8th of 25 from Rajasthan
Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
73%
₹10.72 Cr recommended · 159 works
About the median
Paid to vendors
₹5.27 Cr
36% of allocation
About the median
Works completed
64
40% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP159 works
₹10.72 Cr · 73% of the ₹14.70 Cr allocated
- Sanctioned by the district121 works
76% sanctioned · took 4.0 months on average (due within 45 days)
- Completed64 works
₹3.70 Cr final cost · 9.4 months from recommendation on average
38 works are still awaiting sanction, 34 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 159 works worth ₹10.72 Cr, a fund utilisation of 73%, higher than 45% of 18th Lok Sabha MPs.
- The district has sanctioned 121 of them, taking 4.0 months on average.
- ₹5.27 Cr has been paid to vendors, 36% of the allocation.
- 64 works are complete, typically 9.4 months after recommendation. 36 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 514 vendors. The largest received 11%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 59/100: finishing works counts most
- Works completed 30%40Completed ÷ recommended works.
- Spending efficiency 20%70Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%73Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%56Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%36Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Jai Mata Rani Construction, 11% of payments across 514 vendors.
District sanction speed
77/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%77Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
159 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Public lighting system from Majhewla Bus Stand to Majhewla
Electricity & lightingLighting of public spaces· Ajmer· #315940
₹3.0 L Awaiting sanction · 44 daysRec. 18 Sep 2026Public lighting system in various streets of Village Kadel
Electricity & lightingLighting of public spaces· Ajmer· #315944
₹3.0 L Awaiting sanction · 44 daysRec. 18 Sep 2026Public lighting system in Village Rewat
Electricity & lightingLighting of public spaces· Ajmer· #315950
₹2.0 L Awaiting sanction · 44 daysRec. 18 Sep 2026Lighting system in various streets of Dungariya Kallan
Electricity & lightingLighting of public spaces· Ajmer· #315954
₹2.0 L Awaiting sanction · 44 daysRec. 18 Sep 2026CONSTRUCTION OF PUBLIC TOILET AND BATHROOM NEAR CHATURDAS JI MAHARAJ TEMPLE IN VILLAGE CHOTA NARENA
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #300061
₹5.0 L Sanctioned · 15 Sept 2026Rec. 31 Jul 2026Construction of Comunity hall near mata ji place at JOGINADA, gram panchayat pagara
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #201048
₹5.0 L Sanctioned · 8 Sept 2026Rec. 19 May 2025Construction of community hall near Chavandamaata temple in Junagaon Gudhakhurd
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #259555
₹5.0 L Sanctioned · 8 Sept 2026Rec. 17 Jan 2026Constructio of Open Tibara in Kharol Mohalla
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #261811
₹5.9 L Sanctioned · 8 Sept 2026Rec. 25 Jan 2026Construction of Comunity Hall neat Teja place kadel
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #140154
₹3.0 L Completed 5 Sept 2026Rec. 10 Sep 2024Paid ₹3.0 LConstruction of Teen shade and ladder in village rewat
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #140155
₹1.9 L Completed 5 Sept 2026Rec. 10 Sep 2024Paid ₹1.9 LSTREET LIGHT INSTALATION FROM MAJHEVLA BUS STAND TO KADEL
Electricity & lightingStreet lights· Ajmer· #215801
₹4.0 L Completed 5 Sept 2026Rec. 8 Jul 2025Paid ₹4.0 LRoad light work in village Sarasdi of Gram Panchayat Kalesara, Panchayat Samiti Pisangan
Electricity & lightingStreet lights· Ajmer· #277889
₹7.5 L Completed 31 Aug 2026Rec. 10 Apr 2026Paid ₹7.5 LCommunity hall and boundary wall construction in Gudli, Panchayat Bir
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #240586
₹5.0 L Completed 25 Aug 2026Rec. 7 Oct 2025Paid ₹5.0 LCommunity hall construction work in ward no 59
Community buildings & public spacesConstruction of community centers and community halls· Ajmer· #199757
₹4.4 L Completed 20 Aug 2026Rec. 15 May 2025Paid ₹4.4 LConstruction of cemented block road from Khandal Brahmin Hostel to the main road in front of Jaipur Road.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Ajmer· #247437
₹7.3 L Completed 20 Aug 2026Rec. 11 Nov 2025Paid ₹7.3 L
18th Lok Sabha MPs from Rajasthan
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Hanuman Beniwal · Nagaur | 59% | 44% | 184 | 68 |
| 2 | Lumbaram · Jalore | 67% | 45% | 96 | 67 |
| 3 | Brijendra Singh Ola · Jhunjhunu | 56% | 45% | 115 | 67 |
| 4 | Ummeda Ram Beniwal · Barmer | 78% | 48% | 99 | 66 |
| 5 | Sanjna Jatav · Bharatpur | 89% | 52% | 78 | 63 |
| 6 | Bhupender Yadav · Alwar | 75% | 43% | 32 | 62 |
| 7 | Damodar Agarwal · Bhilwara | 73% | 44% | 119 | 62 |
| 8 | Bhagirath Chaudhary · Ajmer | 73% | 36% | 64 | 59 |
| 9 | Shri Arjun Ram Meghwal · Bikaner | 63% | 24% | 20 | 53 |
| 10 | Amraram · Sikar | 56% | 27% | 56 | 53 |
| 11 | Manju Sharma · Jaipur | 69% | 14% | 17 | 52 |
| 12 | Raj Kumar Roat · Banswara | 87% | 48% | 23 | 52 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.