Allocated limit
₹15.20 Cr
Median ₹14.70 Cr
Fund utilisation
59%
₹9.01 Cr recommended · 187 works
Below median (76%)
Paid to vendors
₹6.98 Cr
46% of allocation
Above median (37%)
Works completed
74
40% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP187 works
₹9.01 Cr · 59% of the ₹15.20 Cr allocated
- Sanctioned by the district177 works
95% sanctioned · took 32 days on average (due within 45 days)
- Completed74 works
₹3.70 Cr final cost · 5.9 months from recommendation on average
10 works are still awaiting sanction, 7 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 187 works worth ₹9.01 Cr, a fund utilisation of 59%, higher than 22% of 18th Lok Sabha MPs.
- The district has sanctioned 177 of them, taking 32 days on average.
- ₹6.98 Cr has been paid to vendors, 46% of the allocation.
- 74 works are complete, typically 5.9 months after recommendation. 69 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 131 vendors. The largest received 7.2%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 60/100: finishing works counts most
- Works completed 30%40Completed ÷ recommended works.
- Spending efficiency 20%53Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%59Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%93Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%46Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: gagan book supplier, 7.2% of payments across 131 vendors.
District sanction speed
98/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%98Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
187 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
CC Road Nirman
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Rajnandgaon· #322979
₹5.0 L Vendor Identification · 29 Oct 2026Rec. 16 Oct 2026Paid ₹2.5 LWard 01 ke Samdayik Bhavan me Tin Shed Nirman
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Rajnandgaon· #316900
₹5.0 L Vendor Identification · 16 Oct 2026Rec. 22 Sep 2026Paid ₹2.5 LBoundary Wall Nirman (Shri Ram Gaushala ke pas)
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Rajnandgaon· #322977
₹2.5 L Awaiting sanction · 16 daysRec. 16 Oct 2026CC Road Nirman (Awas para me)
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Rajnandgaon· #322978
₹5.0 L Awaiting sanction · 16 daysRec. 16 Oct 2026Sahityapara ke Samudayik Bhavan me ahata nirman
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Rajnandgaon· #322981
₹2.0 L Awaiting sanction · 16 daysRec. 16 Oct 2026Shed Nirman work in karma samudayik Bhavan
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Rajnandgaon· #278459
₹5.0 L Completed 25 Sept 2026Rec. 17 Apr 2026Paid ₹5.0 LSamudayik Bhavan Me Jirnodhar Kary ward 05 me
Community buildings & public spacesConstruction of community centers and community halls· Rajnandgaon· #278779
₹2.0 L Completed 25 Sept 2026Rec. 21 Apr 2026Paid ₹2.0 LCC Road (Bajar Chaok)
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Rajnandgaon· #313584
₹5.0 L Vendor Identification · 22 Sept 2026Rec. 9 Sep 2026Paid ₹2.5 LSamudayik Bhavan Nirman (Shitla Para)
Community buildings & public spacesConstruction of community centers and community halls· Rajnandgaon· #313585
₹5.0 L Sanctioned · 22 Sept 2026Rec. 9 Sep 2026For the installation of lights
Electricity & lightingLighting of public spaces· Rajnandgaon· #313604
₹2.5 L Vendor Identification · 22 Sept 2026Rec. 9 Sep 2026Paid ₹1.3 LFor the installation of lights
Electricity & lightingLighting of public spaces· Rajnandgaon· #313605
₹2.5 L Vendor Identification · 22 Sept 2026Rec. 9 Sep 2026Paid ₹1.3 LPM Shri Atma Nand Hindi & English Medium School CCTV Camera Installation
Safety & securityProviding CCTV camera system for security of public areas· Mohla-Manpur-Ambagarh Chouki· #312968
₹3.5 L Awaiting sanction · 55 daysRec. 7 Sep 2026CC Road Nirman Ward 06
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Rajnandgaon· #277626
₹5.0 L Completed 1 Sept 2026Rec. 7 Apr 2026Paid ₹5.0 LMaidan Samtali karan
Sports & fitnessDevelopment of playfields and sports grounds· Rajnandgaon· #239146
₹7.0 L Completed 24 Aug 2026Rec. 30 Sep 2025Paid ₹7.0 LSamudayik Bhavan me Ahata nirman (yadav para me)
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Rajnandgaon· #275637
₹3.0 L Vendor Identification · 20 Aug 2026Rec. 24 Mar 2026Paid ₹1.3 L
18th Lok Sabha MPs from Chhattisgarh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Kamlesh Jangde · Janjgir Champa | 92% | 68% | 261 | 79 |
| 2 | Jyotsna Charandas Mahant · Korba | 84% | 51% | 152 | 68 |
| 3 | Radhe Shyam Rathiya · Raigarh | 87% | 55% | 77 | 67 |
| 4 | Roop Kumari Choudhary · Mahasamund | 80% | 54% | 82 | 64 |
| 5 | Santosh Pandey · Rajnandgaon | 59% | 46% | 74 | 60 |
| 6 | Vijay Baghel · Durg | 96% | 50% | 71 | 59 |
| 7 | Chintamani Maharaj · Sarguja | 70% | 45% | 94 | 57 |
| 8 | Mahesh Kashyap · Bastar | 87% | 46% | 48 | 55 |
| 9 | Tokhan Sahu · Bilaspur | 72% | 40% | 46 | 55 |
| 10 | Brijmohan Agrawal · Raipur | 87% | 47% | 38 | 52 |
| 11 | Bhojraj Nag · Kanker | 49% | 24% | 31 | 51 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.