20th of 26 from Gujarat
Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
80%
₹11.79 Cr recommended · 562 works
Above median (76%)
Paid to vendors
₹3.75 Cr
26% of allocation
Below median (37%)
Works completed
118
21% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP562 works
₹11.79 Cr · 80% of the ₹14.70 Cr allocated
- Sanctioned by the district461 works
82% sanctioned · took 5.4 months on average (due within 45 days)
- Completed118 works
₹2.44 Cr final cost · 9.1 months from recommendation on average
101 works are still awaiting sanction, 78 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 562 works worth ₹11.79 Cr, a fund utilisation of 80%, higher than 56% of 18th Lok Sabha MPs.
- The district has sanctioned 461 of them, taking 5.4 months on average.
- ₹3.75 Cr has been paid to vendors, 26% of the allocation.
- 118 works are complete, typically 9.1 months after recommendation. 100 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 135 vendors. The largest received 4.0%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 57/100: finishing works counts most
- Works completed 30%21Completed ÷ recommended works.
- Spending efficiency 20%65Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%80Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%85Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%26Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: MR GRAM PANCHAYAT NAMANAAR, 4.0% of payments across 135 vendors.
District sanction speed
74/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%74Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
562 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
CONSTRUCTION CEMENT CONCRET ROAD WORK BEDHIYA DHULAKHATU MUVADI MAIN ROAD TO DHARMSHALA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Panch Mahals· #323459
₹5.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026CONSTRUCTION INCOMPELET CEMENT CONCRET ROAD WORK BEDHIYA MAIN ROAD TO DHARMSHALA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Panch Mahals· #323460
₹5.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026CONSTRUCTION CEMENT CONCRET ROAD WORK BEDHIYA COMUNITY PUBLIC TOILET TO JALARAM MANDIR FALIYA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Panch Mahals· #323461
₹5.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026CONSTRUCTION CEMENT CONCRET ROAD WORK ADADRA UDESINH MANGALSINH HOUSE TO JADAV NAVALSINH FATESINH FALIYA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Panch Mahals· #323462
₹3.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK ERAL BHIKHAPURA MANDIR FALIYA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323463
₹5.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026BORE WELL WORK PALASA MAIN ROAD NEAR SOMSINH FALIYA
Drinking waterInstalling tube-wells and borewells· Panch Mahals· #323465
₹60,000 Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK PATLA VAGU 2 FALIYA PALASA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323467
₹4.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK PALASA BHATHIJI MANDIR FALIYA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323468
₹2.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK PALASA SIKLIGAR FALIYA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323469
₹2.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK JIVAN JYOT VIDHYALAY PURANA VILLAGE
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323473
₹2.5 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK NEAR RUPAL MEDICAL JYOTI HOSPITAL ADADRA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323474
₹2.5 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK IN ALALI VAV FALIYA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323475
₹5.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK IN ALALI VILLAGE ASHVINBHAI FALIYA FALIYA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323476
₹5.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026PEWER BLOCK WORK NANI SHAMALDEVI UGMANA FALIYA
Roads & bridgesConstruction of footpaths and pedestrian ways· Panch Mahals· #323485
₹3.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026CONSTRUCTION CEMENT CONCRET ROAD WORK KANDACH VILLAGE VIRBHADRSINH FALIYA TO UTREDIYA VILLAGE ROAD
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Panch Mahals· #323486
₹3.0 L Awaiting sanction · 5 daysRec. 27 Oct 2026
18th Lok Sabha MPs from Gujarat
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | C R Patil · Navsari | 83% | 48% | 278 | 81 |
| 2 | Bharatbhai Manubhai Sutariya · Amreli | 90% | 47% | 200 | 76 |
| 3 | Mansukhbhai Dhanjibhai Vasava · Bharuch | 81% | 47% | 231 | 71 |
| 4 | Bharatsinhji Shankarji Dabhi · Patan | 88% | 57% | 162 | 71 |
| 5 | Rajeshbhai Naranbhai Chudasama · Junagadh | 98% | 41% | 157 | 71 |
| 6 | Mukeshkumar Chandrakaant Dalal · Surat | 83% | 29% | 109 | 69 |
| 7 | Shobhanaben Mahendrasinh Baraiya · Sabarkantha | 77% | 43% | 131 | 67 |
| 8 | Parshottambhai Rupala · Rajkot | 91% | 30% | 115 | 67 |
| 9 | Dhaval Laxmanbhai Patel · Valsad | 64% | 30% | 78 | 66 |
| 10 | Mitesh Rameshbhai Bakabhai Patel · Anand | 83% | 53% | 267 | 65 |
| 11 | Dr. Mansukh Mandaviya · Porbandar | 96% | 28% | 82 | 64 |
| 12 | Jaswantsinh Sumanbhai Bhabhor · Dahod | 90% | 21% | 99 | 64 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.