State profile
Meghalaya
3 MPs: 2 in the Lok Sabha and 1 in the Rajya Sabha. Median MP score 66 out of 100.
Allocated
₹29.40 Cr
3 MPs
Fund utilisation
88%
₹26.02 Cr recommended · 625 works
Sanctioned
82%
71 works waiting over 45 days
Paid to vendors
₹18.06 Cr
61% of allocation
Works completed
249
40% of recommended works
Follow the money
Bar length relative to the largest stage
- Allocated limit₹29.40 Cr
- Recommended by MPs₹26.02 Cr
88% fund utilisation · 625 works
- Paid to vendors₹18.06 Cr
61% of allocation · 822 payments
- Value of completed works₹9.50 Cr
249 works finished
Top sectors
Value of works recommended in Meghalaya
MPs from Meghalaya
Ranked by MP score. How it’s scored
| # | MP | House | Utilisation | Spent | Completion | Score |
|---|---|---|---|---|---|---|
| 1 | Saleng A SangmaTura | Lok Sabha | 99% | 73% | 41% | 67 |
| 2 | Andrew J. SyngkonShillong | Lok Sabha | 100% | 74% | 43% | 66 |
| 3 | Shri James Pangsang Kongkal SangmaRajya Sabha | Rajya Sabha | 34% | 0% | 0% | 7 |
Implementing agencies
District authorities with the most works recommended
| Agency | Works | Awaiting sanction | Completed | Avg time |
|---|---|---|---|---|
| West Garo Hills | 149 | 22 (2 late) | 92 (62%) | 11.4 months |
| East Garo Hills | 99 | 61 (55 late) | 2 (2.0%) | 54 days |
| Ri Bhoi | 78 | 6 (5 late) | 35 (45%) | 10.9 months |
| East Khasi Hills | 65 | 5 (5 late) | 21 (32%) | 12.7 months |
| North Garo Hills | 60 | 5 | 33 (55%) | 10.5 months |
| South West Garo Hills | 47 | 6 (2 late) | 5 (11%) | 8.1 months |
| West Jaintia Hills | 40 | 1 (1 late) | 16 (40%) | 8.4 months |
| South Garo Hills | 25 | 4 | 13 (52%) | 18.0 months |
| East Jaintia Hills | 20 | 0 | 13 (65%) | 11.8 months |
| West Khasi Hills | 16 | 2 | 6 (38%) | 13.9 months |
Worth asking about
Each flag states the rule that triggered it. It prompts a question; it is not a finding of wrongdoing.
- Shri James Pangsang Kongkal SangmaRajya Sabha
No completed works reported
32 works recommended, none reported complete yet.