity & lightingLighting of public spaces· Malappuram· #220991
₹2.2 L Completed 24 Oct 2026Rec. 22 Jul 2025Paid ₹2.2 LSetting up of Low mast light at Kumbala town in Kumbala - Badiyidukka road, Ward no.22, Kumbala Panchayat
Electricity & lightingLighting of public spaces· Kasaragod· #182020
₹2.0 L Sanctioned · 22 Oct 2026Rec. 15 Mar 2025Construction of Kandungal Ayyapankunn Chenniparamb road or pathway, Ward no 14, Kodiyathur Panchayat
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kozhikode· #220580
₹10.0 L Sanctioned · 22 Oct 2026Rec. 21 Jul 2025
Rajya Sabha MPs from Kerala
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Abdul Wahab | 86% | 32% | 132 | 68 |
| 2 | Smt. P. T. Usha | 74% | 32% | 54 | 65 |
| 3 | Smt. Jebi Mather Hisham | 69% | 25% | 52 | 65 |
| 4 | Dr. John Brittas | 94% | 29% | 40 | 63 |
| 5 | Shri A. A. Rahim | 52% | 29% | 33 | 61 |
| 6 | Dr. V. Sivadasan | 98% | 12% | 34 | 60 |
| 7 | Shri Jose K. Mani | 77% | 19% | 45 | 59 |
| 8 | Shri Sandosh Kumar P | 68% | 26% | 40 | 59 |
| 9 | Shri P. P. Suneer | 70% | 17% | 22 | 55 |
| 10 | Shri Haris Beeran | 87% | 17% | 20 | 54 |
| 11 | Shri C. Sadanandan Master | 94% | 0% | 0 | 20 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.