Allocated limit
₹19.60 Cr
Median ₹14.70 Cr
Fund utilisation
53%
₹10.37 Cr recommended · 81 works
Below median (70%)
Paid to vendors
₹4.87 Cr
25% of allocation
About the median
Works completed
6
7.4% of recommended
Below median (26%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP81 works
₹10.37 Cr · 53% of the ₹19.60 Cr allocated
- Sanctioned by the district50 works
62% sanctioned · took 6.0 months on average (due within 45 days)
- Completed6 works
₹1.14 Cr final cost · 10.8 months from recommendation on average
31 works are still awaiting sanction, 19 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 81 works worth ₹10.37 Cr, a fund utilisation of 53%, higher than 35% of Rajya Sabha MPs.
- The district has sanctioned 50 of them, taking 6.0 months on average.
- ₹4.87 Cr has been paid to vendors, 25% of the allocation.
- 6 works are complete, typically 10.8 months after recommendation. 5 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 19 vendors. The largest received 27%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 39/100: finishing works counts most
- Works completed 30%7Completed ÷ recommended works.
- Spending efficiency 20%23Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%53Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%83Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%25Paid to vendors ÷ allocated limit.
- Vendor diversity 10%92How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: DHIRENDRA SINGH, 27% of payments across 19 vendors.
District sanction speed
67/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%67Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
81 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
For the provision of equipment at the Urban Primary Health Centre, Police Lines, Meerut.
HealthPurchase of hospital equipment· Meerut· #301199
₹23.0 L Completed 31 Oct 2026Rec. 4 Aug 2026Paid ₹23.0 LConstruction of an approximately 70-metre CC road and drain in Lane No. 5, from the house of Shri Pankaj Kumar Tyagi to the house of Shri Chetan Tyagi, son of Shri Pappu Tyagi, at Village Goyna Jasrup Nagar, Block Hapur, under MPLADS funds.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Hapur· #325076
₹9.8 L Awaiting sanction · 2 daysRec. 30 Oct 2026Installation of 63 Nos. of 20-Watt Solar Lights at Various Residential Locations in Village Punner and Village Nagla Mal, Hathras Parliamentary Constituency.
Electricity & lightingLighting of public spaces· Hathras· #325103
₹10.8 L Awaiting sanction · 2 daysRec. 30 Oct 2026Construction of a Classroom (Science Laboratory) at Shri Harihar Prasad Mishra Higher Secondary School.
Education & librariesConstruction of rooms and halls in school and colleges· Prayagraj· #325154
₹10.0 L Awaiting sanction · 2 daysRec. 30 Oct 2026Installation of Interlocking Tiles at the Open Gym Site in Chaudhary Charan Singh District Jail, Meerut, for the Convenience and Safety of Persons Using the Gym.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Meerut· #324870
₹3.4 L Awaiting sanction · 3 daysRec. 29 Oct 2026Additional Works for the Construction of Medical and Cancer Screening Centre at Police Lines Primary Health Centre, Meerut (1) RCC Frame and Structural Works (2) Water Supply and Sanitary Works (3) Internal Electrification
HealthConstruction of rooms and facilities for hospitals, FWC , PHC Centers and ANM centers· Meerut· #324975
₹13.7 L Awaiting sanction · 3 daysRec. 29 Oct 2026Renovation and construction work
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Meerut· #166044
₹30.9 L Completed 15 Oct 2026Rec. 16 Jan 2025Paid ₹30.9 LConstruction of Interlocking Tiles at the Market Premises of Gram Sabha Satan, Development Block Sikandarpur Karan, District Unnao, under the Members of Parliament Local Area Development Scheme (MPLADS).
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Unnao· #313472
₹36.0 L Sanctioned · 5 Oct 2026Rec. 8 Sep 2026Construction of a Seating Shed, a Room, and Installation of a Submersible Pump at the Cremation Ground in Village Kitholi, Jani Development Block.
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Meerut· #294025
₹13.9 L Sanctioned · 1 Oct 2026Rec. 10 Jul 2026Additional construction work and beautification of the Public Sarai at Village Supakot under the Members of Parliament Local Area Development Scheme (MPLADS).
Community buildings & public spacesConstruction of additional rooms and halls in the existing public and community building· Almora· #2311
₹10.0 L Awaiting sanction · 32 daysRec. 30 Sep 2026Installation of an Open Gym in Gram Panchayat Umarpur, Sub District Nakur, Block Gangoh, District Saharanpur, Uttar Pradesh.
Sports & fitnessInstallation of multi-gym equipment· Saharanpur· #318679
₹6.0 L Awaiting sanction · 34 daysRec. 28 Sep 2026Installation of a Solar RO Water Pump in Village Mangrol Mustakil, Development Block Mahewa, Tehsil Kalpi, District Jalaun
Drinking waterInstalling community drinking water plants· Jalaun· #318704
₹6.7 L Awaiting sanction · 34 daysRec. 28 Sep 2026Installation of One Solar High Mast Light At ancient temple dedicate to Maharishi Valmiki ji, Ravindra Puri, Ward No. 4, near the Cantt Hospital in Meerut Cantonment.
Electricity & lightingLighting of public spaces· Meerut· #318799
₹1.1 L Awaiting sanction · 34 daysRec. 28 Sep 2026Installation of 04 High Mast Lights and 04 Solar Lights in Village Telpurwa. Tehsil Bansi, Distt. Siddharth Nagar, Uttar Pradesh. Contact Person Shri Ganesh Kumar ji, Mob.: 9807975387 or 9721931720
Electricity & lightingLighting of public spaces· Siddharthnagar· #317713
₹4.5 L Awaiting sanction · 38 daysRec. 24 Sep 2026Installation of 6 solar street lights at Village-Bhyouchilam, Post-Thakulsari Bari, Via-Bironkhal, Distt. Pauri Garhwal, Uttrakhand
Electricity & lightingLighting of public spaces· Pauri Garhwal· #2291
₹1.2 L Awaiting sanction · 40 daysRec. 22 Sep 2026
Rajya Sabha MPs from Uttar Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Mithlesh Kumar | 99% | 93% | 197 | 88 |
| 2 | Smt. Geeta alias Chandraprabha | 100% | 94% | 211 | 88 |
| 3 | Shri B.L. Verma | 100% | 88% | 350 | 83 |
| 4 | Smt. Darshana Singh | 100% | 89% | 31 | 81 |
| 5 | Shri Javed Ali Khan | 99% | 84% | 126 | 79 |
| 6 | Smt. Seema Dwivedi | 100% | 81% | 231 | 79 |
| 7 | Shri Hardeep Singh Puri | 96% | 80% | 344 | 79 |
| 8 | Dr. K. Laxman | 79% | 63% | 275 | 77 |
| 9 | Shri Baburam Nishad | 96% | 70% | 437 | 75 |
| 10 | Smt. Sangeeta Yadav | 100% | 87% | 44 | 73 |
| 11 | Shri Ratanjit Pratap Narain Singh | 79% | 62% | 88 | 70 |
| 12 | Shri Ramji | 100% | 83% | 154 | 68 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.