Skip to content
MPLADSTracker
This is a record from the 17th Lok Sabha (2019–24). eSAKSHI covers its final year only, from April 2023. Comparisons are with other 17th Lok Sabha MPs.

MPLADS report card · 17th Lok Sabha

Smt Preneet Kaur

Lok SabhaPatiala · Punjab

MP score85/100267th of 539 in the 17th Lok Sabha
9th of 13 from Punjab

Allocated limit

₹9.87 Cr

Median ₹8.60 Cr

Fund utilisation

96%

₹9.48 Cr recommended · 220 works
About the median

Paid to vendors

₹8.89 Cr

90% of allocation
About the median

Works completed

161

73% of recommended
Below median (83%)

From recommendation to completion

Every work this MP recommended, by stage

  1. Recommended by the MP220 works

    ₹9.48 Cr · 96% of the ₹9.87 Cr allocated

  2. Sanctioned by the district220 works

    100% sanctioned · took 42 days on average (due within 45 days)

  3. Completed161 works

    ₹6.96 Cr final cost · 17.1 months from recommendation on average

In plain words

What the numbers say

  • Recommended 220 works worth ₹9.48 Cr, a fund utilisation of 96%, higher than 37% of 17th Lok Sabha MPs.
  • The district has sanctioned 220 of them, taking 42 days on average.
  • ₹8.89 Cr has been paid to vendors, 90% of the allocation.
  • 161 works are complete, typically 17.1 months after recommendation. 152 works have geo-tagged photos on eSAKSHI.
  • The largest share of funds went to Community buildings & public spaces.
  • Payments went to 444 vendors. The largest received 5.1%.
  • No citizen ratings have been reported for completed works.

How the score is made

MP score 85/100: finishing works counts most

  1. Works completed 30%73Completed ÷ recommended works.
  2. Spending efficiency 20%78Value of completed works ÷ money paid out. Money paid without works finished scores low.
  3. Fund utilisation 15%96Value of works recommended ÷ allocated limit (MoSPI’s measure).
  4. Proof of work 15%94Share of completed works with photos or documents uploaded on eSAKSHI.
  5. Funds spent 10%90Paid to vendors ÷ allocated limit.
  6. Vendor diversity 10%
    i

    Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.

    100
    How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.

Largest vendor: Vinod Kumar Garg, 5.1% of payments across 444 vendors.

District sanction speed

100/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank

  1. Sanction speed 100%100Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.

Activity over time

Recommendations, payments and completions by month

Value of works MPs recommended each month

Who got paid

Top vendors by payments received

Implementing district authorities

The districts that sanction and execute this MP’s works

Works

220 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI

Open in explorer
  • Construction of SC Community Centre at village Pipal Mangholi (376) block Ghanaur (Patiala)

    Community buildings & public spacesConstruction of community centers and community halls· Patiala· #111996

    ₹5.0 L Completed 13 Oct 2026Rec. 22 Feb 2024Paid ₹5.0 L
  • Construction of shelter for cows at Nabha Gaushala located at Village Bir Dosanjhan (207) block & tehsil Nabha (Patiala)

    Agriculture & animal careConstruction of shelters for animals· Patiala· #84758

    ₹4.9 L Completed 12 Oct 2026Rec. 19 Jan 2024Paid ₹4.9 L
  • Construction of shed in cremation ground at village Nanhera (145) block Shambhu Kalan (Patiala)

    Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Patiala· #85184

    ₹2.5 L Completed 26 Sept 2026Rec. 19 Jan 2024Paid ₹2.5 L
  • Construction of boundary wall of dispensary at village Nanhera Khurd (145) block Shambhu Kalan (Patiala)

    HealthConstruction of veterinary hospitals and dispensaries· Patiala· #85183

    ₹2.5 L Completed 23 Sept 2026Rec. 19 Jan 2024Paid ₹2.5 L
  • Construction of Room in Anganwadi Centre at Village Dakala

    Education & librariesConstruction of buildings for crèches and anganwadies· Patiala· #5368

    ₹1.5 L Completed 21 Sept 2026Rec. 22 Jul 2023Paid ₹1.5 L
  • Construction of SC Community Centre at village Badshahpur (188) block Samana (Patiala)

    Community buildings & public spacesConstruction of community centers and community halls· Patiala· #60448

    ₹5.0 L Completed 12 Aug 2026Rec. 12 Dec 2023Paid ₹5.0 L
  • Construction of street/drain/gutters at village Paidan (356) block Patiala Rural (Patiala) from h/o Ajaib Singh s/o Siria Singh to h/o Bawa Singh s/o Hari Dhan and Satwant Singh s/o Kartar Singh

    Sanitation & drainageProviding drains and gutters for public drainage· Patiala· #37752

    ₹4.0 L Completed 7 May 2026Rec. 17 Oct 2023Paid ₹4.0 L
  • Community shed at village Premsingh wala block Samana

    Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Patiala· #6981

    ₹2.0 L Completed 16 Mar 2026Rec. 29 Jul 2023Paid ₹2.0 L
  • Construction of street/drain/gutters at village Alipur Jattan (193), blocck Sanour (Patiala) from main road to Govt. Elementary School

    Sanitation & drainageProviding drains and gutters for public drainage· Patiala· #37330

    ₹5.3 L Completed 20 Feb 2026Rec. 16 Oct 2023Paid ₹5.3 L
  • Construction of boundary wall and shed in cremation ground at village Kartarpur (119) (Abadi Kartarpur) block Sanour (Patiala)

    Community buildings & public spacesCrematoriums / Energy efficient crematoriums or structures on burial / cremation ground· Patiala· #41898

    ₹5.0 L Completed 20 Feb 2026Rec. 30 Oct 2023Paid ₹5.0 L
  • Construction of streets with drain/gutters at Village Sauja (46) block Nabha (Patiala)

    Sanitation & drainageProviding drains and gutters for public drainage· Patiala· #46267

    ₹3.5 L Completed 18 Feb 2026Rec. 6 Nov 2023Paid ₹3.5 L
  • Construction street with drain/gutter from h/o Chitwant Singh to h/o Surinder Singh

    Sanitation & drainageProviding drains and gutters for public drainage· Patiala· #40782

    ₹5.5 L Completed 17 Feb 2026Rec. 26 Oct 2023Paid ₹5.5 L
  • Construction of building village Panchayat House in village Bhat Heri (92) blocck Sanour (Patiala)

    Safety & securityConstruction of Government office buildings (Post office, Police station, Police chauki, etc.)· Patiala· #41160

    ₹3.0 L Completed 12 Feb 2026Rec. 27 Oct 2023Paid ₹3.0 L
  • Construction of street with drain/gutter at village Panaudian (90) block Sanour (Patiala) from h/o Sewa Singh to h/o Paramjit Singh

    Sanitation & drainageProviding drains and gutters for public drainage· Patiala· #41167

    ₹3.0 L Completed 12 Feb 2026Rec. 27 Oct 2023Paid ₹3.0 L
  • Construction of boundary wall, kitchen shed and laying of pipe line in Govt. Elementary School Village Lalina block Sanour (Patiala)

    Education & librariesConstruction of rooms and halls in school and colleges· Patiala· #22883

    ₹4.1 L Completed 6 Feb 2026Rec. 19 Sep 2023Paid ₹4.1 L

17th Lok Sabha MPs from Punjab

Ranked by MP score

#MPUtilisationSpentCompletedScore
1Smt Harsimrat Kaur Badal · Bhatinda99%98%21695
2Mohammad Sadique · Faridkot100%100%22295
3Sardar Simranjit Singh Mann · Sangrur97%97%51192
4Shri Amar Singh · Fatehgarh Sahib95%90%30888
5Sushil Kumar Rinku · Jalandhar95%89%8788
6Ravneet Singh · Ludhiana93%91%31388
7Sukhbir Singh Badal · Firozpur94%94%24686
8Manish Tewari · Anandpur Sahib94%88%21686
9Smt Preneet Kaur · Patiala96%90%16185
10Shri Som Prakash · Hoshiarpur92%85%35581
11Shri Gurjeet Singh Aujla · Amritsar95%95%12280
12Shri Sunny Deol · Gurdaspur92%78%16080

Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.