MPLADS report card · Rajya Sabha
Smt. Geeta alias Chandraprabha
Rajya Sabha
BJPTerm 2020–2026Uttar Pradesh
2nd of 30 from Uttar Pradesh
Payments concentrated with one vendor
55% of vendor payments went to RAHISH WARSI.
Allocated limit
₹19.61 Cr
Median ₹14.70 Cr
Fund utilisation
100%
₹19.61 Cr recommended · 247 works
Above median (70%)
Paid to vendors
₹18.37 Cr
94% of allocation
Above median (25%)
Works completed
211
85% of recommended
Above median (26%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP247 works
₹19.61 Cr · 100% of the ₹19.61 Cr allocated
- Sanctioned by the district247 works
100% sanctioned · took 2.0 months on average (due within 45 days)
- Completed211 works
₹16.16 Cr final cost · 20.0 months from recommendation on average
In plain words
What the numbers say
- Recommended 247 works worth ₹19.61 Cr, a fund utilisation of 100%, higher than 99% of Rajya Sabha MPs.
- The district has sanctioned 247 of them, taking 2.0 months on average.
- ₹18.37 Cr has been paid to vendors, 94% of the allocation.
- 211 works are complete, typically 20.0 months after recommendation. 210 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 6 vendors. The largest received 55%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 88/100: finishing works counts most
- Works completed 30%85Completed ÷ recommended works.
- Spending efficiency 20%88Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%94Paid to vendors ÷ allocated limit.
- Vendor diversity 10%56How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: RAHISH WARSI, 55% of payments across 6 vendors.
District sanction speed
97/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%97Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
247 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299335
₹8.1 L Vendor Identification · 22 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299338
₹8.1 L Vendor Identification · 22 Sept 2026Rec. 28 Jul 2026Paid ₹1.6 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299339
₹8.1 L Vendor Identification · 22 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L1 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299341
₹2.7 L Vendor Identification · 22 Sept 2026Rec. 28 Jul 2026Paid ₹1.6 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299342
₹8.1 L Vendor Identification · 22 Sept 2026Rec. 28 Jul 2026Paid ₹1.6 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299345
₹8.1 L Vendor Identification · 22 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299343
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299344
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299346
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299349
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299350
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299356
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299357
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299358
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L3 high mast light
Electricity & lightingLighting of public spaces· Auraiya· #299360
₹8.1 L Vendor Identification · 19 Sept 2026Rec. 28 Jul 2026Paid ₹4.8 L
Rajya Sabha MPs from Uttar Pradesh
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Mithlesh Kumar | 99% | 93% | 197 | 88 |
| 2 | Smt. Geeta alias Chandraprabha | 100% | 94% | 211 | 88 |
| 3 | Shri B.L. Verma | 100% | 88% | 350 | 83 |
| 4 | Smt. Darshana Singh | 100% | 89% | 31 | 81 |
| 5 | Shri Javed Ali Khan | 99% | 84% | 126 | 79 |
| 6 | Smt. Seema Dwivedi | 100% | 81% | 231 | 79 |
| 7 | Shri Hardeep Singh Puri | 96% | 80% | 344 | 79 |
| 8 | Dr. K. Laxman | 79% | 63% | 275 | 77 |
| 9 | Shri Baburam Nishad | 96% | 70% | 437 | 75 |
| 10 | Smt. Sangeeta Yadav | 100% | 87% | 44 | 73 |
| 11 | Shri Ratanjit Pratap Narain Singh | 79% | 62% | 88 | 70 |
| 12 | Shri Ramji | 100% | 83% | 154 | 68 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.