Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
65%
₹9.61 Cr recommended · 86 works
Below median (76%)
Paid to vendors
₹9.22 Cr
63% of allocation
Above median (37%)
Works completed
69
80% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP86 works
₹9.61 Cr · 65% of the ₹14.70 Cr allocated
- Sanctioned by the district83 works
97% sanctioned · took 5.9 months on average (due within 45 days)
- Completed69 works
₹7.39 Cr final cost · 6.9 months from recommendation on average
3 works are still awaiting sanction, 3 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 86 works worth ₹9.61 Cr, a fund utilisation of 65%, higher than 32% of 18th Lok Sabha MPs.
- The district has sanctioned 83 of them, taking 5.9 months on average.
- ₹9.22 Cr has been paid to vendors, 63% of the allocation.
- 69 works are complete, typically 6.9 months after recommendation. 63 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 53 vendors. The largest received 7.4%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 80/100: finishing works counts most
- Works completed 30%80Completed ÷ recommended works.
- Spending efficiency 20%80Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%65Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%91Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%63Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Sathess kumar, 7.4% of payments across 53 vendors.
District sanction speed
77/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%77Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
86 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Community Sanitary Complex at Chinnanchettipatti Village in pandalgudi panchayat
Sanitation & drainageConstruction of public toilets and bathrooms· Virudhunagar· #240856
₹10.0 L Work partially Completed · 26 Sept 2026Rec. 24 Oct 2025Paid ₹10.0 LConstruction of additional facilities for the Government Boys Higher Secondary School auditorium in Pandalkudi village and panchayat.
Education & librariesConstruction of rooms and halls in school and colleges· Virudhunagar· #242044
₹10.0 L Work partially Completed · 25 Aug 2026Rec. 11 Feb 2026Paid ₹10.0 LConstruction of Bus stop at N.Mettupatti Village and panchayat
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Virudhunagar· #231792
₹10.0 L Completed 24 Aug 2026Rec. 24 Oct 2025Paid ₹10.0 LConstruction of Bus shelter in P.Kammaipatti Village at Papakudi Panchayat
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Virudhunagar· #288943
₹8.0 L Completed 24 Aug 2026Rec. 30 Jun 2026Paid ₹8.0 LConstruction of community Hall Building in Sengamalapatti Village and panchayat 2024 25
Community buildings & public spacesConstruction of community centers and community halls· Virudhunagar· #242062
₹30.0 L Completed 8 Aug 2026Rec. 11 Feb 2026Paid ₹30.0 LConstruction of Bathtub with borewell at Kanjanaiyakkenpatti Village and panchayat
Sanitation & drainageConstruction of public toilets and bathrooms· Virudhunagar· #231764
₹6.0 L Completed 7 Aug 2026Rec. 24 Oct 2025Paid ₹6.0 LConstruction of PDS Building in Thenpalai Village and Puliyooran panchayat
Safety & securityConstruction of Government office buildings (Post office, Police station, Police chauki, etc.)· Virudhunagar· #242035
₹11.0 L Completed 7 Aug 2026Rec. 24 Oct 2025Paid ₹11.0 LConstruction of Waiting shed and bath tub with borewell in Burial ground at Pudhukottai Village and Panchayat
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Virudhunagar· #260750
₹10.0 L Completed 7 Aug 2026Rec. 29 Jan 2026Paid ₹10.0 LConstruction of Kalaiarangam at Soorakkulam Village and Panchayat in Thiruparankundram Block. (Additional Fund)
Community buildings & public spacesConstruction of community centers and community halls· Madurai· #295239
₹5.0 L Physical Inspection · 15 Jul 2026Rec. 15 Jul 2026Paid ₹5.0 LConstruction of Bus Shelter at SadaiyaKavundanpatti Village at Mathipanur Panchayat.
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Madurai· #295260
₹7.5 L Awaiting sanction · 109 daysRec. 15 Jul 2026Construction of Passenger shelter in Moolipatti Village and Panchayat (2024-2025)
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Virudhunagar· #269387
₹9.0 L Physical Inspection · 7 Jul 2026Rec. 30 Jun 2026Paid ₹9.0 LProviding New Bore well with Pipe line and Bathing Tub at Sankaralingapuram Village and Panchayat
Sanitation & drainageConstruction of public toilets and bathrooms· Virudhunagar· #269417
₹7.5 L Physical Inspection · 7 Jul 2026Rec. 30 Jun 2026Paid ₹7.5 LSupply and Erection of 10 Nos 30W and 2 Nos 120W LED light lamp fittings in ward No 13 at Virudhunagar Municipality
Electricity & lightingLighting of public spaces· Virudhunagar· #269416
₹1.2 L Work partially Completed · 30 Jun 2026Rec. 30 Jun 2026Paid ₹1.2 LConstruction of community hall near Sivan kovil at A.Kokkulam village and Panchayat
Community buildings & public spacesConstruction of community centers and community halls· Madurai· #195862
₹25.0 L Physical Inspection · 25 Jun 2026Rec. 1 Jul 2025Paid ₹25.0 LConstruction of Bus shelter at Koothiyarkundu - Aastinpatti Highway Junction in Uchapatti panchayat.
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Madurai· #207544
₹7.5 L Physical Inspection · 25 Jun 2026Rec. 1 Jul 2025Paid ₹7.0 L
18th Lok Sabha MPs from Tamil Nadu
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Dr Rani Sri Kumar · Tenkasi | 88% | 66% | 117 | 83 |
| 2 | V S Matheswaran · Namakkal | 79% | 62% | 150 | 82 |
| 3 | Tharaniventhan M S · Arani | 94% | 67% | 203 | 81 |
| 4 | Manickam Tagore B · Virudhunagar | 65% | 63% | 69 | 80 |
| 5 | Ganesan Selvam · Kancheepuram | 91% | 59% | 278 | 80 |
| 6 | CN Annadurai · Tiruvannamalai | 71% | 62% | 175 | 79 |
| 7 | K Subbarayan · Tiruppur | 94% | 57% | 65 | 76 |
| 8 | Gopinath K · Krishnagiri | 57% | 34% | 67 | 76 |
| 9 | Robert Bruce C · Tirunelveli | 95% | 49% | 76 | 76 |
| 10 | K E Prakash · Erode | 78% | 59% | 141 | 75 |
| 11 | M.K. Vishnuprasad · Cuddalore | 70% | 53% | 74 | 74 |
| 12 | Murasoli S · Thanjavur | 97% | 54% | 48 | 74 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.