23rd of 39 from Tamil Nadu
Allocated limit
₹9.18 Cr
Median ₹8.60 Cr
Fund utilisation
100%
₹9.15 Cr recommended · 96 works
About the median
Paid to vendors
₹8.05 Cr
88% of allocation
About the median
Works completed
82
85% of recommended
About the median
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP96 works
₹9.15 Cr · 100% of the ₹9.18 Cr allocated
- Sanctioned by the district91 works
95% sanctioned · took 9.6 months on average (due within 45 days)
- Completed82 works
₹7.07 Cr final cost · 11.6 months from recommendation on average
5 works are still awaiting sanction, 5 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 96 works worth ₹9.15 Cr, a fund utilisation of 100%, higher than 72% of 17th Lok Sabha MPs.
- The district has sanctioned 91 of them, taking 9.6 months on average.
- ₹8.05 Cr has been paid to vendors, 88% of the allocation.
- 82 works are complete, typically 11.6 months after recommendation. 81 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Education & libraries.
- Payments went to 26 vendors. The largest received 6.8%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 92/100: finishing works counts most
- Works completed 30%85Completed ÷ recommended works.
- Spending efficiency 20%88Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%99Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%88Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Metro Lights, 6.8% of payments across 26 vendors.
District sanction speed
59/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%59Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
96 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Public Library Building.
Education & librariesConstruction of public libraries and reading rooms· Chengalpattu· #26376
₹12.5 L Completed 21 Aug 2026Rec. 26 Sep 2023Paid ₹12.5 LConstruction of Anganwadi Building.
Education & librariesConstruction of buildings for crèches and anganwadies· Chengalpattu· #26377
₹11.0 L Completed 21 Aug 2026Rec. 26 Sep 2023Paid ₹11.0 LConstruction of a Community Hall
Community buildings & public spacesConstruction of community centers and community halls· Kancheepuram· #42070
₹50.0 L Completed 11 Aug 2026Rec. 30 Oct 2023Paid ₹50.0 LConstruction of Public Library Building
Education & librariesConstruction of public libraries and reading rooms· Kancheepuram· #25332
₹14.1 L Completed 8 Oct 2025Rec. 23 Sep 2023Paid ₹14.1 LConstruction of an Anganwadi Building.
Education & librariesConstruction of buildings for crèches and anganwadies· Kancheepuram· #118581
₹16.5 L Completed 18 Sept 2025Rec. 1 Mar 2024Paid ₹16.5 LConstruction of 2 Class Room Buildings for Corporation Middle School, Valasaravakkam Zone
Education & librariesConstruction of rooms and halls in school and colleges· Chennai· #25204
₹53.4 L Completed 10 Sept 2025Rec. 23 Sep 2023Paid ₹53.4 LProviding 1 Nos. Mini Highmast Light
Electricity & lightingStreet lights· Kancheepuram· #118584
₹1.6 L Completed 15 May 2025Rec. 1 Mar 2024Paid ₹1.6 LProviding Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25281
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011Providing Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25284
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011Providing Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25285
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011Providing Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25286
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011Providing Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25291
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011Providing Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25294
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011Providing Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25295
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011Providing Three Wheeler Petrol Scooter for Physically Challenged Beneficiary.
HealthPurchase of vehicle for mobile dispensaries (Four, three and two wheelers)· Chennai· #25296
₹96,011 Completed 24 Apr 2025Rec. 23 Sep 2023Paid ₹96,011
17th Lok Sabha MPs from Tamil Nadu
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | A Ganeshamurthi · Erode | 100% | 100% | 101 | 99 |
| 2 | Ganesan Selvam · Kancheepuram | 100% | 97% | 206 | 97 |
| 3 | Dhanush M Kumar · Tenkasi | 100% | 99% | 211 | 97 |
| 4 | S Gnanathiraviam · Tirunelveli | 97% | 94% | 93 | 97 |
| 5 | Kanimozhi Karunanidhi · Thoothukkudi | 99% | 96% | 62 | 97 |
| 6 | Thirumaa Valavan Thol · Chidambaram | 99% | 96% | 81 | 96 |
| 7 | S Venkatesan · Madurai | 97% | 96% | 165 | 96 |
| 8 | Kalanidhi Veeraswamy · Chennai North | 99% | 98% | 32 | 96 |
| 9 | AKP Chinraj · Namakkal | 98% | 98% | 93 | 96 |
| 10 | MK Vishnu Prasad · Arani | 100% | 100% | 102 | 95 |
| 11 | TRVS Ramesh · Cuddalore | 96% | 89% | 114 | 95 |
| 12 | M Selvaraj · Nagapattinam | 99% | 99% | 76 | 95 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.