Re-elected to the 18th Lok Sabha Then: 94% utilisation, 33 works completed, score 69.
  • Payments concentrated with one vendor

    53% of vendor payments went to Aradhya Agency.

Allocated limit

₹9.81 Cr

Median ₹8.60 Cr

Fund utilisation

100%

₹9.79 Cr recommended · 70 works
About the median

Paid to vendors

₹9.68 Cr

99% of allocation
Above median (88%)

Works completed

56

80% of recommended
About the median

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP70 works

    ₹9.79 Cr · 100% of the ₹9.81 Cr allocated

  2. Sanctioned by the district70 works

    100% sanctioned · took 2.7 months on average (due within 45 days)

  3. Completed56 works

    ₹8.19 Cr final cost · 27.9 months from recommendation on average

In plain words

What the numbers say

  • Recommended 70 works worth ₹9.79 Cr, a fund utilisation of 100%, higher than 77% of 17th Lok Sabha MPs.
  • The district has sanctioned 70 of them, taking 2.7 months on average.
  • ₹9.68 Cr has been paid to vendors, 99% of the allocation.
  • 56 works are complete, typically 27.9 months after recommendation. 45 works have geo-tagged photos on eSAKSHI.
  • The largest share of funds went to Electricity & lighting.
  • Payments went to 37 vendors. The largest received 53%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 84/100: finishing works counts most

  1. Works completed 30%80Completed ÷ recommended works.
  2. Spending efficiency 20%85Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%100Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%80Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%99Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    59
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: Aradhya Agency, 53% of payments across 37 vendors.

District sanction speed

94/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%94Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

70 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Purchase of computer (Desktop) for Ramkrishnanagar college at Ramkrishnanagar

    Education & librariesPurchase of IT systems, including hardware and software for educational purposes· Sribhumi· #8821

    ₹20.0 L Completed 23 Sept 2026Rec. 11 Aug 2023Paid ₹20.0 L
  • Installation of Solar Street light Double Arm LED 40W with Pole 6M

    Electricity & lightingStreet lights· Sribhumi· #18357

    ₹12.9 L Completed 23 Sept 2026Rec. 9 Sep 2023Paid ₹12.9 L
  • Construction of Community Hall Near Kali Mandir Sevashram Bidyanagar

    Community buildings & public spacesConstruction of community centers and community halls· Sribhumi· #48640

    ₹10.0 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹10.0 L
  • Construction of Road with C.C. block along with side drain including slab from Balicherra Smasan Road to the house of Bikash Ranjan Singha at R.K Nagar.

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Sribhumi· #48646

    ₹10.0 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹10.0 L
  • Infrastructure development of Communication Hall near Anandpur Mukamkalibari at Village Dagarbond Pt-II Phase-III

    Community buildings & public spacesConstruction of community centers and community halls· Sribhumi· #48647

    ₹25.0 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹25.0 L
  • Installation of Solar Street Light Double Arm LED40W with pole 6M

    Electricity & lightingStreet lights· Sribhumi· #48659

    ₹17.7 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹17.7 L
  • Installation of Solar Street Light Double Arm LED40W with pole 6M

    Electricity & lightingStreet lights· Sribhumi· #48661

    ₹17.7 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹17.7 L
  • Installation of Solar Street Light Double Arm LED40W with pole 6M

    Electricity & lightingStreet lights· Sribhumi· #48663

    ₹17.7 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹17.7 L
  • Installation of Solar Street Light Double Arm LED40W with pole 6M

    Electricity & lightingStreet lights· Sribhumi· #48665

    ₹17.7 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹17.7 L
  • Installation of Solar Street Light Double Arm LED40W with pole 6M

    Electricity & lightingStreet lights· Sribhumi· #48667

    ₹17.7 L Completed 23 Sept 2026Rec. 10 Nov 2023Paid ₹17.7 L
  • Distribution of Solar Fan & Home Lighting system.

    Electricity & lightingPurchase of non-conventional energy system and devices for community use· Sribhumi· #22554

    ₹15.6 L Completed 20 Sept 2026Rec. 18 Sep 2023Paid ₹15.6 L
  • Distribution of Solar Fan & Home Lighting system at Different Govt. Institutions at Dullavcherra Block.

    Electricity & lightingPurchase of non-conventional energy system and devices for community use· Sribhumi· #22556

    ₹19.4 L Completed 20 Sept 2026Rec. 18 Sep 2023Paid ₹19.4 L
  • Distribution of Solar Fan & Home Lighting system at Different Govt. Institutions at Lowairpoa Block.

    Electricity & lightingPurchase of non-conventional energy system and devices for community use· Sribhumi· #22567

    ₹15.6 L Completed 20 Sept 2026Rec. 18 Sep 2023Paid ₹15.6 L
  • Distribution of Solar Fan & Home Lighting system at Different Govt. Institutions at North Karimganj Block.

    Electricity & lightingPurchase of non-conventional energy system and devices for community use· Sribhumi· #22618

    ₹15.6 L Completed 20 Sept 2026Rec. 18 Sep 2023Paid ₹15.6 L
  • Distribution of Solar Fan & Home Lighting system at Different Govt. Institutions at Patharkandi Block.

    Electricity & lightingPurchase of non-conventional energy system and devices for community use· Sribhumi· #22619

    ₹15.6 L Completed 20 Sept 2026Rec. 18 Sep 2023Paid ₹15.6 L

17th Lok Sabha MPs from Assam

Ranked by MP score

#MPUtilisationSpentCompletedScore
1Kripanath Mallah · Karimganj100%99%5684
2Maulana Ajmal Badruddin · Dhubri99%90%6283
3Rajdeep Roy · Silchar100%99%10283
4Shri Abdul Khaleque · Barpeta98%86%11276
5Topon Kumar Gogoi · Jorhat99%91%9271
6Dilip Saikia · Darrang-Udalguri94%77%11169
7Horen Sing Bey · Diphu100%93%2065
8Pradan Baruah · Lakhimpur94%85%4263
9Shri Naba (Hira) Kumar Sarania · Kokrajhar99%89%2062
10Pradyut Bordoloi · Nowgong94%81%4362
11Pallab Lochan Das · Sonitpur99%94%5659
12Queen Oja · Guwahati91%86%555

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.