MPLADS report card · 17th Lok Sabha

Kalanidhi Veeraswamy

Lok SabhaChennai North · Tamil Nadu

MP score96/10046th of 539 in the 17th Lok Sabha
8th of 39 from Tamil Nadu
Re-elected to the 18th Lok Sabha Then: 86% utilisation, 40 works completed, score 68.
  • Payments concentrated with one vendor

    53% of vendor payments went to Annamalai construction.

Allocated limit

₹11.77 Cr

Median ₹8.60 Cr

Fund utilisation

99%

₹11.67 Cr recommended · 32 works
About the median

Paid to vendors

₹11.56 Cr

98% of allocation
Above median (88%)

Works completed

32

100% of recommended
Above median (83%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP32 works

    ₹11.67 Cr · 99% of the ₹11.77 Cr allocated

  2. Sanctioned by the district32 works

    100% sanctioned · took 4.6 months on average (due within 45 days)

  3. Completed32 works

    ₹11.56 Cr final cost · 4.6 months from recommendation on average

In plain words

What the numbers say

  • Recommended 32 works worth ₹11.67 Cr, a fund utilisation of 99%, higher than 63% of 17th Lok Sabha MPs.
  • The district has sanctioned 32 of them, taking 4.6 months on average.
  • ₹11.56 Cr has been paid to vendors, 98% of the allocation.
  • 32 works are complete, typically 4.6 months after recommendation. 32 works have geo-tagged photos on eSAKSHI.
  • The largest share of funds went to Community buildings & public spaces.
  • Payments went to 11 vendors. The largest received 53%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 96/100: finishing works counts most

  1. Works completed 30%100Completed ÷ recommended works.
  2. Spending efficiency 20%100Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%99Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%98Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    59
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: Annamalai construction, 53% of payments across 11 vendors.

District sanction speed

85/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%85Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

32 works · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Construction of Multipurpose hall V.O.C nagar in dn -72, Zone - 6

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #99691

    ₹49.6 L Completed 28 Oct 2025Rec. 9 Feb 2024Paid ₹49.6 L
  • Construction of Gym building and Indoor stadium hall at Viyasarpadi kamatchi nagar in dn 44, Zone - 4

    Sports & fitnessConstruction of buildings for multi-gym· Chennai· #99653

    ₹49.6 L Completed 14 Aug 2025Rec. 9 Feb 2024Paid ₹49.6 L
  • Construction of footpath, compound wall time clock at sakthipuram srirangam new town park in Dn 5, Zone-1

    Community buildings & public spacesDevelopment of public parks· Chennai· #129468

    ₹28.0 L Completed 30 Dec 2024Rec. 15 Mar 2024Paid ₹28.0 L
  • Construction of footpath, compound wall time clock at Hansa garden park and Ajacks park T.H. Road in Dn- 5, Zone-1

    Community buildings & public spacesDevelopment of public parks· Chennai· #129474

    ₹22.0 L Completed 30 Dec 2024Rec. 15 Mar 2024Paid ₹22.0 L
  • Construction of Multipurpose hall near Meenambal nagar Korukkupet in dn 47, Zone - 4

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #99616

    ₹24.4 L Completed 5 Nov 2024Rec. 9 Feb 2024Paid ₹24.4 L
  • Construction of Strong room Venkatadri street in dn 76, Zone - 6

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #99690

    ₹34.9 L Completed 23 Oct 2024Rec. 9 Feb 2024Paid ₹34.9 L
  • Additional Construction of Community hall Venkatadri street in dn 76, Zone - 6

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #99692

    ₹34.9 L Completed 23 Oct 2024Rec. 9 Feb 2024Paid ₹34.9 L
  • Construction of Multipurpose hall near Srinivasapuram 2nd street Korukkupet in dn 53, Zone - 4

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #99647

    ₹28.5 L Completed 27 Sept 2024Rec. 9 Feb 2024Paid ₹28.5 L
  • Construction of Multi purpose hall at Elaya Street Dn-42, Unit-10, Zone-4.

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #41078

    ₹39.3 L Completed 10 Jul 2024Rec. 27 Oct 2023Paid ₹39.3 L
  • Construction of Multipurpose hall near New Vinoba nagar 1st street Todiarpet in dn 38, Zone - 4

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #99648

    ₹32.4 L Completed 10 Jul 2024Rec. 9 Feb 2024Paid ₹32.4 L
  • Construction of Compound wall Indra Gandhi Nagar, 1st street in dn-36, Unit-9, Zone-4, Perambur

    Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Chennai· #41079

    ₹5.9 L Completed 4 Jul 2024Rec. 27 Oct 2023Paid ₹5.9 L
  • Construction of Multipurpose hall at Lalagunda Housing Board Building in dn 48, Zone -4.

    Community buildings & public spacesConstruction of community centers and community halls· Chennai· #99615

    ₹24.5 L Completed 24 Jun 2024Rec. 9 Feb 2024Paid ₹24.5 L
  • 1.Zero Degree Nasal Endoscope With Accessories-1No. 2.Radio Frequency Cautery with Monitor-1No. 3.High End Ear Operating Unit With monitor-1No 4.Advance Ophthalmic Ultrasound scanner with Probes and Accessories-1No, dn,52. Zone-5

    HealthPurchase of hospital equipment· Chennai· #99716

    ₹59.9 L Completed 14 Jun 2024Rec. 9 Feb 2024Paid ₹59.9 L
  • 1.Ceiling Mounted Highend LED OT Light. 2.Electrically Adjustable C-ARM Compactible Ot Table With All Attachments-2No. 3.Highend Multiparameter Monitor-2No. 4.Diathermy Machine With Non Stick Bipolar Forceps-2No. 5.Anaesthesia Workstation (High End With Servoflurane Vaporiser-3No

    HealthPurchase of hospital equipment· Chennai· #99720

    ₹69.9 L Completed 14 Jun 2024Rec. 9 Feb 2024Paid ₹69.9 L
  • Construction of Indoor stadium Chennai Primary School at Seniamman kovil street in dn 42, Zone - 4

    Sports & fitnessConstruction of stadiums· Chennai· #99689

    ₹73.8 L Completed 12 Jun 2024Rec. 9 Feb 2024Paid ₹73.8 L

17th Lok Sabha MPs from Tamil Nadu

Ranked by MP score

#MPUtilisationSpentCompletedScore
1A Ganeshamurthi · Erode100%100%10199
2Ganesan Selvam · Kancheepuram100%97%20697
3Dhanush M Kumar · Tenkasi100%99%21197
4S Gnanathiraviam · Tirunelveli97%94%9397
5Kanimozhi Karunanidhi · Thoothukkudi99%96%6297
6Thirumaa Valavan Thol · Chidambaram99%96%8196
7S Venkatesan · Madurai97%96%16596
8Kalanidhi Veeraswamy · Chennai North99%98%3296
9AKP Chinraj · Namakkal98%98%9396
10MK Vishnu Prasad · Arani100%100%10295
11TRVS Ramesh · Cuddalore96%89%11495
12M Selvaraj · Nagapattinam99%99%7695

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.