Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
56%
₹8.30 Cr recommended · 63 works
Below median (70%)
Paid to vendors
₹2.86 Cr
19% of allocation
Below median (25%)
Works completed
10
16% of recommended
Below median (26%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP63 works
₹8.30 Cr · 56% of the ₹14.70 Cr allocated
- Sanctioned by the district40 works
63% sanctioned · took 6.7 months on average (due within 45 days)
- Completed10 works
₹1.41 Cr final cost · 11.5 months from recommendation on average
23 works are still awaiting sanction, 10 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 63 works worth ₹8.30 Cr, a fund utilisation of 56%, higher than 37% of Rajya Sabha MPs.
- The district has sanctioned 40 of them, taking 6.7 months on average.
- ₹2.86 Cr has been paid to vendors, 19% of the allocation.
- 10 works are complete, typically 11.5 months after recommendation. 9 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Education & libraries.
- Payments went to 19 vendors. The largest received 10%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 49/100: finishing works counts most
- Works completed 30%16Completed ÷ recommended works.
- Spending efficiency 20%49Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%56Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%90Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%19Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: MAITRA CONSTRUCTION, 10% of payments across 19 vendors.
District sanction speed
67/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%67Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
63 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Renovation at Kotera Dakshinpara Free Primary School,Kotera PO, Tarakeswar PS, Kotera Village, Hooghly,Pin-712410
Education & librariesConstruction of rooms and halls in school and colleges· Hooghly· #325483
₹6.0 L Awaiting sanction · 1 daysRec. 31 Oct 2026Renovation at Joypur Surangamayee Girls High School ,Joypur PO, Joypur PS,Howrah District, Pin-7111401
Education & librariesConstruction of rooms and halls in school and colleges· Howrah· #325484
₹6.0 L Awaiting sanction · 1 daysRec. 31 Oct 2026Renovation at Gazipur Balika Vidyalaya , Gazipur Village & PO, Howrah District.
Education & librariesConstruction of rooms and halls in school and colleges· Howrah· #325485
₹6.0 L Awaiting sanction · 1 daysRec. 31 Oct 2026Construction of Childrens Park at Ideal School for the Deaf, CF -217,Sector I,Saltlake City, Kolkata-700064
Education & librariesConstruction of rooms and halls in school and colleges· North 24 Parganas· #325486
₹10.0 L Awaiting sanction · 1 daysRec. 31 Oct 2026Construction of Cultural Hall at Gogra S.C. High School (H.S.) P.O-Gogra,Block-Saltora,Dist-Bankura,Pin-722137
Education & librariesConstruction of rooms and halls in school and colleges· Bankura· #324698
₹10.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of New Community Hall at Tarasundari Park in ward no-23 (Old) Borough IV,KMC
Community buildings & public spacesConstruction of community centers and community halls· Kolkata· #324699
₹30.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Hall room and Bathroom at Ghorateria Primary School , Kanikha PO, Kharaghpur II Block, Paschim Medinipur
Education & librariesConstruction of rooms and halls in school and colleges· Paschim Medinipur· #324875
₹10.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Renovation at Kuthipara Primary School, Kuthipara Village, Gobordanga PS. North 24 Parganas.
Education & librariesConstruction of rooms and halls in school and colleges· North 24 Parganas· #324876
₹5.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Academic Building & Classrooms at Chhatna Basuli Balika Banipith,chhatna PO, Chhatna Block, Bankura district, pin- 722132
Education & librariesConstruction of rooms and halls in school and colleges· Bankura· #324903
₹10.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Bidhannagar BH Block Society Community Centre at rear side of the existing Children's Park, BH Block, Sector-II, Saltlake City, Kol-700091
Community buildings & public spacesConstruction of community centers and community halls· North 24 Parganas· #324915
₹30.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of Smart Classroom & Biology Lab at Jhargram nanibala Balika vidyalaya, Jhargram PO, Jhargram Block, Jhargram District,Pin-721507
Education & librariesConstruction of rooms and halls in school and colleges· Paschim Medinipur· #324943
₹10.0 L Awaiting sanction · 3 daysRec. 29 Oct 2026Construction of CC Road from Sonajhuri Hutkhola Tin Mohini towards Saden Roy Pond, at Jatar Pur, Aktail GP, Habibpur Development Block
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malda· #241018
₹4.0 L Sanctioned · 6 Oct 2026Rec. 9 Oct 2025Repairing of Black Top road from Kinkar Ghosh House to Baribhasha Main road at Madhya Shantinagar Under Dabgram-II Gram Panchayat , Rajganj Block
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Jalpaiguri· #219838
₹14.6 L Sanctioned · 5 Oct 2026Rec. 18 Jul 2025Repairing of CC Road from Karnel Hembrom house towards Saresh Mardi House at Boldanga, Baidyapur GP,Habibpur Development Block
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Malda· #241022
₹4.0 L Work partially Completed · 30 Sept 2026Rec. 9 Oct 2025Paid ₹4.0 LInstallation of Solar Submersible pump with multi-tap water tank at Kalpathar Academy,JL-116,Plot no-1, Kalpathar Gram Panchayat under development block Bankura-I
Electricity & lightingPurchase of non-conventional energy system and devices for community use· Bankura· #219793
₹5.0 L Sanctioned · 25 Sept 2026Rec. 18 Jul 2025
Rajya Sabha MPs from West Bengal
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Nagendra Ray | 71% | 60% | 20 | 86 |
| 2 | Smt. Mamata Thakur | 37% | 30% | 52 | 69 |
| 3 | Shri Samik Bhattacharya | 56% | 19% | 10 | 49 |
| 4 | Ms. Dola Sen | 71% | 40% | 1 | 26 |
| 5 | Shri Mohammed Nadimul Haque | 66% | 31% | 1 | 24 |
| 6 | Shri Derek O' Brien | 71% | 41% | 0 | 21 |
| 7 | Shri Samirul Islam | 71% | 42% | 0 | 21 |
| 8 | Smt. Sagarika Ghose | 66% | 32% | 0 | 19 |
| 9 | Shri Prakash Chik Baraik | 81% | 0% | 0 | 17 |
| 10 | Shri Harsh Vardhan Shringla | 13% | 0% | 0 | 3 |
| 11 | Shri Biswajit Sinha (Rahul Sinha) | 1.4% | 0% | 0 | 0 |
| 12 | Shri Rajeev Kumar | 0% | 0% | 0 | 0 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.