11th of 25 from Rajasthan
Works waiting for sanction
29 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.
Allocated limit
₹16.71 Cr
Median ₹14.70 Cr
Fund utilisation
69%
₹11.49 Cr recommended · 72 works
Below median (76%)
Paid to vendors
₹2.40 Cr
14% of allocation
Below median (37%)
Works completed
17
24% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP72 works
₹11.49 Cr · 69% of the ₹16.71 Cr allocated
- Sanctioned by the district38 works
53% sanctioned · took 3.8 months on average (due within 45 days)
- Completed17 works
₹1.43 Cr final cost · 9.7 months from recommendation on average
34 works are still awaiting sanction, 29 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 72 works worth ₹11.49 Cr, a fund utilisation of 69%, higher than 38% of 18th Lok Sabha MPs.
- The district has sanctioned 38 of them, taking 3.8 months on average.
- ₹2.40 Cr has been paid to vendors, 14% of the allocation.
- 17 works are complete, typically 9.7 months after recommendation. 13 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 20 vendors. The largest received 15%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 52/100: finishing works counts most
- Works completed 30%24Completed ÷ recommended works.
- Spending efficiency 20%60Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%69Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%76Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%14Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: SHRI LAXMI CONSTRUCTION, 15% of payments across 20 vendors.
District sanction speed
69/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%69Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
72 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Regarding the construction of a tin shed and other works at the Community Centre, Indra Path, Sector 12, Ward No. 48, in the Sanganer Assembly constituency.
Community buildings & public spacesConstruction of community centers and community halls· Jaipur· #325526
₹8.0 L Awaiting sanction · 0 daysRec. 1 Nov 2026Regarding the construction of the building for the Government Girls' Higher Secondary School, Sanganer, located in Ward No. 51 of the Sanganer Assembly constituency.
Education & librariesConstruction of rooms and halls in school and colleges· Jaipur· #325527
₹15.0 L Awaiting sanction · 0 daysRec. 1 Nov 2026Regarding the provision of necessary equipment and development work for Ward No. 79 of the Malviya Nagar Assembly constituency, located at the Rajasthan School of Arts, Jaipur (Block 9, Dr. Radhakrishnan Shiksha Sankul, JLN Marg, Jaipur).
Education & librariesPurchase of training equipment· Jaipur· #325528
₹10.0 L Awaiting sanction · 0 daysRec. 1 Nov 2026Regarding shifting of the transformer installed outside Palle Walon Ke Darwaze Sethyon Ke Chowk situated on Nahargarh Road in Ward No. 107 of Kishanpol Assembly Constituency.
Electricity & lightingImprovement of electricity distribution infrastructure· Jaipur· #318552
₹5.0 L Awaiting sanction · 35 daysRec. 27 Sep 2026construction of a community building near Nijhra Dhobi Ghat, located near Hanuman Ji temple in the Adarsh Nagar Assembly (Vidhan Sabha) constituency
Community buildings & public spacesConstruction of community centers and community halls· Jaipur· #318554
₹30.0 L Awaiting sanction · 35 daysRec. 27 Sep 2026For the construction of a
Community buildings & public spacesConstruction of community centers and community halls· Jaipur· #241671
₹15.0 L Sanctioned · 20 Aug 2026Rec. 12 Oct 2025For the expansion of the Jamdoli Moksha Dham construction.
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Jaipur· #277604
₹20.0 L Sanctioned · 20 Aug 2026Rec. 6 Apr 2026Construction of a box drain from Mangodi Walon Ki to the Brahmapuri Nala.
Sanitation & drainageProviding drains and gutters for public drainage· Jaipur· #277725
₹30.0 L Sanctioned · 20 Aug 2026Rec. 7 Apr 2026Regarding the Provision of Deep Freezers
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Jaipur· #277601
₹1.0 L Sanctioned · 19 Aug 2026Rec. 6 Apr 2026Regarding construction of second floor at Valmiki Community Centre in Balanandaji Ka Rasta, Valmiki Colony Chandpol Bazaar, Ward No. 57, Kishanpol Vidya Sabha area.
Community buildings & public spacesConstruction of community centers and community halls· Jaipur· #250951
₹20.0 L Sanctioned · 18 Aug 2026Rec. 27 Nov 2025Regarding the construction of a yoga shed at Siddheshwar Park, Pratap Nagar (Sector 19, Block 191, Ward No. 118), within the Bagru Assembly constituency.
Community buildings & public spacesDevelopment of public parks· Jaipur· #301221
₹10.0 L Sanctioned · 18 Aug 2026Rec. 4 Aug 2026Regarding the construction of a building for the Rana Rajput Seva Samiti, Jaipur, located opposite the Government Higher Primary School in Barna village (Ward No. 04 of the Vidyadhar Nagar Assembly constituency).
Community buildings & public spacesConstruction of community centers and community halls· Jaipur· #304787
₹20.0 L Awaiting sanction · 76 daysRec. 17 Aug 2026aadarsh nagar vidyansbha kshetra ke parking parisar damodar das dalmia vidyalaya keshav vidyapeeth jamdoli, jaipur ke upar se ja rahi 132 kv vidyut line parking parisar ke bahar shift karne babat
Electricity & lightingImprovement of electricity distribution infrastructure· Jaipur· #304365
₹50.0 L Awaiting sanction · 77 daysRec. 16 Aug 2026For construction of building at Kamla Devi Seva Bharti School, Shyam Vihar Colony, Khedi Mod, Buxawala, Sanganer Jaipur, Ward No. 98 of Sanganer Vidya Sabha area
Community buildings & public spacesConstruction of community centers and community halls· Jaipur· #303432
₹25.0 L Awaiting sanction · 80 daysRec. 13 Aug 2026Regarding changing one room and tin shed and carrying out other development works at Mokshdwar located in Mansarovar, Sanganer Assembly constituency.
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Jaipur· #302524
₹10.0 L Awaiting sanction · 83 daysRec. 10 Aug 2026
18th Lok Sabha MPs from Rajasthan
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Hanuman Beniwal · Nagaur | 59% | 44% | 184 | 68 |
| 2 | Lumbaram · Jalore | 67% | 45% | 96 | 67 |
| 3 | Brijendra Singh Ola · Jhunjhunu | 56% | 45% | 115 | 67 |
| 4 | Ummeda Ram Beniwal · Barmer | 78% | 48% | 99 | 66 |
| 5 | Sanjna Jatav · Bharatpur | 89% | 52% | 78 | 63 |
| 6 | Bhupender Yadav · Alwar | 75% | 43% | 32 | 62 |
| 7 | Damodar Agarwal · Bhilwara | 73% | 44% | 119 | 62 |
| 8 | Bhagirath Chaudhary · Ajmer | 73% | 36% | 64 | 59 |
| 9 | Shri Arjun Ram Meghwal · Bikaner | 63% | 24% | 20 | 53 |
| 10 | Amraram · Sikar | 56% | 27% | 56 | 53 |
| 11 | Manju Sharma · Jaipur | 69% | 14% | 17 | 52 |
| 12 | Raj Kumar Roat · Banswara | 87% | 48% | 23 | 52 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.