23rd of 25 from Rajasthan
Works waiting for sanction
188 recommended works are still awaiting sanction more than 45 days later. Sanction is the district authority’s responsibility.
Recommended, but little spent
54% of funds recommended, but only 4.6% paid out to vendors.
No completed works reported
196 works recommended, none reported complete yet.
Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
54%
₹7.95 Cr recommended · 196 works
Below median (76%)
Paid to vendors
₹67.2 L
4.6% of allocation
Below median (37%)
Works completed
0
0% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP196 works
₹7.95 Cr · 54% of the ₹14.70 Cr allocated
- Sanctioned by the district8 works
4.1% sanctioned · took 44 days on average (due within 45 days)
- Completed0 works
₹0 final cost
188 works are still awaiting sanction, 188 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 196 works worth ₹7.95 Cr, a fund utilisation of 54%, higher than 16% of 18th Lok Sabha MPs.
- The district has sanctioned 8 of them, taking 44 days on average.
- ₹67.2 L has been paid to vendors, 4.6% of the allocation.
- 0 works are complete.
- The largest share of funds went to Education & libraries.
- Payments went to 23 vendors. The largest received 34%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 17/100: finishing works counts most
- Works completed 30%0Completed ÷ recommended works.
- Spending efficiency 20%0Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%54Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%0Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%5Paid to vendors ÷ allocated limit.
- Vendor diversity 10%82How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Jai mata di construction kelwara, 34% of payments across 23 vendors.
District sanction speed
52/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%52Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
196 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Boundary wall and park development work of Bagh playground in front of Gram Panchayat office Antana, village Antana.
Community buildings & public spacesDevelopment of public parks· Baran· #284691
₹6.0 L Sanctioned · 25 Sept 2026Rec. 3 Jul 2026Construction work of interlocking Kharanja drain from the main road towards Pappu Mali's house in village Vyas Khedi.
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Baran· #300753
₹6.0 L Work partially Completed · 16 Sept 2026Rec. 3 Aug 2026Paid ₹4.8 LConstruction of a classroom with verandah at Government Higher Secondary School, Harnavada Shahji.
Education & librariesConstruction of rooms and halls in school and colleges· Baran· #315633
₹4.8 L Awaiting sanction · 46 daysRec. 16 Sep 2026Construction of a classroom with verandah at Government Higher Secondary School, Kasbathana.
Education & librariesConstruction of rooms and halls in school and colleges· Baran· #315634
₹4.8 L Awaiting sanction · 46 daysRec. 16 Sep 2026Construction work of multi-purpose dome (tin shed at prayer hall) in Government Adarsh Higher Secondary School, Himmatgarh. (33x20 Meter (660 SQM) PPC, Inerlocking RSF Truss Agle, RSF GI Corrugated Sheet)
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Jhalawar· #299650
₹18.8 L Sanctioned · 31 Aug 2026Rec. 3 Aug 2026Anganwadi building construction in Turkadia school campus, Turkadia
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305440
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Bhalta -1 school campus, Bhalta
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305441
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Ghatoli-2 school campus, Ghatoli
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305442
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Borband school campus, Borband
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305443
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Asnawar-1 school campus, Asnawar
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305444
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Aanwalheda-1 school campus, Aanwalheda
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305445
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Jawar-1 school campus, Jawar
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305447
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Arjunpura-1 school campus, Arjunpura
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305449
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Kherkheda school campus, Kherkheda
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305450
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026Anganwadi building construction in Dangipura school campus, Dangipura
Education & librariesConstruction of buildings for crèches and anganwadies· Jhalawar· #305452
₹4.0 L Awaiting sanction · 69 daysRec. 24 Aug 2026
18th Lok Sabha MPs from Rajasthan
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Shri Hanuman Beniwal · Nagaur | 59% | 44% | 184 | 68 |
| 2 | Lumbaram · Jalore | 67% | 45% | 96 | 67 |
| 3 | Brijendra Singh Ola · Jhunjhunu | 56% | 45% | 115 | 67 |
| 4 | Ummeda Ram Beniwal · Barmer | 78% | 48% | 99 | 66 |
| 5 | Sanjna Jatav · Bharatpur | 89% | 52% | 78 | 63 |
| 6 | Bhupender Yadav · Alwar | 75% | 43% | 32 | 62 |
| 7 | Damodar Agarwal · Bhilwara | 73% | 44% | 119 | 62 |
| 8 | Bhagirath Chaudhary · Ajmer | 73% | 36% | 64 | 59 |
| 9 | Shri Arjun Ram Meghwal · Bikaner | 63% | 24% | 20 | 53 |
| 10 | Amraram · Sikar | 56% | 27% | 56 | 53 |
| 11 | Manju Sharma · Jaipur | 69% | 14% | 17 | 52 |
| 12 | Raj Kumar Roat · Banswara | 87% | 48% | 23 | 52 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.