37th of 42 from West Bengal
Allocated limit
₹7.05 Cr
Median ₹8.60 Cr
Fund utilisation
100%
₹7.05 Cr recommended · 57 works
About the median
Paid to vendors
₹5.69 Cr
81% of allocation
Below median (88%)
Works completed
34
60% of recommended
Below median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP57 works
₹7.05 Cr · 100% of the ₹7.05 Cr allocated
- Sanctioned by the district57 works
100% sanctioned · took 4.1 months on average (due within 45 days)
- Completed34 works
₹3.74 Cr final cost · 17.9 months from recommendation on average
In plain words
What the numbers say
- Recommended 57 works worth ₹7.05 Cr, a fund utilisation of 100%, higher than 85% of 17th Lok Sabha MPs.
- The district has sanctioned 57 of them, taking 4.1 months on average.
- ₹5.69 Cr has been paid to vendors, 81% of the allocation.
- 34 works are complete, typically 17.9 months after recommendation. 34 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Education & libraries.
- Payments went to 50 vendors. The largest received 12%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 79/100: finishing works counts most
- Works completed 30%60Completed ÷ recommended works.
- Spending efficiency 20%66Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%81Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: FUTURE AUTOMOBILE AGENCY PVT LTD, 12% of payments across 50 vendors.
District sanction speed
88/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%88Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
57 works · tap “Photos” to see geo-tagged photos from eSAKSHI
PURCHASE AND INSTALLATION(INCLUDING FITTINGS WITH ELECTRICAL WIRING) OF NEW COMPUTER, COMPUTER TABLES, PRINTER WITH SCANNER, CCTV CAMERA, PROJECTOR SET WITH SCREEN, NON-CONVENTIONAL ENERGY (SOLAR PANELS) SYSTEM, AND CHANGING OF PIPELINES FOR DRINKING WATER SUPPLY AT BALLYGUNGE VIDYALAYA & SILPA SIKSHAYATAN, 14, BALLYGUNGE PLACE, KOLKATA-700019, WARD 68.
Education & librariesPurchase of IT systems, including hardware and software for educational purposes· Kolkata· #95360
₹14.6 L Completed 23 Mar 2026Rec. 3 Feb 2024Paid ₹14.6 LDEVELOPMENT OF POND INCLUDING BULLAH PILING AT RAMCHANDRA PALLY POND KMC WARD 123 UNDER BR XVI.
Irrigation, flood & environmentRenovation of ponds and lakes· Kolkata· #82288
₹14.8 L Completed 14 Mar 2026Rec. 15 Jan 2024Paid ₹14.8 LDEVELOPMENT OF MYSORE GARDEN BY INSTALLATION OF FOUNTAIN SYSTEMS ALONG WITH LIGHTING ARRANGEMENTS, LOCATED AT KABISEKHAR KALIDAS ROY ROAD (TOLLYGUNGE ROAD) KOLKATA - 700026, ADJACENT TO KEORATALA BURNING GHAT IN KMC WARD NO. 88, BOROUGH - VIII.
Community buildings & public spacesDevelopment of public parks· Kolkata· #101816
₹13.4 L Completed 21 Feb 2026Rec. 10 Feb 2024Paid ₹13.4 LDEVELOPMENT OF STREET LIGHTING SYSTEM AT R.K. CHATTERJEE ROAD, BOSEPUKUR ROAD,SARAT GHOSH GARDEN ROAD & BANERJEE PARA ROAD IN KMC WARD 91.
Electricity & lightingStreet lights· Kolkata· #64524
₹7.4 L Completed 12 Feb 2026Rec. 18 Dec 2023Paid ₹7.4 LDEVELOPMENT OF JOKA NIMNA BUNIARY BIDYALAY HANSPUKUR, POST - JOKA, KOLKATA - 104, WARD 144.
Education & librariesConstruction of rooms and halls in school and colleges· Kolkata· #27589
₹8.7 L Completed 11 Feb 2026Rec. 27 Sep 2023Paid ₹8.7 LDEVELOPMENT WORK OF CHAKRAMNAGAR ABAITANIK PRATHAMIK BIDYALAY AT P.O. - R.C. THAKURANI, P.S.-HARIDEVPUR,KOLKATA-700104,IN KMC WARD 142.
Education & librariesConstruction of rooms and halls in school and colleges· Kolkata· #64556
₹10.0 L Completed 11 Feb 2026Rec. 18 Dec 2023Paid ₹10.0 LCONSTRUCTION OF BOUNDARY WALL, APPROACH, SANITARY, TILING, AND OTHER ALLIED WORKS OF COMMUNITY HALL AT 9/1A, A.J.C.BOSE ROAD, KOLKATA - 700017, IN WARD 63.
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Kolkata· #27588
₹24.9 L Completed 7 Feb 2026Rec. 27 Sep 2023Paid ₹24.9 LDEVELOPMENT OF FOOTPATH (CEMENT CONCRETE FOOTPATH & CHANNEL WORK) AT 2, LOWER RANGE TO 18, LOWER RANGE IN KMC WARD 64.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kolkata· #64554
₹4.4 L Completed 7 Feb 2026Rec. 18 Dec 2023Paid ₹4.4 LDEVELOPMENT OF FOOTPATH (CEMENT CONCRETE FOOTPATH & CHANNEL WORK) AT BOTH SIDES OF MEHER ALI ROAD IN KMC WARD 64.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kolkata· #64555
₹4.5 L Completed 7 Feb 2026Rec. 18 Dec 2023Paid ₹4.5 LCONSTRUCTION OF PATHWAYS BY PROVIDING CEMENT CONCRETE AT 3, ANJUMAN ROAD & ADJACENT AREA IN KMC WARD NO 60, UNDER BOROUGH - VI.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Kolkata· #95280
₹9.1 L Completed 3 Feb 2026Rec. 3 Feb 2024Paid ₹9.1 LIMPROVEMENT OF FOOTPATH ON GANGA PRASAD MUKHERJEE ROAD, BINOY BOSE ROAD, BAKUL BAGAN ROAD ETC. IN K.M.C. WARD-72 UNDER BOROUGH-VIII.
Roads & bridgesConstruction of footpaths and pedestrian ways· Kolkata· #35476
₹6.7 L Completed 14 Jan 2026Rec. 10 Oct 2023Paid ₹6.7 LCONSTRUCTION OF BUS SHEDS AT PANCHANANGRAM, V.I.P. BAZAR AND BIDHAN NAGAR ALONG EM BYPASS IN KMC WARD 107, UNDER BOROUGH-XII.
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Kolkata· #35475
₹10.6 L Completed 22 Sept 2025Rec. 10 Oct 2023Paid ₹10.6 LINSTALLATION OF LIFT AT DAKSHINAYANAN COMMUNITY HALL LOCATED AT 56/2, PRATAPADITYA ROAD, KOLKATA - 700026 IN WARD 88 UNDER BOROUGH VIII.
Community buildings & public spacesConstruction of community centers and community halls· Kolkata· #114011
₹11.5 L Completed 16 Sept 2025Rec. 24 Feb 2024Paid ₹11.5 LDEVELOPMENT WORK INCLUDING SUPPLY,INSTALLATION OF AIR CONDITIONERS INCLUDING ELECTRICAL WIRING & ACCESSORIES AT MUNSHI PREMCHAND COMMUNITY HALL IN KMC WARD 75.
Community buildings & public spacesConstruction of community centers and community halls· Kolkata· #67535
₹6.2 L Completed 8 Aug 2025Rec. 21 Dec 2023Paid ₹6.2 LDEVELOPMENT OF FOOTPATH ALONG WITH ANCILLARY CIVIL WORK NEAR PR. NO. - 250A, S.N. ROY ROAD IN WARD NO. 117 UNDER BOROUGH - XIII.
Roads & bridgesConstruction of footpaths and pedestrian ways· Kolkata· #70702
₹14.7 L Completed 6 Aug 2025Rec. 28 Dec 2023Paid ₹14.7 L
17th Lok Sabha MPs from West Bengal
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Kalyan Banerjee · Sreerampur | 100% | 98% | 111 | 99 |
| 2 | Ms Mimi Chakraborty · Jadavpur | 100% | 96% | 250 | 97 |
| 3 | Shri Abhishek Banerjee · Diamond Harbour | 100% | 97% | 149 | 97 |
| 4 | Ms Mahua Moitra · Krishnanagar | 100% | 100% | 27 | 97 |
| 5 | Pratima Mondal · Joynagar | 100% | 97% | 140 | 96 |
| 6 | Smt Sajda Ahmed · Uluberia | 96% | 96% | 180 | 96 |
| 7 | Smt Locket Chatterjee · Hooghly | 100% | 100% | 307 | 96 |
| 8 | Smt Satabdi Roy (Banerjee) · Birbhum | 100% | 99% | 127 | 95 |
| 9 | Shri Kunar Hembram · Jhargram | 100% | 100% | 31 | 95 |
| 10 | Dr Sukanta Majumdar · Balurghat | 94% | 82% | 336 | 95 |
| 11 | Asit Kumar Mal · Bolpur | 100% | 100% | 55 | 94 |
| 12 | Shri Deepak (Dev) Adhikari · Ghatal | 93% | 87% | 195 | 94 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.