7th of 28 from Karnataka
Allocated limit
₹7.36 Cr
Median ₹8.60 Cr
Fund utilisation
99%
₹7.29 Cr recommended · 122 works
About the median
Paid to vendors
₹6.35 Cr
86% of allocation
About the median
Works completed
88
72% of recommended
Below median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP122 works
₹7.29 Cr · 99% of the ₹7.36 Cr allocated
- Sanctioned by the district112 works
92% sanctioned · took 13.1 months on average (due within 45 days)
- Completed88 works
₹4.99 Cr final cost · 15.5 months from recommendation on average
10 works are still awaiting sanction, 10 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 122 works worth ₹7.29 Cr, a fund utilisation of 99%, higher than 60% of 17th Lok Sabha MPs.
- The district has sanctioned 112 of them, taking 13.1 months on average.
- ₹6.35 Cr has been paid to vendors, 86% of the allocation.
- 88 works are complete, typically 15.5 months after recommendation. 88 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 59 vendors. The largest received 19%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 86/100: finishing works counts most
- Works completed 30%72Completed ÷ recommended works.
- Spending efficiency 20%79Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%99Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%86Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: NIRMITHI KENDRA CHAMARAJANAGAR, 19% of payments across 59 vendors.
District sanction speed
46/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%46Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
122 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Constrution of Dr Shree Malle Mahadeshwara Swamy Betta Nayakara Community Hall Mahadeshwarabetta Village
Community buildings & public spacesConstruction of community centers and community halls· Chamarajanagar· #65188
₹5.0 L Physical Inspection · 16 Oct 2026Rec. 15 Dec 2023Paid ₹5.0 LBuilding Construction at Badanavalu Village Government High School (Toilet Room & Water Fecility)
Community buildings & public spacesConstruction of community centers and community halls· Mysuru· #65495
₹4.8 L Completed 14 Oct 2026Rec. 18 Dec 2023Paid ₹4.8 LConstruction of Maharshi Valmiki Samudaya Bhavana
Community buildings & public spacesConstruction of community centers and community halls· Chamarajanagar· #65247
₹5.0 L Physical Inspection · 19 Sept 2026Rec. 18 Dec 2023Paid ₹5.0 LBuilding Construction at Chamarajanagar Pathrakarthara Sangha (Paper Editor Offcie)
Community buildings & public spacesConstruction of community centers and community halls· Chamarajanagar· #66430
₹10.0 L Completed 1 Sept 2026Rec. 18 Dec 2023Paid ₹10.0 LConstruction of Press Reporters Building at Hanuru Town
Community buildings & public spacesConstruction of community centers and community halls· Chamarajanagar· #64781
₹5.0 L Work partially Completed · 18 Aug 2026Rec. 18 Dec 2023Paid ₹3.8 LBuilding Constrution at Yalandur Town Savitha Samaja Building
Community buildings & public spacesConstruction of community centers and community halls· Chamarajanagar· #65259
₹5.0 L Completed 13 Aug 2026Rec. 15 Dec 2023Paid ₹5.0 LBuilding Construction at Mudala Agrahara Village Kambaleshwara Samudaya Bhavana
Community buildings & public spacesConstruction of community centers and community halls· Chamarajanagar· #67058
₹10.0 L Completed 13 Aug 2026Rec. 21 Dec 2023Paid ₹10.0 LConstrution of Basava Bhavan in Kilagere Village
Community buildings & public spacesConstruction of community centers and community halls· Chamarajanagar· #65265
₹5.0 L Completed 1 Jan 2026Rec. 15 Dec 2023Paid ₹5.0 LConstruction of Basava Bhavana Building
Community buildings & public spacesConstruction of community centers and community halls· Mysuru· #65270
₹5.0 L Completed 26 Dec 2025Rec. 18 Dec 2023Paid ₹5.0 LRoad Construction at Hallare Village Kere Road to Kongalli Road
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Mysuru· #65467
₹4.9 L Completed 26 Dec 2025Rec. 18 Dec 2023Paid ₹4.9 LConstrution of Valmiki Community Hall Ongoing Work in Harathale Village
Community buildings & public spacesConstruction of community centers and community halls· Mysuru· #65190
₹5.0 L Physical Inspection · 26 Nov 2025Rec. 15 Dec 2023Paid ₹5.0 LBus stand construction at Gattavadi pura Vi
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Mysuru· #66090
₹5.0 L Completed 19 Nov 2025Rec. 18 Dec 2023Paid ₹5.0 LBuilding Construction at Hullahalli Village Dr.B.R.Ambedkar Samudaya Bhavana
Community buildings & public spacesConstruction of community centers and community halls· Mysuru· #68208
₹25.0 L Completed 14 Nov 2025Rec. 21 Dec 2023Paid ₹25.0 LConstrution of Harijan Colony Sharandi Works in Shiramalli Village, Nanjangud Tq
Community buildings & public spacesConstruction of community centers and community halls· Mysuru· #65193
₹5.0 L Completed 13 Nov 2025Rec. 15 Dec 2023Paid ₹5.0 LBuilding Construction at Magge Village Namadhari Samudaya Bhavana
Community buildings & public spacesConstruction of community centers and community halls· Mysuru· #67100
₹10.0 L Completed 5 Nov 2025Rec. 21 Dec 2023Paid ₹10.0 L
17th Lok Sabha MPs from Karnataka
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Gowdar Mallikarjunappa Siddeshwara · Davanagere | 90% | 90% | 72 | 97 |
| 2 | Parvatagouda Chandanagouda Gaddigoudar · Bagalkot | 98% | 93% | 140 | 94 |
| 3 | Shri Nalin Kumar Kateel · Dakshina Kannada | 99% | 94% | 98 | 93 |
| 4 | Doddaalahalli Kempegowda Suresh · Bangalore Rural | 99% | 99% | 80 | 89 |
| 5 | Km Shobha Karandlaje · Udupi Chikmagalur | 100% | 90% | 160 | 87 |
| 6 | Prajwal Revanna · Hassan | 87% | 80% | 208 | 87 |
| 7 | V Srinivas Prasad · Chamarajanagar | 99% | 86% | 88 | 86 |
| 8 | Pralhad Venkatesh Joshi · Dharwad | 100% | 70% | 104 | 83 |
| 9 | Shri DV Sadananda Gowda · Bangalore North | 100% | 99% | 204 | 83 |
| 10 | Shri Gangasandra Siddappa Basavaraj · Tumkur | 100% | 86% | 154 | 81 |
| 11 | Shri B Y Raghavendra · Shimoga | 94% | 90% | 157 | 80 |
| 12 | Bache BN Gowda · Chikballapur | 100% | 95% | 116 | 80 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.