Skip to content
MPLADSTracker

MPLADS report card · 18th Lok Sabha

Mukeshkumar Chandrakaant Dalal

Lok SabhaBJPSurat · Gujarat

MP score69/100102nd of 542 in the 18th Lok Sabha
6th of 26 from Gujarat

Allocated limit

₹14.70 Cr

Median ₹14.70 Cr

Fund utilisation

83%

₹12.23 Cr recommended · 236 works
Above median (76%)

Paid to vendors

₹4.30 Cr

29% of allocation
Below median (37%)

Works completed

109

46% of recommended
Above median (28%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP236 works

    ₹12.23 Cr · 83% of the ₹14.70 Cr allocated

  2. Sanctioned by the district178 works

    75% sanctioned · took 3.0 months on average (due within 45 days)

  3. Completed109 works

    ₹3.65 Cr final cost · 9.0 months from recommendation on average

58 works are still awaiting sanction, 23 of them for more than 45 days.

In plain words

What the numbers say

  • Recommended 236 works worth ₹12.23 Cr, a fund utilisation of 83%, higher than 62% of 18th Lok Sabha MPs.
  • The district has sanctioned 178 of them, taking 3.0 months on average.
  • ₹4.30 Cr has been paid to vendors, 29% of the allocation.
  • 109 works are complete, typically 9.0 months after recommendation. 108 works have geo-tagged photos on eSAKSHI.
  • The largest share of funds went to Education & libraries.
  • Payments went to 41 vendors. The largest received 37%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 69/100: finishing works counts most

  1. Works completed 30%46Completed ÷ recommended works.
  2. Spending efficiency 20%85Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%83Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%99Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%29Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    79
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: INTELIN NETSOL, 37% of payments across 41 vendors.

District sanction speed

88/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%88Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

236 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • To allocate 1 Smart Panel to each of the schools mentioned in the list at a cost of 260000 per unit

    Education & librariesPurchase of smart boards, visual display units and projectors· Surat· #274318

    ₹57.1 L Completed 30 Oct 2026Rec. 14 Mar 2026Paid ₹57.1 L
  • To allocate 1 Smart Panel to each of the schools mentioned in the list at a cost of RS. 260000 per unit.

    Education & librariesPurchase of smart boards, visual display units and projectors· Surat· #274319

    ₹51.9 L Completed 30 Oct 2026Rec. 14 Mar 2026Paid ₹51.9 L
  • At Veer Narmad South Gujarat University, from the Hon'ble Member of Parliament's eligible grant, it is proposed to provide two (2) battery-operated modified e-vehicles within the University campus, particularly for the convenience of persons with disabilities (Divyangjan), senior citizens, dignitaries, and guests attending various academic, cultural, and national-level events organized by the University.

    Community buildings & public spacesPurchase of hearse van (Four, Three and Two wheelers)· Surat· #294802

    ₹19.0 L Sanctioned · 19 Oct 2026Rec. 13 Jul 2026
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Obhla village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208035

    ₹2.0 L Completed 7 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Madhar village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208047

    ₹2.0 L Completed 7 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Erthan village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208058

    ₹2.0 L Completed 7 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Syadla village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208061

    ₹2.0 L Completed 7 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Karamla village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208072

    ₹2.0 L Completed 7 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Sandhiyer village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208073

    ₹2.0 L Completed 7 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Bhatgam village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208037

    ₹2.0 L Completed 6 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Delasa village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208044

    ₹2.0 L Completed 6 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Mirjapor village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208045

    ₹2.0 L Completed 6 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Kamroli village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208069

    ₹2.0 L Completed 6 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • To allocate 2,00,000 for the construction of a permanent rainwater harvesting structure in Pardi Zankhri village of Olpad taluka.

    Irrigation, flood & environmentConstruction of rainwater harvesting structures· Surat· #208079

    ₹2.0 L Completed 6 Oct 2026Rec. 11 Jun 2025Paid ₹2.0 L
  • onstruction of paver blocks on one side of the main asphalt road up to the village outskirts (Padar) in Bhadol village.

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Surat· #320415

    ₹5.0 L Awaiting sanction · 26 daysRec. 6 Oct 2026

18th Lok Sabha MPs from Gujarat

Ranked by MP score

Compare
#MPUtilisationSpentCompletedScore
1C R Patil · Navsari83%48%27881
2Bharatbhai Manubhai Sutariya · Amreli90%47%20076
3Mansukhbhai Dhanjibhai Vasava · Bharuch81%47%23171
4Bharatsinhji Shankarji Dabhi · Patan88%57%16271
5Rajeshbhai Naranbhai Chudasama · Junagadh98%41%15771
6Mukeshkumar Chandrakaant Dalal · Surat83%29%10969
7Shobhanaben Mahendrasinh Baraiya · Sabarkantha77%43%13167
8Parshottambhai Rupala · Rajkot91%30%11567
9Dhaval Laxmanbhai Patel · Valsad64%30%7866
10Mitesh Rameshbhai Bakabhai Patel · Anand83%53%26765
11Dr. Mansukh Mandaviya · Porbandar96%28%8264
12Jaswantsinh Sumanbhai Bhabhor · Dahod90%21%9964

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.