Skip to content
MPLADSTracker
This is a record from the 17th Lok Sabha (2019–24). eSAKSHI covers its final year only, from April 2023. Comparisons are with other 17th Lok Sabha MPs.

MPLADS report card · 17th Lok Sabha

Shrikant Eknath Shinde

Lok SabhaKalyan · Maharashtra

MP score57/100509th of 539 in the 17th Lok Sabha
44th of 48 from Maharashtra
Re-elected to the 18th Lok Sabha Then: 1.9% utilisation, 0 works completed, score 1.

Allocated limit

₹7.36 Cr

Median ₹8.60 Cr

Fund utilisation

97%

₹7.12 Cr recommended · 34 works
About the median

Paid to vendors

₹3.62 Cr

49% of allocation
Below median (88%)

Works completed

16

47% of recommended
Below median (83%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP34 works

    ₹7.12 Cr · 97% of the ₹7.36 Cr allocated

  2. Sanctioned by the district33 works

    97% sanctioned · took 11.6 months on average (due within 45 days)

  3. Completed16 works

    ₹2.54 Cr final cost · 14.0 months from recommendation on average

1 works are still awaiting sanction, 1 of them for more than 45 days.

In plain words

What the numbers say

  • Recommended 34 works worth ₹7.12 Cr, a fund utilisation of 97%, higher than 42% of 17th Lok Sabha MPs.
  • The district has sanctioned 33 of them, taking 11.6 months on average.
  • ₹3.62 Cr has been paid to vendors, 49% of the allocation.
  • 16 works are complete, typically 14.0 months after recommendation.
  • The largest share of funds went to Sports & fitness.
  • Payments went to 14 vendors. The largest received 23%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 57/100: finishing works counts most

  1. Works completed 30%47Completed ÷ recommended works.
  2. Spending efficiency 20%70Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%97Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%0Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%49Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    96
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: Shree Ganesh Infra, 23% of payments across 14 vendors.

District sanction speed

50/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%50Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

34 works · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Smt. Suhasini Adhikari Construction of primary school classrooms and other construction works in Ambernath Municipal Council area

    Education & librariesConstruction of rooms and halls in school and colleges· Thane· #130606

    ₹7.5 L Work partially Completed · 21 Sept 2026Rec. 16 Mar 2024Paid ₹7.3 L
  • Construction of primary school classrooms and other construction works in Smt. Suhasini Adhikari school, Ambernath Municipal Council Area

    Education & librariesConstruction of rooms and halls in school and colleges· Thane· #165327

    ₹7.5 L Work partially Completed · 21 Sept 2026Rec. 14 Jan 2024Paid ₹7.3 L
  • Carrying out various construction works near Mr. Mukne's house at Ulhasnagar 3 in Ulhasnagar Municipal Corporation.

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Thane· #130660

    ₹15.0 L Work partially Completed · 26 Feb 2026Rec. 16 Mar 2024Paid ₹15.0 L
  • Ambernath Municipal Council Area Reservation No. 125 Construction of new up-to-date gymnasium and other construction works at Gawdevi Gymnasium.

    Sports & fitnessInstallation of multi-gym equipment· Thane· #130611

    ₹15.0 L Work partially Completed · 20 Jan 2026Rec. 16 Mar 2024Paid ₹14.9 L
  • Construction of Gaon Devi Gymnasium and other construction works in reservation no.125, Ambernath Municipal Council Area

    Sports & fitnessConstruction of buildings for multi-gym· Thane· #165328

    ₹15.0 L Work partially Completed · 20 Jan 2026Rec. 14 Jan 2024Paid ₹14.9 L
  • Construction of Senior Citizen Katta and Open Gym at Dombivli East Khandkar Galli, Tilaknagar, Dombivli East in Kalyan Dombivli Municipal Corporation area.

    Sports & fitnessConstruction of buildings for multi-gym· Thane· #165325

    ₹5.0 L Work partially Completed · 5 Aug 2025Rec. 14 Jan 2024Paid ₹4.5 L
  • Open gym and construction work in premises adjacent to Kalyan East 60 feet road in Kalyan Dombivli Municipal Corporation area.

    Sports & fitnessInstallation of multi-gym equipment· Thane· #165326

    ₹5.0 L Work partially Completed · 5 Aug 2025Rec. 14 Jan 2024Paid ₹5.0 L
  • Kalyan Dombivli Municipal Corporation Area Ward No. Construction of drain and laying of culvert near 104 Sangeeta Colony - Main Road - Mahesh Apartment

    Sanitation & drainageProviding drains and gutters for public drainage· Thane· #130548

    ₹12.5 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹12.5 L
  • Kalyan Dombivli Municipal Corporation Area Dombivli East on Gymkhana Road ST. Construction of public toilet in Agar.

    Sanitation & drainageConstruction of public toilets and bathrooms· Thane· #130563

    ₹12.5 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹12.5 L
  • Repairing and providing new equipment to the gymnasium in Savalaram Maharaj Sports Complex at Dombivli East in Kalyan Dombivli Municipal Corporation area.

    Sports & fitnessProviding sports equipment, except consumable items· Thane· #130602

    ₹12.5 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹12.5 L
  • Renovation and beautification of Tilaknagar Rest Park adjacent to Manav Kalyan Hospital in Dombivli East in Kalyan Dombivli Municipal Corporation area.

    Community buildings & public spacesDevelopment of public parks· Thane· #130638

    ₹9.9 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹9.9 L
  • Beautification of Dombivli Pisavli Lake in Kalyan Dombivli Municipal Corporation area.

    Irrigation, flood & environmentRenovation of ponds and lakes· Thane· #130658

    ₹29.9 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹29.9 L
  • Installation of paver blocks and benches in the area of ??Dhanashree Pratham Society, Nandivali Hill, Dombivali East, Kalyan Dombivali Municipal Corporation.

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Thane· #130666

    ₹10.0 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹10.0 L
  • Concreting of sewer and road from Om Annapurna Ashish Society to Datta Mandir at Ghanshyam Gupte Road Galli No.03 of Dombivli Ward No.60.

    Roads & bridgesConstruction of roads, link roads, pathways or any other road with or without drainage system· Thane· #130670

    ₹29.7 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹29.7 L
  • Kalyan Dombivli Municipal Corporation Area Q. No. 65 Installation of open gym in Gadevi Mandir area at Kopargaon.

    Sports & fitnessInstallation of multi-gym equipment· Thane· #130718

    ₹5.6 L Completed 3 Jun 2025Rec. 16 Mar 2024Paid ₹5.6 L

17th Lok Sabha MPs from Maharashtra

Ranked by MP score

#MPUtilisationSpentCompletedScore
1Unmesh Bhaiyyasaheb Patil · Jalgaon99%98%17999
2Sudhakar Tukaram Shrangre · Latur96%96%10699
3Bharti Pravin Pawar · Dindori96%94%16097
4Dhairyasheel Sambhajirao Mane · Hatkanangle98%92%15196
5Sanjay(Kaka) Ramchandra Patil · Sangli94%88%14894
6Sanjay Sadashivrao Mandlik · Kolhapur99%88%9394
7Ramdas Chandrabhanji Tadas · Wardha99%96%19594
8Ashok Mahadeorao Nete · Gadchiroli-Chimur99%88%8392
9Hemant Shriram Patil · Hingoli98%83%9392
10Nitin Jairam Gadkari · Nagpur100%67%3691
11Prataprao Govindrao Patil Chikhalikar · Nanded99%84%11991
12Sanjay Haribhau Jadhav · Parbhani98%96%11291

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.