6th of 21 from Odisha
Allocated limit
₹7.34 Cr
Median ₹8.60 Cr
Fund utilisation
100%
₹7.34 Cr recommended · 262 works
About the median
Paid to vendors
₹6.07 Cr
83% of allocation
Below median (88%)
Works completed
187
71% of recommended
Below median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP262 works
₹7.34 Cr · 100% of the ₹7.34 Cr allocated
- Sanctioned by the district262 works
100% sanctioned · took 41 days on average (due within 45 days)
- Completed187 works
₹5.20 Cr final cost · 14.6 months from recommendation on average
In plain words
What the numbers say
- Recommended 262 works worth ₹7.34 Cr, a fund utilisation of 100%, higher than 87% of 17th Lok Sabha MPs.
- The district has sanctioned 262 of them, taking 41 days on average.
- ₹6.07 Cr has been paid to vendors, 83% of the allocation.
- 187 works are complete, typically 14.6 months after recommendation. 102 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 100 vendors. The largest received 6.4%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 80/100: finishing works counts most
- Works completed 30%71Completed ÷ recommended works.
- Spending efficiency 20%86Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%55Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%83Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: MANINI MEHER, 6.4% of payments across 100 vendors.
District sanction speed
100/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%100Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
262 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Provision of Deep Borewell with Submersible Pump Set at Plot No 1338 of Khata No 353 near Mahajantikra-( The Executing Agency is EE, RWSS, Bargarh)
Drinking waterInstalling tube-wells and borewells· Baragada· #19527
₹4.0 L Completed 14 May 2026Rec. 13 Sep 2023Paid ₹4.0 LConstruction of Ramji Community Center near Ram Mandir
Community buildings & public spacesConstruction of community centers and community halls· Baragada· #19421
₹2.5 L Completed 24 Feb 2026Rec. 13 Sep 2023Paid ₹2.5 LConstruction of Community Center at Gudipada
Community buildings & public spacesConstruction of community centers and community halls· Baragada· #36600
₹3.6 L Completed 19 Feb 2026Rec. 13 Oct 2023Paid ₹3.6 LConstruction of Kalyan Mandap at Ainlapali Village
Community buildings & public spacesConstruction of buildings for community cultural activities· Baragada· #91250
₹3.0 L Completed 19 Feb 2026Rec. 29 Jan 2024Paid ₹3.0 LConstruction of Community Center at Ainlapali
Community buildings & public spacesConstruction of community centers and community halls· Baragada· #17042
₹3.0 L Completed 22 Jan 2026Rec. 6 Sep 2023Paid ₹3.0 LConstruction of Kalyan Mandap near Shiva Temple
Community buildings & public spacesConstruction of buildings for community cultural activities· Baragada· #19422
₹4.0 L Completed 9 Jan 2026Rec. 13 Sep 2023Paid ₹4.0 LConstruction of CC Building near Yangan Mandap
Community buildings & public spacesConstruction of community centers and community halls· Jharsuguda· #17432
₹3.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹3.0 LCompletion of Kalyan Mandap near Mutharnala
Community buildings & public spacesConstruction of buildings for community cultural activities· Jharsuguda· #17433
₹3.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹3.0 LConstruction of Community Center
Community buildings & public spacesConstruction of community centers and community halls· Jharsuguda· #17434
₹3.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹3.0 LCompletion of CC Building at Gudiapada
Community buildings & public spacesConstruction of community centers and community halls· Jharsuguda· #17435
₹1.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹1.0 LCompletion of CC Building
Community buildings & public spacesConstruction of community centers and community halls· Jharsuguda· #17437
₹2.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹2.0 LConstruction of Mandap
Community buildings & public spacesConstruction of buildings for community cultural activities· Jharsuguda· #17440
₹3.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹3.0 LConstruction of Community Center
Community buildings & public spacesConstruction of community centers and community halls· Jharsuguda· #17441
₹3.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹3.0 LConstruction of Mandap near Shiba Temple
Community buildings & public spacesConstruction of buildings for community cultural activities· Jharsuguda· #17442
₹3.0 L Completed 20 Nov 2025Rec. 7 Sep 2023Paid ₹3.0 LConstructioin of CC Building near SSVM, Kanaktora
Community buildings & public spacesConstruction of community centers and community halls· Jharsuguda· #17793
₹3.0 L Completed 20 Nov 2025Rec. 8 Sep 2023Paid ₹3.0 L
17th Lok Sabha MPs from Odisha
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Anubhav Mohanty · Kendrapara | 100% | 99% | 134 | 93 |
| 2 | Nitesh Ganga Deb · Sambalpur | 100% | 88% | 176 | 88 |
| 3 | Smt Manjulata Mandal · Bhadrak | 98% | 75% | 127 | 84 |
| 4 | Shri Jual Oram · Sundargarh | 100% | 87% | 98 | 81 |
| 5 | Saptagiri Sankar Ulaka · Koraput | 97% | 78% | 184 | 81 |
| 6 | Suresh Pujari · Bargarh | 100% | 83% | 187 | 80 |
| 7 | Shri Bhartruhari Mahtab · Cuttack | 100% | 63% | 139 | 79 |
| 8 | Smt Sangeeta Kumari Singh Deo · Bolangir | 100% | 73% | 277 | 75 |
| 9 | Pinaki Misra · Puri | 100% | 69% | 177 | 74 |
| 10 | Basanta Kumar Panda · Kalahandi | 99% | 78% | 235 | 73 |
| 11 | Shri Chandra Sekhar Sahu · Berhampur | 100% | 45% | 92 | 73 |
| 12 | Ms Chandrani Murmu · Keonjhar | 100% | 87% | 157 | 72 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.