4th of 5 from Jammu and Kashmir
Allocated limit
₹15.48 Cr
Median ₹14.70 Cr
Fund utilisation
60%
₹9.26 Cr recommended · 268 works
Below median (76%)
Paid to vendors
₹3.36 Cr
22% of allocation
Below median (37%)
Works completed
50
19% of recommended
Below median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP268 works
₹9.26 Cr · 60% of the ₹15.48 Cr allocated
- Sanctioned by the district149 works
56% sanctioned · took 3.7 months on average (due within 45 days)
- Completed50 works
₹2.24 Cr final cost · 6.1 months from recommendation on average
119 works are still awaiting sanction, 29 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 268 works worth ₹9.26 Cr, a fund utilisation of 60%, higher than 23% of 18th Lok Sabha MPs.
- The district has sanctioned 149 of them, taking 3.7 months on average.
- ₹3.36 Cr has been paid to vendors, 22% of the allocation.
- 50 works are complete, typically 6.1 months after recommendation. 42 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Electricity & lighting.
- Payments went to 50 vendors. The largest received 11%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 53/100: finishing works counts most
- Works completed 30%19Completed ÷ recommended works.
- Spending efficiency 20%67Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%60Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%84Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%22Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: MADIHA TRADERS, 11% of payments across 50 vendors.
District sanction speed
84/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%84Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
268 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Providing Sports Gears to different Sports Clubs in District Budgam.
Sports & fitnessProviding sports equipment, except consumable items· Budgam· #321815
₹5.0 L Sanctioned · 31 Oct 2026Rec. 12 Oct 2026Installation of 25KVA Transformer at Badran, Peth-dradhun.
Electricity & lightingImprovement of electricity distribution infrastructure· Budgam· #314182
₹3.2 L Sanctioned · 27 Oct 2026Rec. 10 Sep 2026Purchase of Force Tempo Ambulance Type B for PHC Soibugh.
HealthPurchase of ambulances (Four, Three and Two wheelers)· Budgam· #288165
₹17 Sanctioned · 21 Oct 2026Rec. 22 Jun 2026Construction of Drain near Masjid Shareef Shahi Jahan, Ward no 7, Chewa
Sanitation & drainageProviding drains and gutters for public drainage· Bandipora· #250917
₹1.1 L Completed 20 Oct 2026Rec. 27 Nov 2025Paid ₹1.1 LConstruction of Tile Path from Guru Mohallah to House of Ab Majeed Wani and Ab Majeed Sheikh at Potpora Sumlar.
Roads & bridgesConstruction of footpaths and pedestrian ways· Bandipora· #323632
₹1.3 L Awaiting sanction · 12 daysRec. 20 Oct 2026Construction of Tile Path from House of Bashir Ah Wani, Gh Nabi Wani, Ab Rashid Wani at Patipora, Sumlar A.
Roads & bridgesConstruction of footpaths and pedestrian ways· Bandipora· #323633
₹80,000 Awaiting sanction · 12 daysRec. 20 Oct 2026Construction of Protection Wall near House of Farooq Ah Wani, Gh Mohiudin Lone at Bonpora Sumlar A
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Bandipora· #323634
₹80,000 Awaiting sanction · 12 daysRec. 20 Oct 2026Construction of Protection Wall near House of Hafiz Qazafi Khan to Onwards at Panzigam
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Bandipora· #323635
₹1.2 L Awaiting sanction · 12 daysRec. 20 Oct 2026Construction of Concrete Path from House of Mushtaq Ahmad Khan to M. Sultan Khan near Noor Masjid Stadium Colony, Ward no1 along with Cover Drain with Iron plates from House of Mushtaq Ah. Khan to House of Ab Gaffar Wani. (Phase 1)
Roads & bridgesConstruction of footpaths and pedestrian ways· Bandipora· #323636
₹2.5 L Awaiting sanction · 12 daysRec. 20 Oct 2026Construction of Lining Wall /path from House of Gh Hassan Dar upto Cement Bridge at Ward no 14 Nathpora Bandipora.
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Bandipora· #323641
₹1.0 L Awaiting sanction · 12 daysRec. 20 Oct 2026Construction of Drain with Grilled iron cover near House of Ab Razak Bhat at Chewa A, near Masjid Shahjahan, ward no 7.
Sanitation & drainageProviding drains and gutters for public drainage· Bandipora· #323643
₹1.0 L Awaiting sanction · 12 daysRec. 20 Oct 2026Procurement of C-ARM Machine for CHC Dawar Gurez.
HealthPurchase of hospital equipment· Bandipora· #323425
₹21.0 L Awaiting sanction · 15 daysRec. 17 Oct 2026Beautification of Main Market Wagoora and Main Market Kreeri by way of Installation of Ornamental Solar Street Lights.
Electricity & lightingLighting of public spaces· Baramulla· #323426
₹4.0 L Awaiting sanction · 15 daysRec. 17 Oct 2026Purchase of Portable ECG and Dental Chair for NTPHC Trehgam.
HealthPurchase of hospital equipment· Kupwara· #322271
₹6.5 L Awaiting sanction · 18 daysRec. 14 Oct 2026Construction of P-Bund near Madrasa Islah-ul-Bannat at Sarmargi, Dori Mohallah
Community buildings & public spacesConstruction of boundary walls of existing public and community buildings· Kupwara· #322273
₹1.5 L Awaiting sanction · 18 daysRec. 14 Oct 2026
18th Lok Sabha MPs from Jammu and Kashmir
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Jitendra Singh · Udhampur | 81% | 36% | 195 | 74 |
| 2 | Aga Syed Ruhullah Mehdi · Srinagar | 99% | 17% | 66 | 62 |
| 3 | Shri Jugal Kishore Sharma · Jammu | 78% | 24% | 51 | 55 |
| 4 | Abdul Rashid Sheikh · Baramullah | 60% | 22% | 50 | 53 |
| 5 | Mian Altaf Ahmad · Anantnag | 93% | 21% | 22 | 52 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.