4th of 7 from Delhi
Allocated limit
₹15.43 Cr
Median ₹14.70 Cr
Fund utilisation
46%
₹7.11 Cr recommended · 113 works
Below median (76%)
Paid to vendors
₹2.92 Cr
19% of allocation
Below median (37%)
Works completed
47
42% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP113 works
₹7.11 Cr · 46% of the ₹15.43 Cr allocated
- Sanctioned by the district80 works
71% sanctioned · took 2.3 months on average (due within 45 days)
- Completed47 works
₹2.36 Cr final cost · 10.8 months from recommendation on average
33 works are still awaiting sanction, 31 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 113 works worth ₹7.11 Cr, a fund utilisation of 46%, higher than 9.6% of 18th Lok Sabha MPs.
- The district has sanctioned 80 of them, taking 2.3 months on average.
- ₹2.92 Cr has been paid to vendors, 19% of the allocation.
- 47 works are complete, typically 10.8 months after recommendation. 47 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 27 vendors. The largest received 16%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 62/100: finishing works counts most
- Works completed 30%42Completed ÷ recommended works.
- Spending efficiency 20%81Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%46Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%19Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Swing Craft, 16% of payments across 27 vendors.
District sanction speed
83/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%83Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
113 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Installation of Four Boom Barriers
Safety & securitySecurity gates in streets/public place for safety purpose· Central· #312536
₹11.1 L Sanctioned · 22 Oct 2026Rec. 5 Sep 2026Installation of Childrens Play Equipment (Swings)
Sports & fitnessDevelopment of playfields and sports grounds· Central· #322727
₹11.3 L Awaiting sanction · 10 daysRec. 22 Oct 2026Provision of lighting arrangement
Electricity & lightingLighting of public spaces· Central· #322729
₹16.6 L Awaiting sanction · 10 daysRec. 22 Oct 2026Provision of lighting arrangement
Electricity & lightingLighting of public spaces· Central· #261158
₹6.8 L Completed 5 Oct 2026Rec. 31 Jan 2026Paid ₹6.8 LProvision of lighting arrangement
Electricity & lightingLighting of public spaces· Central· #261225
₹5.5 L Completed 5 Oct 2026Rec. 31 Jan 2026Paid ₹5.5 LProvision of lighting arrangement
Electricity & lightingLighting of public spaces· Central· #266758
₹7.5 L Completed 5 Oct 2026Rec. 10 Feb 2026Paid ₹7.5 LProvision of lighting arrangement
Electricity & lightingLighting of public spaces· Central· #277944
₹6.4 L Completed 5 Oct 2026Rec. 23 Apr 2026Paid ₹6.4 LWork for Construction, Improvement/Development of Road by providing RMC (Ready Mix Concrete)
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Central· #312537
₹19.2 L Awaiting sanction · 57 daysRec. 5 Sep 2026Work for Construction, Improvement/Development of Lane by providing Ready Mix Concrete (RMC)
Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Central· #312548
₹20.8 L Awaiting sanction · 57 daysRec. 5 Sep 2026Provision of lighting arrangement
Electricity & lightingLighting of public spaces· Central· #250043
₹6.5 L Completed 3 Sept 2026Rec. 25 Nov 2025Paid ₹6.5 LProvision of lighting arrangement
Electricity & lightingStreet lights· Central· #310742
₹3.8 L Awaiting sanction · 60 daysRec. 2 Sep 2026Provision of lighting arrangement
Electricity & lightingStreet lights· Central· #310743
₹13.3 L Awaiting sanction · 60 daysRec. 2 Sep 2026Installation of Two Boom Barriers
Safety & securitySecurity gates in streets/public place for safety purpose· Central· #310744
₹6.5 L Awaiting sanction · 60 daysRec. 2 Sep 2026Provision of lighting arrangement
Electricity & lightingStreet lights· Central· #310745
₹7.8 L Awaiting sanction · 60 daysRec. 2 Sep 2026Providing and fixing of rubber flooring under open gym equipment
Community buildings & public spacesDevelopment of public parks· Central· #298281
₹8.0 L Sanctioned · 31 Aug 2026Rec. 27 Jul 2026
18th Lok Sabha MPs from Delhi
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Kamaljeet Sehrawat · West Delhi | 63% | 11% | 32 | 66 |
| 2 | Praveen Khandelwal · Chandini Chowk | 43% | 21% | 38 | 65 |
| 3 | Harsh Malhotra · East Delhi | 53% | 25% | 65 | 64 |
| 4 | Bansuri Swaraj · New Delhi | 46% | 19% | 47 | 62 |
| 5 | Ramvir Singh Bidhuri · South Delhi | 88% | 25% | 43 | 62 |
| 6 | Yogendra Chandoliya · North West Delhi | 62% | 10% | 11 | 51 |
| 7 | Manoj Tiwari · North East Delhi | 57% | 13% | 7 | 41 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.