1st of 2 from Tripura
Allocated limit
₹14.70 Cr
Median ₹14.70 Cr
Fund utilisation
68%
₹9.97 Cr recommended · 45 works
Below median (76%)
Paid to vendors
₹4.29 Cr
29% of allocation
Below median (37%)
Works completed
18
40% of recommended
Above median (28%)
From recommendation to completion
Every work this MP recommended, by stage
- Recommended by the MP45 works
₹9.97 Cr · 68% of the ₹14.70 Cr allocated
- Sanctioned by the district35 works
78% sanctioned · took 5.4 months on average (due within 45 days)
- Completed18 works
₹2.25 Cr final cost · 11.6 months from recommendation on average
10 works are still awaiting sanction, 7 of them for more than 45 days.
In plain words
What the numbers say
- Recommended 45 works worth ₹9.97 Cr, a fund utilisation of 68%, higher than 36% of 18th Lok Sabha MPs.
- The district has sanctioned 35 of them, taking 5.4 months on average.
- ₹4.29 Cr has been paid to vendors, 29% of the allocation.
- 18 works are complete, typically 11.6 months after recommendation. 18 works have geo-tagged photos on eSAKSHI.
- The largest share of funds went to Community buildings & public spaces.
- Payments went to 6 vendors. The largest received 30%.
- No citizen ratings have been reported for completed works.
How the score is made
MP score 59/100: finishing works counts most
- Works completed 30%40Completed ÷ recommended works.
- Spending efficiency 20%52Value of completed works ÷ money paid out. Money paid without works finished scores low.
- Fund utilisation 15%68Value of works recommended ÷ allocated limit (MoSPI’s measure).
- Proof of work 15%100Share of completed works with photos or documents uploaded on eSAKSHI.
- Funds spent 10%29Paid to vendors ÷ allocated limit.
- Vendor diversity 10%87How spread out payments are: full marks when no vendor gets over 20% of the money, none when one vendor gets everything.
i
Members of Parliament (MPs) do not have direct, operational control over the specific vendors selected for government public works. However, they exert significant indirect influence by shaping procurement frameworks, passing supplier diversity laws, and conducting oversight.
Largest vendor: Senior Deputy Magistrate Khowai, 30% of payments across 6 vendors.
District sanction speed
73/100 · sanction is the district authority’s job, so this doesn’t change the MP’s rank
- Sanction speed 100%73Average days to sanction (full marks within the 45-day guideline, none at a year), and the share of works not overdue.
Activity over time
Recommendations, payments and completions by month
Sectors
Value of works by category
Who got paid
Top vendors by payments received
Implementing district authorities
The districts that sanction and execute this MP’s works
Works
45 works · tap “Photos” to see geo-tagged photos from eSAKSHI
Procurement of water tankers
Drinking waterPurchase of mobile water tankers· North Tripura· #322377
₹24.0 L Awaiting sanction · 18 daysRec. 14 Oct 2026Construstion of Market Shed
Community buildings & public spacesConstruction of community centers and community halls· Khowai· #322392
₹10.0 L Awaiting sanction · 18 daysRec. 14 Oct 2026solar street lights
Electricity & lightingStreet lights· Dhalai· #254548
₹1.00 Cr Vendor Identification · 9 Oct 2026Rec. 17 Dec 2025Paid ₹100.0 LRenovation of Niranjan Hati under Twikarma VC
Community buildings & public spacesConstruction of common work sheds / common covered sitting area· Khowai· #321074
₹10.0 L Awaiting sanction · 24 daysRec. 8 Oct 2026BUS SHED, BUS STOP WITH BEAUTIFICATION
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Khowai· #241590
₹20.0 L Completed 16 Sept 2026Rec. 11 Oct 2025Paid ₹20.0 LCONSTRUCTION OF BUS SHEDS
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Khowai· #244259
₹20.0 L Completed 16 Sept 2026Rec. 28 Oct 2025Paid ₹20.0 LCONSTRUCTION OF BUS SHEDS
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Khowai· #244260
₹20.0 L Completed 16 Sept 2026Rec. 28 Oct 2025Paid ₹20.0 LBus shade,Bus stop, with beutification.
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Khowai· #219206
₹20.0 L Completed 15 Sept 2026Rec. 17 Jul 2025Paid ₹20.0 LCONSTRUCTION OF BUS SHEDS
Community buildings & public spacesConstruction of bus-sheds or bus-stops· Khowai· #244261
₹20.0 L Completed 15 Sept 2026Rec. 28 Oct 2025Paid ₹20.0 LSupply of Customized joined benches along with modernization of science lab.
Education & librariesPurchase of furniture and fixtures for educational purposes· South Tripura· #297399
₹1.00 Cr Sanctioned · 14 Sept 2026Rec. 21 Jul 2026Supply, Installation and commissioning of Solar Outdoor Lighting Systems with Civil work and Boundary work
Electricity & lightingLighting of public spaces· Dhalai· #301145
₹1.00 Cr Awaiting sanction · 89 daysRec. 4 Aug 2026Solar High Mast Lighting Octagonal Tower with Solar based LED Street Lights ( Q3)
Electricity & lightingLighting of public spaces· South Tripura· #273891
₹10.0 L Sanctioned · 24 Jul 2026Rec. 12 Mar 2026Solar High Mast Lighting Octagonal Tower with Solar based LED Street Lights ( Q3)
Electricity & lightingLighting of public spaces· South Tripura· #273892
₹10.0 L Sanctioned · 24 Jul 2026Rec. 12 Mar 2026Solar High Mast Lighting Octagonal Tower with Solar based LED Street Lights ( Q3)
Electricity & lightingLighting of public spaces· South Tripura· #273893
₹10.0 L Sanctioned · 24 Jul 2026Rec. 12 Mar 2026Solar High Mast Lighting Octagonal Tower with Solar based LED Street Lights ( Q3)
Electricity & lightingLighting of public spaces· South Tripura· #273894
₹10.0 L Sanctioned · 24 Jul 2026Rec. 12 Mar 2026
18th Lok Sabha MPs from Tripura
Ranked by MP score
| # | MP | Utilisation | Spent | Completed | Score |
|---|---|---|---|---|---|
| 1 | Kriti Devi Debbarman · Tripura East | 68% | 29% | 18 | 59 |
| 2 | Biplab Kumar Deb · Tripura West | 78% | 42% | 7 | 53 |
Source: MoSPI eSAKSHI (eSAKSHI API (mplads.mospi.gov.in)). Fund utilisation = works recommended ÷ allocated limit (MoSPI’s definition); spent = vendor payments ÷ allocated limit; completion = completed ÷ recommended works. The MP score weighs completion, spending efficiency, utilisation, proof of work, spending and vendor diversity. How it’s calculated.