Allocated limit
₹16.75 Cr
Median ₹14.70 Cr
Fund utilisation
72%
₹11.99 Cr recommended · 225 works
Below median (76%)
Paid to vendors
₹6.92 Cr
41% of allocation
Above median (37%)
Works completed
92
41% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP225 works
₹11.99 Cr · 72% of the ₹16.75 Cr allocated
- Sanctioned by the district169 works
75% sanctioned · took 4.4 months on average (due within 45 days)
- Completed92 works
₹4.59 Cr final cost · 7.8 months from recommendation on average
56 works are still awaiting sanction, 56 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 225 works worth ₹11.99 Cr, a fund utilisation of 72%, higher than 42% of 18th Lok Sabha MPs.
- The district has sanctioned 169 of them, taking 4.4 months on average.
- ₹6.92 Cr has been paid to vendors, 41% of the allocation.
- 92 works are complete, typically 7.8 months after recommendation. 90 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 102 vendors. The largest received 11%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 65/100: finishing works counts most
- Works completed 30%41Completed ÷ recommended works.
- Spending efficiency 20%66Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%72Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%98Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%41Paid to vendors ÷ allocated limit.
- Vendor diversity 10%100How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Chairman Nirmithi Kendra Bagalkot, 11% of payments across 102 vendors.
District sanction speed
74/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%74Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
225 works · the 60 most recent are listed here, all of them in the explorer · tap “Photos” to see geo-tagged photos from eSAKSHI
Construction of Community Hall in CHIKKA HANDIGOL Village Property No.401-1
Community buildings & public spacesConstruction of community centers and community halls· Gadag· #179411
₹5.0 L Completed 25 Aug 2026Rec. 12 Mar 2025Paid ₹5.0 LConstruction of College Building of KES Samyukta Padavi Purva College Konnur
Education & librariesConstruction of rooms and halls in school and colleges· Gadag· #244777
₹5.0 L Completed 25 Aug 2026Rec. 30 Oct 2025Paid ₹5.0 LConstruction of Community Hall in BALAGANUR Village, Property No.212A
Community buildings & public spacesConstruction of community centers and community halls· Gadag· #179412
₹5.0 L Completed 24 Aug 2026Rec. 12 Mar 2025Paid ₹5.0 LConstruction of Community Hall in RAMPUR Village Property No.133
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #188580
₹5.0 L Sanctioned · 13 Aug 2026Rec. 1 Apr 2025Construction of Community Hall in SHIVAPUR Village, Property No.72-A -YARAGOPPA SB
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #213796
₹5.0 L Work partially Completed · 13 Aug 2026Rec. 16 Jul 2025Paid ₹3.8 LConstruction of Gym Hall in HEBBALLI Village Property No.228
Sports & fitnessConstruction of buildings for multi-gym· Bagalkote· #300586
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in KARADIGUDD S.N. Village Property No.126
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300587
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in NEERALAKERI Village Property No.654
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300588
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in HANAMASAGAR Village Property No.02
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300589
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in THAMINAL Village Property No.252
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300592
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in DHANAKASHIRUR Village Property No.303-A
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300593
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in HIRENASABI Village Property No.19
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300594
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in SOMANAKOPPA Village Property No.211-B
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300595
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in BELAVALAKOPPA Village Property No.51-B
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300596
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026Construction of Community Hall in HULYAL Village Property No.442
Community buildings & public spacesConstruction of community centers and community halls· Bagalkote· #300962
₹5.0 L Awaiting sanction · 87 daysRec. 6 Aug 2026
18th Lok Sabha MPs from Karnataka
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Parvatagouda Chandanagouda Gaddigoudar · Bagalkot | 72% | 41% | 92 | 65 |
| 2 | Captain Brijesh Chowta · Dakshina Kannada | 65% | 39% | 83 | 63 |
| 3 | K. Rajashekar Basavaraj Hitnal · Koppal | 90% | 47% | 68 | 62 |
| 4 | Dr C N Manjunath · Bangalore Rural | 92% | 46% | 75 | 57 |
| 5 | Kota Srinivas Poojary · Udupi Chikmagalur | 95% | 37% | 53 | 55 |
| 6 | Shreyas. M. Patel · Hassan | 89% | 46% | 59 | 54 |
| 7 | Ramesh Chandappa Jigajinagi · Bijapur | 75% | 10% | 55 | 54 |
| 8 | Sunil Bose · Chamarajanagar | 62% | 37% | 28 | 52 |
| 9 | Yaduveer Krishnadatta Chamaraja Wadiyar · Mysore | 79% | 45% | 48 | 52 |
| 10 | Shobha Karandlaje · Bangalore North | 85% | 45% | 30 | 51 |
| 11 | Shri B Y Raghavendra · Shimoga | 99% | 51% | 49 | 50 |
| 12 | Priyanka Satish Jarkiholi · Chikkodi | 87% | 20% | 16 | 50 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.