Allocated limit

₹5.13 Cr

Median ₹8.60 Cr

Fund utilisation

90%

₹4.60 Cr recommended · 72 works
Below median (98%)

Paid to vendors

₹4.60 Cr

90% of allocation
About the median

Works completed

72

100% of recommended
Above median (83%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP72 works

    ₹4.60 Cr · 90% of the ₹5.13 Cr allocated

  2. Sanctioned by the district72 works

    100% sanctioned · took 3.7 months on average (due within 45 days)

  3. Completed72 works

    ₹4.60 Cr final cost · 28.6 months from recommendation on average

In plain words

What the numbers say

  • Recommended 72 works worth ₹4.60 Cr, a fund utilisation of 90%, higher than 17% of 17th Lok Sabha MPs.
  • The district has sanctioned 72 of them, taking 3.7 months on average.
  • ₹4.60 Cr has been paid to vendors, 90% of the allocation.
  • 72 works are complete, typically 28.6 months after recommendation. 71 works have geo-tagged photos on eSAKSHI.
  • The largest share of funds went to Education & libraries.
  • Payments went to 46 vendors. The largest received 14%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 97/100: finishing works counts most

  1. Works completed 30%100Completed ÷ recommended works.
  2. Spending efficiency 20%100Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%90Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%99Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%90Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    100
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: NIRMITHI KENDRA DAVANGERE, 14% of payments across 46 vendors.

District sanction speed

89/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%89Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

72 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Construction of Toilet Block to Government Higher Primary School at Site No.:18, Hiremallanahole Village, Jagalur Taluk.

    Sanitation & drainageConstruction of toilet blocks· Davanagere· #86824

    ₹5.0 L Completed 9 Oct 2026Rec. 22 Jan 2024Paid ₹5.0 L
  • Construction work of bus-stand at Site No.:675, Near Daddimane of Mayakonda village, Davangere Taluku (Mayakonda Assembly Constituency).

    Community buildings & public spacesConstruction of bus-sheds or bus-stops· Davanagere· #103267

    ₹4.0 L Completed 2 Sept 2026Rec. 12 Feb 2024Paid ₹4.0 L
  • Installation if High-Mast Electric Light in the Beside K.K. Road at Shantisagara Village, Channagiri taluk, Davanagere Dist.

    Electricity & lightingStreet lights· Davanagere· #61791

    ₹2.0 L Completed 28 Aug 2026Rec. 14 Dec 2023Paid ₹2.0 L
  • Construction of School Room to Government Upgraded Higher Primary School at Echagatta village, Davanagere taluk, Davanagere Dist.

    Education & librariesConstruction of rooms and halls in school and colleges· Davanagere· #61826

    ₹8.8 L Completed 28 Aug 2026Rec. 14 Dec 2023Paid ₹8.8 L
  • Construction of school room to Government Upgraded Higher Primary School at Site No.:175, Kempanahalli Village (Navilehal Gram Panchayat), Channagiri Taluk (Mayakonda Assembly Constituency).

    Education & librariesConstruction of rooms and halls in school and colleges· Davanagere· #86821

    ₹8.8 L Completed 28 Aug 2026Rec. 22 Jan 2024Paid ₹8.8 L
  • Construction of Air theater for cultural activities in Government Higher Primary School Premises at Jammapura Village.

    Community buildings & public spacesConstruction of buildings for community cultural activities· Davanagere· #38226

    ₹2.9 L Completed 27 Aug 2026Rec. 18 Oct 2023Paid ₹2.9 L
  • Construction of School room to Government Higher Primary School, Benkikere village, Channagiri taluk, Davanagere Dist.,

    Education & librariesConstruction of rooms and halls in school and colleges· Davanagere· #47987

    ₹8.3 L Completed 27 Aug 2026Rec. 9 Nov 2023Paid ₹8.3 L
  • Construction of School room to Government Boys Higher Primary School at Hodigere village, Channagiri taluk, Davanagere Dist.

    Education & librariesConstruction of rooms and halls in school and colleges· Davanagere· #61825

    ₹9.2 L Completed 27 Aug 2026Rec. 14 Dec 2023Paid ₹9.2 L
  • Installation of 500 ltrs Capacity Drinking Water R.O. Plant at Government First Grade College, Harihara town.

    Drinking waterInstalling community drinking water plants· Davanagere· #86534

    ₹5.4 L Completed 25 Aug 2026Rec. 22 Jan 2024Paid ₹5.4 L
  • Construction work of bus-stand at Site No.:510, Near Ganesha temple of Mayakonda village, Davangere Taluku (Mayakonda Assembly Constituency).

    Community buildings & public spacesConstruction of bus-sheds or bus-stops· Davanagere· #103266

    ₹4.0 L Completed 25 Aug 2026Rec. 12 Feb 2024Paid ₹4.0 L
  • Construction of School room to Government School at site No: 453 Channapura village, Channagiri taluk.

    Education & librariesConstruction of rooms and halls in school and colleges· Davanagere· #98196

    ₹10.0 L Completed 15 May 2026Rec. 6 Feb 2024Paid ₹10.0 L
  • Construction of School room for Government Higher Primary School at Hosakolenahalli village, Davanagere Taluk.

    Education & librariesConstruction of rooms and halls in school and colleges· Davanagere· #35734

    ₹9.7 L Completed 18 Apr 2026Rec. 11 Oct 2023Paid ₹9.7 L
  • Construction of Open air theater for cultural activities at Sogilu Village.

    Community buildings & public spacesConstruction of buildings for community cultural activities· Davanagere· #38153

    ₹7.3 L Completed 18 Apr 2026Rec. 18 Oct 2023Paid ₹7.3 L
  • Construction of Toilet block to Pre University college, Belaguthi.

    Sanitation & drainageConstruction of toilet blocks· Davanagere· #38154

    ₹6.9 L Completed 18 Apr 2026Rec. 18 Oct 2023Paid ₹6.9 L
  • Construction of School room for Government Higher Primary School, Singatagere village.

    Education & librariesConstruction of rooms and halls in school and colleges· Davanagere· #38157

    ₹8.8 L Completed 18 Apr 2026Rec. 18 Oct 2023Paid ₹8.8 L

17th Lok Sabha MPs from Karnataka

Ranked by MP score

#MPUtilisationSpentCompletedScore
1Gowdar Mallikarjunappa Siddeshwara · Davanagere90%90%7297
2Parvatagouda Chandanagouda Gaddigoudar · Bagalkot98%93%14094
3Shri Nalin Kumar Kateel · Dakshina Kannada99%94%9893
4Doddaalahalli Kempegowda Suresh · Bangalore Rural99%99%8089
5Km Shobha Karandlaje · Udupi Chikmagalur100%90%16087
6Prajwal Revanna · Hassan87%80%20887
7V Srinivas Prasad · Chamarajanagar99%86%8886
8Pralhad Venkatesh Joshi · Dharwad100%70%10483
9Shri DV Sadananda Gowda · Bangalore North100%99%20483
10Shri Gangasandra Siddappa Basavaraj · Tumkur100%86%15481
11Shri B Y Raghavendra · Shimoga94%90%15780
12Bache BN Gowda · Chikballapur100%95%11680

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.