5th of 40 from Bihar
Allocated limit
₹19.49 Cr
Median ₹14.70 Cr
Fund utilisation
92%
₹17.92 Cr recommended · 373 works
Above median (76%)
Paid to vendors
₹14.47 Cr
74% of allocation
Above median (37%)
Works completed
270
72% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP373 works
₹17.92 Cr · 92% of the ₹19.49 Cr allocated
- Sanctioned by the district321 works
86% sanctioned · took 3.5 months on average (due within 45 days)
- Completed270 works
₹13.40 Cr final cost · 5.1 months from recommendation on average
52 works are still awaiting sanction, 31 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 373 works worth ₹17.92 Cr, a fund utilisation of 92%, higher than 77% of 18th Lok Sabha MPs.
- The district has sanctioned 321 of them, taking 3.5 months on average.
- ₹14.47 Cr has been paid to vendors, 74% of the allocation.
- 270 works are complete, typically 5.1 months after recommendation. 109 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Sports & fitness.
- Payments went to 15 vendors. The largest received 27%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 77/100: finishing works counts most
- Works completed 30%72Completed ÷ recommended works.
- Spending efficiency 20%93Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%92Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%40Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%74Paid to vendors ÷ allocated limit.
- Vendor diversity 10%92How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Gyan Ganga, 27% of payments across 15 vendors.
District sanction speed
86/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%86Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
373 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Installation of High Mast Light
Electricity & lightingLighting of public spaces· Munger· #322190
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Munger· #322194
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Munger· #322198
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Munger· #322199
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Munger· #322203
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Munger· #322205
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Near Sainik Chowk, Raipura
Electricity & lightingLighting of public spaces· Munger· #322208
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Munger· #322211
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Jamui· #322215
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Jamui· #322217
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Jamui· #322219
₹9.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Installation of High Mast Light
Electricity & lightingLighting of public spaces· Jamui· #285177
₹9.4 L Completed 9 Oct 2026Rec. 12 Jun 2026Paid ₹9.4 LInstallation of High Mast Light
Electricity & lightingLighting of public spaces· Jamui· #285182
₹9.4 L Completed 9 Oct 2026Rec. 12 Jun 2026Paid ₹9.4 LInstallation of High Mast Light
Electricity & lightingLighting of public spaces· Jamui· #285184
₹9.4 L Completed 9 Oct 2026Rec. 12 Jun 2026Paid ₹9.4 LInstallation of High Mast Light
Electricity & lightingLighting of public spaces· Jamui· #285197
₹9.4 L Completed 9 Oct 2026Rec. 12 Jun 2026Paid ₹9.4 L
18th Lok Sabha MPs from Bihar
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Raj Bhushan Choudhary · Muzaffarpur | 97% | 81% | 80 | 81 |
| 2 | Giridhari Yadav · Banka | 98% | 79% | 94 | 81 |
| 3 | Rajesh Verma · Khagaria | 56% | 52% | 67 | 79 |
| 4 | Jitan Ram Manjhi · Gaya | 77% | 46% | 194 | 78 |
| 5 | Arun Bharti · Jamui | 92% | 74% | 270 | 77 |
| 6 | Kaushalendra Kumar · Nalanda | 57% | 37% | 118 | 76 |
| 7 | Smt Veena Devi · Vaishali | 100% | 89% | 30 | 76 |
| 8 | Radha Mohan Singh · Purvi Champaran | 89% | 47% | 68 | 74 |
| 9 | Vijaylakshmi Devi · Siwan | 97% | 95% | 95 | 74 |
| 10 | Ravi Shankar Prasad · Patna Sahib | 48% | 40% | 60 | 72 |
| 11 | Dr Mohammad Jawed · Kishanganj | 89% | 65% | 130 | 72 |
| 12 | Ajay Kumar Mandal · Bhagalpur | 58% | 54% | 59 | 71 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.