Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
100%
₹14.67 Cr recommended · 191 works
Above median (76%)
Paid to vendors
₹10.37 Cr
71% of allocation
Above median (37%)
Works completed
107
56% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP191 works
₹14.67 Cr · 100% of the ₹14.70 Cr allocated
- Sanctioned by the district146 works
76% sanctioned · took 3.1 months on average (due within 45 days)
- Completed107 works
₹9.51 Cr final cost · 4.8 months from recommendation on average
45 works are still awaiting sanction, 45 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 191 works worth ₹14.67 Cr, a fund utilisation of 100%, higher than 97% of 18th Lok Sabha MPs.
- The district has sanctioned 146 of them, taking 3.1 months on average.
- ₹10.37 Cr has been paid to vendors, 71% of the allocation.
- 107 works are complete, typically 4.8 months after recommendation. 60 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 121 vendors. The largest received 10%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 75/100: finishing works counts most
- Works completed 30%56Completed ÷ recommended works.
- Spending efficiency 20%92Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%52Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%71Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: BKM Enterprises, 10% of payments across 121 vendors.
District sanction speed
81/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%81Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
195 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Flood Protection work at Sido Village in East Siang District
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· East Siang· #296437
₹4.0 L Sanctioned · 30 Oct 2026Rec. 18 Jul 2026Flood control work at Hite WRC area, Ledum in East Siang District
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· East Siang· #304254
₹4.0 L Sanctioned · 30 Oct 2026Rec. 16 Aug 2026Construction of Drain at Rayang Village in East Siang District
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· East Siang· #304393
₹6.0 L Sanctioned · 30 Oct 2026Rec. 16 Aug 2026Construction of MIC at Gorang agri area at Ngopok Village in East Siang District
Irrigation, flood & environmentConstruction of public irrigation facilities· East Siang· #314675
₹3.0 L Sanctioned · 30 Oct 2026Rec. 13 Sep 2026Construction of Fence wall at Yabe area, Remi Village in East Siang District
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· East Siang· #296395
₹6.0 L Time Estimation · 29 Oct 2026Rec. 18 Jul 2026Construction of MIC at Peneng WRC area, Bilat Village in East Siang District
Irrigation, flood & environmentEstablishing public lift irrigation projects· East Siang· #296396
₹5.0 L Work partially Completed · 29 Oct 2026Rec. 18 Jul 2026Construction of Link Road at Danang area, Remi Village in East Siang District
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· East Siang· #296398
₹4.0 L Work partially Completed · 29 Oct 2026Rec. 18 Jul 2026Construction of Culvert at Latu Rikmeng Nallah, Mirem Village in East Siang District
Roads & bridgesConstruction of culverts and bridges· East Siang· #296405
₹10.0 L Work partially Completed · 29 Oct 2026Rec. 18 Jul 2026Flood Protection work to protect Tanyo WRC area, Bamin-Bilat in East Siang District
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· East Siang· #296406
₹4.0 L Work partially Completed · 29 Oct 2026Rec. 18 Jul 2026Construction of MIC at Yabe cultivation area, Miglung Village in East Siang District
Irrigation, flood & environmentEstablishing public lift irrigation projects· East Siang· #296409
₹5.0 L Work partially Completed · 29 Oct 2026Rec. 18 Jul 2026Construction of fence wall at Depi Village in East Siang District
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· East Siang· #296416
₹4.0 L Work partially Completed · 29 Oct 2026Rec. 18 Jul 2026Construction of Link Road at 10th Mile, Oyan in East Siang District
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· East Siang· #304252
₹8.0 L Work partially Completed · 29 Oct 2026Rec. 16 Aug 2026Construction of RLR at Oyan Village in East Siang District
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· East Siang· #314661
₹5.0 L Work partially Completed · 29 Oct 2026Rec. 13 Sep 2026Construction of Approach Road from Suka Nallah to Rajer Kheti in Lohit District
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Lohit· #304251
₹7.0 L Sanctioned · 28 Oct 2026Rec. 16 Aug 2026Construction of fence wall near Gangging at Kapong Village, Mengkeng Miri in Namsai District
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Namsai· #314689
₹3.0 L Sanctioned · 22 Oct 2026Rec. 13 Sep 2026
18th Lok Sabha MPs from Arunachal Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Kiren Rijiju · Arunachal West | 81% | 62% | 126 | 80 |
| 2 | Shri Tapir Gao · Arunachal East | 100% | 71% | 107 | 75 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.