13th of 14 from Assam
Allocated limit
₹4.91 Cr
Median ₹8.60 Cr
Fund utilisation
98%
₹4.81 Cr recommended · 212 works
About the median
Paid to vendors
₹3.68 Cr
75% of allocation
Below median (88%)
Works completed
45
21% of recommended
Below median (83%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP212 works
₹4.81 Cr · 98% of the ₹4.91 Cr allocated
- Sanctioned by the district195 works
92% sanctioned · took 5.3 months on average (due within 45 days)
- Completed45 works
₹94.5 L final cost · 16.1 months from recommendation on average
17 works are still awaiting sanction, 17 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 212 works worth ₹4.81 Cr, a fund utilisation of 98%, higher than 50% of 17th Lok Sabha MPs.
- The district has sanctioned 195 of them, taking 5.3 months on average.
- ₹3.68 Cr has been paid to vendors, 75% of the allocation.
- 45 works are complete, typically 16.1 months after recommendation. 21 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 91 vendors. The largest received 10%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 51/100: finishing works counts most
- Works completed 30%21Completed ÷ recommended works.
- Spending efficiency 20%26Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%98Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%47Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%75Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: R G TRADERS, 10% of payments across 91 vendors.
District sanction speed
78/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%78Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
212 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Community Hall at Dakhin Dhingbori Chapari near Subahi Muktab, Dhingbori Chapari GP
Community buildings & public spacesConstruction of community centers and community halls· Nagaon· #52960
₹5.0 L Sanctioned · 31 Jul 2026Rec. 25 Nov 2023Renovation of Community Hall at Dakhin Putakolong Majuli Muktab School, Dakhin Putakolong, Ambagan GP
Community buildings & public spacesConstruction of community centers and community halls· Nagaon· #117462
₹1.0 L Sanctioned · 14 Mar 2026Rec. 29 Feb 2024Construction of office room at Cooperative Society, Balikatia. Jengoni Kolarduba GP
Community buildings & public spacesConstruction of community centers and community halls· Nagaon· #51282
₹3.0 L Completed 18 Dec 2025Rec. 21 Nov 2023Paid ₹3.0 LDevelopment of Borsaikia Namuni Chuk Path, 70 GP
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Jorhat· #35422
₹3.0 L Completed 24 Oct 2025Rec. 10 Oct 2023Paid ₹3.0 LConstruction of Community Hall at 1 no Lalung Gaon near Madrassa, Juria Block, Dhingbari Chapari GP
Community buildings & public spacesConstruction of community centers and community halls· Nagaon· #23371
₹4.0 L Completed 17 Sept 2025Rec. 20 Sep 2023Paid ₹4.0 LDevelopment of Batabari Anchalik Kabarsthan, Sahari GP
Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Nagaon· #52948
₹3.0 L Vendor Identification · 5 Sept 2025Rec. 25 Nov 2023Paid ₹1.8 LConstruction of Boundary Wall at Dakhin Singia Pather Burial Ground, Juria Block, Godaimari GP
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Nagaon· #23364
₹3.0 L Completed 4 Sept 2025Rec. 20 Sep 2023Paid ₹3.0 LConstruction of Boundary wall at 2No Langia Kabarsthan, Jaramari GP
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Nagaon· #51281
₹3.0 L Completed 2 Sept 2025Rec. 21 Nov 2023Paid ₹3.0 LConstruction of Morajan Namghar, Panjan GP
Community buildings & public spacesConstruction of community centers and community halls· Golaghat· #35752
₹2.0 L Completed 31 Aug 2025Rec. 11 Oct 2023Paid ₹2.0 LConstruction of Boundary Wall near at St. Joseph Catholic Church, 1 no Amguri Chungajan, Chungajan M.V.GP
Community buildings & public spacesConstruction of additional rooms and halls in the existing public and community building· Golaghat· #35754
₹2.5 L Completed 31 Aug 2025Rec. 11 Oct 2023Paid ₹2.5 LConstruction of Community Center at 8 No Ward Rongagora gaon (Near Chtistoprem Bapist Church), Gelabil GP
Community buildings & public spacesConstruction of community centers and community halls· Golaghat· #35755
₹2.5 L Completed 31 Aug 2025Rec. 11 Oct 2023Paid ₹2.5 LConstruction of Tengani Sirumoni Sankari Sanskritik Kendra, Pachim Borpathar GP
Community buildings & public spacesConstruction of community centers and community halls· Golaghat· #35851
₹2.0 L Completed 31 Aug 2025Rec. 11 Oct 2023Paid ₹2.0 LConstruction of Tirual Bura Namghar, Premhora GP
Community buildings & public spacesConstruction of community centers and community halls· Golaghat· #35853
₹1.5 L Completed 31 Aug 2025Rec. 11 Oct 2023Paid ₹1.5 LConstruction of Diljan Sautal Cultural Center, Rajaphukuri GP
Community buildings & public spacesConstruction of community centers and community halls· Golaghat· #35855
₹1.5 L Completed 31 Aug 2025Rec. 11 Oct 2023Paid ₹1.5 LConstruction of Amguri Bosapathar Namghar, Ratanpur GP
Community buildings & public spacesConstruction of community centers and community halls· Golaghat· #35856
₹2.5 L Completed 31 Aug 2025Rec. 11 Oct 2023Paid ₹2.5 L
17th Lok Sabha MPs from Assam
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Kripanath Mallah · Karimganj | 100% | 99% | 56 | 84 |
| 2 | Maulana Ajmal Badruddin · Dhubri | 99% | 90% | 62 | 83 |
| 3 | Rajdeep Roy · Silchar | 100% | 99% | 102 | 83 |
| 4 | Shri Abdul Khaleque · Barpeta | 98% | 86% | 112 | 76 |
| 5 | Topon Kumar Gogoi · Jorhat | 99% | 91% | 92 | 71 |
| 6 | Dilip Saikia · Darrang-Udalguri | 94% | 77% | 111 | 69 |
| 7 | Horen Sing Bey · Diphu | 100% | 93% | 20 | 65 |
| 8 | Pradan Baruah · Lakhimpur | 94% | 85% | 42 | 63 |
| 9 | Shri Naba (Hira) Kumar Sarania · Kokrajhar | 99% | 89% | 20 | 62 |
| 10 | Pradyut Bordoloi · Nowgong | 94% | 81% | 43 | 62 |
| 11 | Pallab Lochan Das · Sonitpur | 99% | 94% | 56 | 59 |
| 12 | Queen Oja · Guwahati | 91% | 86% | 5 | 55 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.