10th of 21 from Odisha
Allocated limit
₹14.76 Cr
Median ₹14.70 Cr
Fund utilisation
99%
₹14.57 Cr recommended · 245 works
Above median (76%)
Paid to vendors
₹4.75 Cr
32% of allocation
Below median (37%)
Works completed
27
11% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP245 works
₹14.57 Cr · 99% of the ₹14.76 Cr allocated
- Sanctioned by the district143 works
58% sanctioned · took 3.8 months on average (due within 45 days)
- Completed27 works
₹1.39 Cr final cost · 6.6 months from recommendation on average
102 works are still awaiting sanction, 66 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 245 works worth ₹14.57 Cr, a fund utilisation of 99%, higher than 91% of 18th Lok Sabha MPs.
- The district has sanctioned 143 of them, taking 3.8 months on average.
- ₹4.75 Cr has been paid to vendors, 32% of the allocation.
- 27 works are complete, typically 6.6 months after recommendation. 15 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Roads & bridges.
- Payments went to 55 vendors. The largest received 13%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 46/100: finishing works counts most
- Works completed 30%11Completed ÷ recommended works.
- Spending efficiency 20%29Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%99Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%56Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%32Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SANSKRUTI ASSOCIATES PVT LTD, 13% of payments across 55 vendors.
District sanction speed
76/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%76Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
245 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
INSTALATION OF MULTIGYM AND GYM EQUIPMENTS AT - SHAKTIMAN GYMNASIUM, NANGALAKATA GP- BADJODI BLOCK- BARIPADA AGENCY- BDO BARIPADA
Sports & fitnessInstallation of multi-gym equipment· Mayurbhanj· #300043
₹20.0 L Sanctioned · 28 Oct 2026Rec. 31 Jul 2026CONSTRUCTION OF INCLINE &DOWNGRADE WITH CC ROAD GUARDWALL FROM CHAKRADHAR BEHERA HOUSE TO 60 METER LENGTH AND WEIGH OF 22FT AGENCY- ITDA KAPTIPADA
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· Mayurbhanj· #302744
₹5.0 L Sanctioned · 28 Oct 2026Rec. 11 Aug 2026CONSTRUCTION OF BATHING GHAT AT- NEAR PURUNAPANI SHIVA TEMPLE AGENCY- BDO SAMAKHUNTA
Sanitation & drainageConstruction of public toilets and bathrooms· Mayurbhanj· #303433
₹5.0 L Sanctioned · 28 Oct 2026Rec. 13 Aug 2026CONSTRUCTION OF CC ROAD FROM KHETRA HOUSE TO DASRATH HOUSE AT- SINDURGAURA VILLAGE AGENCY- BDO SAMAKHUNTA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Mayurbhanj· #303434
₹5.0 L Sanctioned · 28 Oct 2026Rec. 13 Aug 2026CONSTRUCTION OF CC ROAD FROM BAJRATUNDI TO LODHA SAHI DAS HOUSE TO MANATRI BHAKTA HOUSE AGENCY- BDO SAMAKHUNTA
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Mayurbhanj· #303435
₹5.0 L Sanctioned · 28 Oct 2026Rec. 13 Aug 2026CONSTRUCTION OF CULVERT NEAR KARAM BANDHA JANGIA BADA AGENCY- ITDA RAIRANGPUR
Roads & bridgesConstruction of culverts and bridges· Mayurbhanj· #304379
₹5.0 L Sanctioned · 28 Oct 2026Rec. 16 Aug 2026CONSTRUCTION OF GUARDWALL NEAR MAJHI BANDH DUBLABADA ROAD AT- HENSELDHI AGENCY- ITDA RAIRANGPUR
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· Mayurbhanj· #304380
₹5.0 L Sanctioned · 28 Oct 2026Rec. 16 Aug 2026CONSTRUCTION OF DRAIN AT- NUAGAON RAGHUNATHPUR ROAD NEAR PRIMERY SCHOOL AGENCY-ITDA RAIRANGPUR
Irrigation, flood & environmentConstruction of public irrigation facilities· Mayurbhanj· #304381
₹5.0 L Sanctioned · 28 Oct 2026Rec. 16 Aug 2026CONSTRUCTION OF CC ROAD RD ROAD TO SAMSANGHAT ROAD PARDHADA AGENCY- ITDA RAIRANGPUR
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Mayurbhanj· #304383
₹5.0 L Sanctioned · 28 Oct 2026Rec. 16 Aug 2026CONSTRUCTION OF GUARDWALL AT- RENGALBEDA KALYANI MANDAP TO S AMSAN ROAD AGENCY ITDA RAIRANGPUR
Irrigation, flood & environmentConstruction of flood control embankments/protection walls along riverbanks, hilltops, roadsides· Mayurbhanj· #304384
₹5.0 L Sanctioned · 28 Oct 2026Rec. 16 Aug 2026INSTALLATION OF HIGHMAST LIGHT AT- GHAT CHHAKA AT- JASHIPUR AGENCY-ITGA RAIRANGPUR
Electricity & lightingLighting of public spaces· Mayurbhanj· #324042
₹7.0 L Awaiting sanction · 9 daysRec. 23 Oct 2026INSTALLATION OF SOLAR HIGH MAST LIGHT AT- BASINGI DAILY MARKET NEAR SURU SHOP AGENCY-ITDA RAIRANGPUR
Electricity & lightingLighting of public spaces· Mayurbhanj· #324043
₹7.0 L Awaiting sanction · 9 daysRec. 23 Oct 2026INSTALLATION OF HIGHMAST LIGHT AT SAMSAN GHAT CHHACK AT-JASIPUR AGENCY-ITDA RAIRANGPUR
Electricity & lightingLighting of public spaces· Mayurbhanj· #324280
₹6.0 L Awaiting sanction · 9 daysRec. 23 Oct 2026INSTALLATION OF HIGH MAST LIGHT AT- JHADGAON CHHACK AGENCY- ITDA RAIRANGPUR
Electricity & lightingLighting of public spaces· Mayurbhanj· #324281
₹6.0 L Awaiting sanction · 9 daysRec. 23 Oct 2026INSTALLATION OF HIGH MAST LIGHT AT-NEAR JHARADHI HOSPITAL AGENCY- ITDA RAIRANGPUR
Electricity & lightingLighting of public spaces· Mayurbhanj· #324282
₹6.0 L Awaiting sanction · 9 daysRec. 23 Oct 2026
18th Lok Sabha MPs from Odisha
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Sambit Patra · Puri | 84% | 30% | 552 | 72 |
| 2 | Shri Jual Oram · Sundargarh | 94% | 40% | 91 | 66 |
| 3 | Sukanta Kumar Panigrahi · Kandhamal | 65% | 32% | 155 | 59 |
| 4 | Shri Bhartruhari Mahtab · Cuttack | 99% | 31% | 89 | 59 |
| 5 | Saptagiri Sankar Ulaka · Koraput | 73% | 28% | 201 | 54 |
| 6 | Pradeep Purohit · Bargarh | 86% | 27% | 52 | 52 |
| 7 | Balabhadra Majhi · Nabarangpur | 67% | 17% | 34 | 49 |
| 8 | Anita Subhadarshini · Aska | 41% | 10% | 26 | 48 |
| 9 | Malvika Devi · Kalahandi | 69% | 35% | 96 | 47 |
| 10 | Naba Charan Majhi · Mayurbhanj | 99% | 32% | 27 | 46 |
| 11 | Smt Aparajita Sarangi · Bhubaneswar | 74% | 25% | 47 | 45 |
| 12 | Smt Sangeeta Kumari Singh Deo · Bolangir | 54% | 6.0% | 12 | 45 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.