3rd of 10 from Rajasthan
Allocated limit
₹19.61 Cr
Median ₹14.70 Cr
Fund utilisation
69%
₹13.59 Cr recommended · 150 works
About the median
Paid to vendors
₹6.51 Cr
33% of allocation
Above median (25%)
Works completed
59
39% of recommended
Above median (26%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP150 works
₹13.59 Cr · 69% of the ₹19.61 Cr allocated
- Sanctioned by the district114 works
76% sanctioned · took 2.9 months on average (due within 45 days)
- Completed59 works
₹4.28 Cr final cost · 11.1 months from recommendation on average
36 works are still awaiting sanction, 34 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 150 works worth ₹13.59 Cr, a fund utilisation of 69%, higher than 49% of Rajya Sabha MPs.
- The district has sanctioned 114 of them, taking 2.9 months on average.
- ₹6.51 Cr has been paid to vendors, 33% of the allocation.
- 59 works are complete, typically 11.1 months after recommendation. 53 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 198 vendors. The largest received 4.6%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 61/100: finishing works counts most
- Works completed 30%39Completed ÷ recommended works.
- Spending efficiency 20%66Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%69Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%85Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%33Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SHARMA CONTRACTOR, 4.6% of payments across 198 vendors.
District sanction speed
82/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%82Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
157 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of boundary wall of Play Ground of Rajkiya Uchch Madhyamik Vidyalay at Gunti Village
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Jhunjhunu· #280044
₹7.5 L Completed 23 Oct 2026Rec. 9 May 2026Paid ₹7.5 LConstruction of Library Building of SWAMI SUKRATI SIKSHA AVAM SAMAJIK KALYAN SAMITI at Kothi Village Tehsil Punasa District Khandwa
Education & librariesConstruction of public libraries and reading rooms· Khandwa· #2312
₹10.0 L Awaiting sanction · 30 daysRec. 2 Oct 2026Construction Of CC Road From Reham House To Kishni Ke Nohre Onwards To Different Streets At Raisees Village
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Bharatpur· #289216
₹10.0 L Sanctioned · 1 Oct 2026Rec. 25 Jun 2026Construction Work of Open Community Sitting Area at Timruwala Bavji Vishram Udiyawala Falan Keriyapada of Choti Sarwan Village
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Banswara· #294989
₹5.0 L Sanctioned · 28 Sept 2026Rec. 14 Jul 2026Construction work of Open Community Sitting Area at Gowalimata of Choti Sarwan Village
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Banswara· #295009
₹5.0 L Sanctioned · 28 Sept 2026Rec. 14 Jul 2026Construction of Community Building on Panchayat Land Khasra Number 146 at Village Jaswanti District Kaithal
Community buildings & public spacesConstruction of community centers and community halls· Kaithal· #2307
₹11.0 L Awaiting sanction · 34 daysRec. 28 Sep 2026Construction work of CC Interlocking Tiles Road Cum Drainage at Different Streets Of Village Narena Katatta
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Deeg· #289214
₹5.0 L Sanctioned · 25 Sept 2026Rec. 25 Jun 2026Asphaltization of the gravel road from village Nizampura towards Purohit ki Dhani (in the border of Nizampura).
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Jhunjhunu· #147421
₹7.9 L Completed 18 Sept 2026Rec. 15 Oct 2024Paid ₹7.9 LConstruction work of CC Road with drainage from Sukandar house to Arah of Maitab onwards at Cheelpura Village
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Dholpur· #294980
₹5.0 L Sanctioned · 17 Sept 2026Rec. 14 Jul 2026Construction work of CC Road with drainage from Main Road to House of Ram Nivas onwards at Cheelpura Village
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Dholpur· #294984
₹2.5 L Sanctioned · 17 Sept 2026Rec. 14 Jul 2026Construction work of CC Road with Drainage at the backside of the house of Rajpati Lodhi at Dihauli Village
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Dholpur· #294986
₹2.5 L Sanctioned · 17 Sept 2026Rec. 14 Jul 2026Construction of Beautyfication and Seating Arrangement at Crematorium, Patan Village
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Dausa· #212177
₹5.0 L Completed 14 Sept 2026Rec. 25 Jun 2025Paid ₹5.0 LConstruction of Gate at Crematoriom, Patan Village
Safety & securitySecurity gates in streets/public place for safety purpose· Dausa· #212192
₹5.0 L Completed 14 Sept 2026Rec. 25 Jun 2025Paid ₹5.0 LConstruction of Community Building at Ratanpura Village
Community buildings & public spacesConstruction of community centers and community halls· Dungarpur· #274613
₹25.0 L Sanctioned · 11 Sept 2026Rec. 16 Mar 2026Construction work of Boundary Wall Soil Filling and Beautification of Navsrijit Gram Panchayat Bhawan at Bedhadi Meenan Village
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Dausa· #298417
₹15.0 L Sanctioned · 7 Sept 2026Rec. 23 Jul 2026
Rajya Sabha MPs from Rajasthan
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Mukul Wasnik | 82% | 63% | 101 | 69 |
| 2 | Shri Pramod Tiwari | 71% | 55% | 69 | 65 |
| 3 | Shri Randeep Singh Surjewala | 69% | 33% | 59 | 61 |
| 4 | Smt. Sonia Gandhi | 88% | 60% | 48 | 58 |
| 5 | Shri Chunnilal Garasiya | 96% | 60% | 26 | 55 |
| 6 | Shri Ghanshyam Tiwari | 53% | 25% | 36 | 54 |
| 7 | Shri Madan Rathore | 74% | 30% | 32 | 51 |
| 8 | Shri Neeraj Dangi | 56% | 10% | 0 | 10 |
| 9 | Dr. Alka Singh | 0% | 0% | 0 | 0 |
| 10 | Dr. Satish Poonia | 0% | 0% | 0 | 0 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.